Bid Tabulations for the Letting of 10/21/2020 LA DOTD Headquarters

Proposal:H.013546.6
Parish:East Baton Rouge
Description:THIBODEAUX ROAD IMPROVEMENTS
Type Construction:GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, LIME TREATMENT, IN-PLACE CEMENT TREATED BASE COURSE, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,216,056.35
Rank License BidderConstruction Bid
112031R.J. Daigle & Sons Contractors, Inc$940,352.23
200046Barber Bros. Contracting Co., L.L.C$1,048,471.15
306276Barriere Construction Co., LLC$1,072,931.87
444013M. Trak, LLC$1,279,097.97


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
R.J. Daigle & Sons Contractors, Inc
- 2 -
Barber Bros. Contracting Co., L.L.C
- 3 -
Barriere Construction Co., LLC
- 4 -
M. Trak, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-06100Removal of Concrete Walks and Drives 99     SQYD9.70960.3020.001,980.000.010.9925.002,475.00
0002202-02-32100Removal of Pipe (Cross Drain) (30" and 60")132     LNFT21.822,880.2430.003,960.0055.007,260.0035.004,620.00
0003202-02-38240Removal of Signs and Supports 30     EACH42.001,260.0010.00300.0026.00780.0025.00750.00
0004203-01-00100General Excavation 90     CUYD38.403,456.0025.002,250.0035.003,150.0025.002,250.00
0005203-07-00100Borrow (Vehicular Measurement) 1,845     CUYD25.8747,730.1530.0055,350.005.009,225.0022.0040,590.00
0006203-10-00100Cleaning Existing Ditches 3,198     LNFT5.9719,092.067.0022,386.009.0028,782.008.0025,584.00
0007204-05-00100Temporary Sediment Check Dams (Hay) 15     EACH154.722,320.80100.001,500.00155.002,325.0050.00750.00
0008204-06-00100Temporary Silt Fencing 7,259     LNFT1.7412,630.661.5010,888.501.4510,525.553.0021,777.00
0010304-01-00100Lime 259.78  TON247.3864,264.38215.0055,852.701.00259.78225.0058,450.50
0011304-05-00100Lime Treatment (Type E) 18,327     SQYD1.2222,358.941.2522,908.751.0018,327.004.0073,308.00
0012402-01-00100Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 30.1   CUYD31.89959.8950.001,505.00100.003,010.0010.00301.00
0013502-01-00100Asphalt Concrete 3,330.4   TON75.94252,910.5880.00266,432.00100.00333,040.00100.00333,040.00
0014502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 175.2   TON60.0010,512.00130.0022,776.00150.0026,280.00125.0021,900.00
0015507-01-00100Asphalt Material (CRS-2P Emulsion) 7,148     GAL5.2737,669.964.9535,382.603.5025,018.005.0035,740.00
0016507-02-00200Aggregate (S2) 18,327     SQYD1.9335,371.111.8032,988.601.5027,490.502.0036,654.00
0017507-02-00300Aggregate (S3) 18,327     SQYD1.6730,606.091.6029,323.201.5027,490.501.6530,239.55
0018509-01-00100Milling Asphalt Pavement 14,666     SQYD1.9528,598.702.0029,332.002.5036,665.002.2532,998.50
0019509-02-00100Contractor Retained Reclaimed Asphalt Pavement -611     CUYD0.01-6.110.000.001.00-611.000.01-6.11
0020701-01-01120Cross Drain Pipe (60" RCP) 50     LNFT400.7920,039.50350.0017,500.00500.0025,000.00410.0020,500.00
0021701-01-02220Cross Drain Pipe (60" RCP or 72" CMP) 42     LNFT446.8218,766.44400.0016,800.00500.0021,000.001,000.0042,000.00
0022701-02-02040Cross Drain Pipe Arch (30" Equiv. RCPA or 36" Equiv. CMPA) 80     LNFT154.5212,361.60140.0011,200.00350.0028,000.00155.0012,400.00
0023701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 92     LNFT14.631,345.965.00460.003.00276.0045.004,140.00
0024711-01-04000Riprap (55 lb, 18" Thick) 18     SQYD51.70930.60145.002,610.00180.003,240.00150.002,700.00
0025711-01-05000Riprap (130 lb, 24" Thick) 100     SQYD64.936,493.00200.0020,000.00180.0018,000.0075.007,500.00
0026711-04-00100Geotextile Fabric 118     SQYD1.68198.243.00354.003.50413.002.50295.00
0027713-01-00100Temporary Signs and Barricades 1     LUMP15,000.0015,000.0065,000.0065,000.0080,000.0080,000.0025,000.0025,000.00
0028713-02-00100Temporary Pavement Markings (4" Width) 21,777     LNFT0.286,097.560.255,444.250.5010,888.500.306,533.10
0029713-02-00500Temporary Pavement Markings (24" Width) 22     LNFT11.00242.0010.00220.0011.00242.001.0022.00
0030713-11-00100Portable Changeable Message Signs 2     EACH1,200.002,400.001,000.002,000.003,500.007,000.001,000.002,000.00
0031726-01-00100Bedding Material 68.8   CUYD85.225,863.1460.004,128.0025.001,720.00125.008,600.00
0032727-01-00100Mobilization 1     LUMP62,500.0062,500.0090,000.0090,000.0055,000.0055,000.00125,000.00125,000.00
0033729-01-00100Sign (Type A) 267.3   SQFT22.005,880.6021.005,613.3020.005,346.0085.0022,720.50
0034729-02-00100Sign (Type B) 12     SQFT33.00396.0031.00372.0020.00240.0085.001,020.00
0035729-08-00100Mounting (2 1/2" Size Post) 2     EACH990.001,980.00930.001,860.001,500.003,000.00150.00300.00
0036729-08-00200Mounting (3 1/2" Size Post) 2     EACH1,210.002,420.001,135.002,270.001,500.003,000.00180.00360.00
0037729-16-00300Object Marker Assembly (Type 3) 6     EACH93.50561.0088.00528.00115.00690.0085.00510.00
0038729-22-00200Square Tubing Post with 2-1/4" Omni-Directional Anchor 36     EACH104.503,762.0098.003,528.00150.005,400.00150.005,400.00
0039731-02-00100Reflectorized Raised Pavement Markers 363     EACH8.252,994.757.752,813.258.002,904.007.502,722.50
0040732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 22     LNFT22.00484.0021.00462.0025.00550.00175.003,850.00
0041732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.84  MILE5,500.0010,120.005,160.009,494.406,000.0011,040.004,000.007,360.00
0042732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.91  MILE3,300.003,003.003,100.002,821.003,250.002,957.506,500.005,915.00
0043735-01-00100Mailboxes 61     EACH16.501,006.5015.50945.5010.00610.0015.00915.00
0044735-02-00100Mailbox Supports (Single) 61     EACH137.508,387.50125.007,625.00135.008,235.00115.007,015.00
0045739-01-00100Hydro-Seeding 1.95  ACRE2,212.964,315.271,250.002,437.502,000.003,900.002,500.004,875.00
0046740-01-00100Construction Layout 1     LUMP8,640.008,640.007,500.007,500.0012,500.0012,500.007,500.637,500.63
0047NS-300-00060Geogrid 92     SQYD3.52323.843.00276.008.00736.0025.002,300.00
0048NS-500-00340Saw Cutting Asphalt Concrete Pavement 711     INLF1.18838.981.00711.001.00711.002.001,422.00
0049NS-600-00220Saw Cutting Portland Cement Concrete Pavement 3,436     INLF1.224,191.921.003,436.001.254,295.002.006,872.00
0050303-01-00300In-Place Cement Stabilized Base Course (10" Thick) 18,327.4   SQYD8.47155,233.089.00164,946.6010.75197,019.5512.00219,928.80
             
  CONTRACTOR TOTAL   940,352.23 1,048,471.15 1,072,931.87 1,279,097.97