Bid Tabulations for the Letting of 10/21/2020 LA DOTD Headquarters

Proposal:H.009633.6
Parish:East Feliciana
Routes:LA 67
Description:LA 67: EBR P/L TO 8.0 MI NORTH OF EBR P/L
Type Construction:MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$5,902,137.79
Rank License BidderConstruction Bid
106276Barriere Construction Co., LLC$4,548,798.13
212031R.J. Daigle & Sons Contractors, Inc$4,598,824.27
312487Diamond B Construction Co., L.L.C.$4,777,542.15
400046Barber Bros. Contracting Co., L.L.C$4,957,205.74
569570Bridging The Gap Solution LLC$5,339,056.45


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barriere Construction Co., LLC
- 2 -
R.J. Daigle & Sons Contractors, Inc
- 3 -
Diamond B Construction Co., L.L.C.
- 4 -
Barber Bros. Contracting Co., L.L.C
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-14500Removal of Guard Rail 2,233.3   LNFT8.0017,866.408.8019,653.048.5519,094.728.3018,536.39
0002203-07-00100Borrow (Vehicular Measurement) 4,406     CUYD12.0052,872.0036.40160,378.4030.00132,180.0038.00167,428.00
0003204-05-00100Temporary Sediment Check Dams (Hay) 24     EACH125.003,000.00138.053,313.20125.003,000.00120.002,880.00
0004204-06-00100Temporary Silt Fencing 925     LNFT2.001,850.002.202,035.002.502,312.501.751,618.75
0005401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 250     CUYD1.00250.0037.729,430.0036.009,000.0050.0012,500.00
0006402-03-00100Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 250     CUYD12.003,000.0018.404,600.0048.0012,000.0040.0010,000.00
0007502-01-00100Asphalt Concrete 41,951.6   TON77.003,230,273.2078.333,286,068.8386.503,628,813.4080.003,356,128.00
0008502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 425.3   TON220.0093,566.00121.3951,627.17145.0061,668.50155.0065,921.50
0009509-01-00100Milling Asphalt Pavement 205,170     SQYD1.70348,789.002.01412,391.701.55318,013.502.00410,340.00
0010509-02-00100Contractor Retained Reclaimed Asphalt Pavement -7,353     CUYD0.01-73.530.01-73.531.00-7,353.000.000.00
0011510-01-00400Pavement Patching (24" Minimum Thickness) 500     SQYD160.0080,000.00146.8273,410.00150.0075,000.00135.0067,500.00
0012704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 1,284     LNFT32.0041,088.0035.2045,196.8033.0042,372.0033.0042,372.00
0013704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 575     LNFT22.0012,650.0024.2013,915.0023.0013,225.0023.0013,225.00
0014704-07-00200Guard Rail Transitions (Double Thrie Beam) 200     LNFT87.0017,400.0095.7019,140.0091.0018,200.0090.0018,000.00
0015704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 8     EACH2,500.0020,000.002,750.0022,000.002,625.0021,000.002,600.0020,800.00
0016707-04-00100Asphalt Curb 108     LNFT58.006,264.0010.001,080.0092.009,936.0040.004,320.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP265,000.00265,000.00142,600.00142,600.0052,000.0052,000.00250,000.00250,000.00
0018713-02-00500Temporary Pavement Markings (24" Width) 915     LNFT1.00915.000.17155.550.25228.750.15137.25
0019713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 24.118 MILE1.0024.1255.071,328.18154.003,714.17350.008,441.30
0020713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 13.988 MILE1.0013.99440.066,155.56415.005,805.02400.005,595.20
0021713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 41.954 MILE1.0041.95770.1132,309.19715.0029,997.11700.0029,367.80
0022724-01-00100Rumble Strips (Centerline) 8     MILE1,200.009,600.00286.002,288.001,350.0010,800.00275.002,200.00
0023724-02-00100Rumble Strips (Shoulder/Edge) 16     MILE1,000.0016,000.00286.004,576.001,350.0021,600.00275.004,400.00
0024727-01-00100Mobilization 1     LUMP180,000.00180,000.00116,000.00116,000.00145,000.00145,000.00300,000.00300,000.00
0025729-16-00200Object Marker Assembly (Type 2) 26     EACH48.001,248.0049.501,287.0050.001,300.0047.001,222.00
0026729-16-00300Object Marker Assembly (Type 3) 8     EACH76.00608.0082.50660.0085.00680.0077.00616.00
0027731-02-00100Reflectorized Raised Pavement Markers 1,517     EACH6.509,860.507.1510,846.557.0010,619.007.0010,619.00
0028732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 305     LNFT12.003,660.0013.204,026.0013.003,965.0012.503,812.50
0029732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 20.977 MILE3,800.0079,712.604,180.6087,696.453,975.0083,383.583,900.0081,810.30
0030732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 6.994 MILE850.005,944.90934.476,535.68850.005,944.90875.006,119.75
0031735-01-00100Mailboxes 137     EACH16.002,192.0016.502,260.501.00137.0015.002,055.00
0032735-02-00100Mailbox Supports (Single) 121     EACH122.0014,762.00132.0015,972.00145.0017,545.00120.0014,520.00
0033735-03-00100Mailbox Supports (Double) 8     EACH215.001,720.00236.501,892.00170.001,360.00215.001,720.00
0034739-01-00100Hydro-Seeding 2     ACRE1,850.003,700.002,035.004,070.002,000.004,000.001,500.003,000.00
0035740-01-00100Construction Layout 1     LUMP25,000.0025,000.0034,000.0034,000.0021,000.0021,000.0020,000.0020,000.00
             
  CONTRACTOR TOTAL   4,548,798.13 4,598,824.27 4,777,542.15 4,957,205.74



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
Bridging The Gap Solution LLC
Unit PriceTotal
Amount
0001202-02-14500Removal of Guard Rail 2,233.3   LNFT11.0024,566.30
0002203-07-00100Borrow (Vehicular Measurement) 4,406     CUYD35.00154,210.00
0003204-05-00100Temporary Sediment Check Dams (Hay) 24     EACH150.003,600.00
0004204-06-00100Temporary Silt Fencing 925     LNFT4.003,700.00
0005401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 250     CUYD50.0012,500.00
0006402-03-00100Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 250     CUYD100.0025,000.00
0007502-01-00100Asphalt Concrete 41,951.6   TON86.493,628,393.88
0008502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 425.3   TON175.0074,427.50
0009509-01-00100Milling Asphalt Pavement 205,170     SQYD2.10430,857.00
0010509-02-00100Contractor Retained Reclaimed Asphalt Pavement -7,353     CUYD0.01-73.53
0011510-01-00400Pavement Patching (24" Minimum Thickness) 500     SQYD100.0050,000.00
0012704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 1,284     LNFT40.0051,360.00
0013704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 575     LNFT30.0017,250.00
0014704-07-00200Guard Rail Transitions (Double Thrie Beam) 200     LNFT100.0020,000.00
0015704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 8     EACH3,300.0026,400.00
0016707-04-00100Asphalt Curb 108     LNFT125.0013,500.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP106,769.00106,769.00
0018713-02-00500Temporary Pavement Markings (24" Width) 915     LNFT6.005,490.00
0019713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 24.118 MILE425.0010,250.15
0020713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 13.988 MILE1,350.0018,883.80
0021713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 41.954 MILE1.0041.95
0022724-01-00100Rumble Strips (Centerline) 8     MILE885.007,080.00
0023724-02-00100Rumble Strips (Shoulder/Edge) 16     MILE885.0014,160.00
0024727-01-00100Mobilization 1     LUMP449,769.00449,769.00
0025729-16-00200Object Marker Assembly (Type 2) 26     EACH50.001,300.00
0026729-16-00300Object Marker Assembly (Type 3) 8     EACH100.00800.00
0027731-02-00100Reflectorized Raised Pavement Markers 1,517     EACH7.0010,619.00
0028732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 305     LNFT11.003,355.00
0029732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 20.977 MILE3,800.0079,712.60
0030732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 6.994 MILE2,200.0015,386.80
0031735-01-00100Mailboxes 137     EACH17.002,329.00
0032735-02-00100Mailbox Supports (Single) 121     EACH130.0015,730.00
0033735-03-00100Mailbox Supports (Double) 8     EACH240.001,920.00
0034739-01-00100Hydro-Seeding 2     ACRE5,000.0010,000.00
0035740-01-00100Construction Layout 1     LUMP49,769.0049,769.00
       
  CONTRACTOR TOTAL   5,339,056.45