Bid Tabulations for the Letting of 9/23/2020 LA DOTD Headquarters

Proposal:H.013739.6
Parish:Livingston
Routes:LA 63
Description:LA 63: LA 442 - LA 449
Type Construction:CLEARING AND GRUBBING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY AND RELATED WORK.
Estimated Construction Cost:$2,501,725.85
Rank License BidderConstruction Bid
106276Barriere Construction Co., LLC$2,054,829.70
269570Bridging The Gap Solution LLC$2,175,343.40
300046Barber Bros. Contracting Co., L.L.C$2,362,184.40
412031R.J. Daigle & Sons Contractors, Inc$2,393,699.92
512487Diamond B Construction Co., L.L.C.$2,417,244.36


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barriere Construction Co., LLC
- 2 -
Bridging The Gap Solution LLC
- 3 -
Barber Bros. Contracting Co., L.L.C
- 4 -
R.J. Daigle & Sons Contractors, Inc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1.5   LUMP35,000.0035,000.0010,000.0010,000.0060,000.0060,000.001,200.001,200.00
0002202-02-00020Removal of Existing Aggregate Shoulders1,642     SQYD2.003,284.005.008,210.0018.0029,556.004.497,372.58
0003202-02-14500Removal of Guard Rail 342     LNFT17.005,814.0015.005,130.0015.505,301.0012.654,326.30
0004202-02-32100Removal of Pipe (Cross Drain) 24" EQ CMPA359     LNFT11.003,949.0050.0017,950.0025.008,975.008.252,961.75
0005202-02-32100Removal of Pipe (Cross Drain) 36" EQ CMPA142     LNFT11.001,562.0050.007,100.0030.004,260.0010.451,483.90
0006202-02-38300Removal of Sign and U-Channel Post 4     EACH55.00220.00125.00500.0050.00200.0011.0044.00
0007203-07-00100Borrow (Vehicular Measurement) 293     CUYD55.0016,115.0035.0010,255.0050.0014,650.0026.407,735.20
0008203-10-00100Cleaning Existing Ditches 2,200     LNFT4.509,900.0015.0033,000.006.0013,200.004.9510,890.00
0009204-02-00100Temporary Hay Bales 144     EACH22.003,168.0010.001,440.0015.002,160.0017.182,473.92
0010204-05-00100Temporary Sediment Check Dams (Hay) 65     EACH125.008,125.00125.008,125.00100.006,500.00134.018,710.65
0011204-06-00100Temporary Silt Fencing 12,402     LNFT1.5018,603.003.0037,206.001.2515,502.501.5819,595.16
0012401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 1,916     CUYD10.0019,160.0020.0038,320.0042.0080,472.0013.6626,172.56
0013502-01-00100Asphalt Concrete 11,071.7   TON82.00907,879.4084.00930,022.8075.00830,377.5081.72904,779.32
0014502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 1,339.4   TON1.001,339.40125.00167,425.0080.00107,152.00110.21147,615.27
0015509-01-00100Milling Asphalt Pavement 56,543     SQYD2.00113,086.002.50141,357.503.00169,629.004.06229,564.58
0016509-02-00100Contractor Retained Reclaimed Asphalt Pavement -5,363     CUYD1.00-5,363.000.01-53.630.000.000.01-53.63
0017510-01-00300Pavement Patching (18" Minimum Thickness) 3,991.5   SQYD100.00399,150.00100.00399,150.00105.00419,107.50105.21419,945.72
0018701-02-02000Cross Drain Pipe Arch (24" Equiv. RCPA or 30" Equiv. CMPA) 372     LNFT155.0057,660.00200.0074,400.00110.0040,920.00222.2682,680.72
0019701-02-02080Cross Drain Pipe Arch (36" Equiv. RCPA or 42" Equiv. CMPA) 156     LNFT180.0028,080.00200.0031,200.00130.0020,280.00256.0139,937.56
0020701-10-01060Reinforced Concrete Pipe (Extension) (24") 4     LNFT210.00840.00500.002,000.00220.00880.00299.201,196.80
0021701-15-00100Concrete Collar 1     EACH3,500.003,500.002,500.002,500.001,600.001,600.001,375.001,375.00
0022701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 268     LNFT55.0014,740.0050.0013,400.001.00268.0018.705,011.60
0023704-01-01000Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 75     LNFT75.005,625.0070.005,250.0073.005,475.0038.502,887.50
0024704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 156     LNFT140.0021,840.00125.0019,500.00130.0020,280.00104.5016,302.00
0025704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 25     LNFT15.00375.0022.00550.0023.00575.0024.20605.00
0026704-10-00110Guard Rail End Treatment (Flared 18' - 9" Length) 1     EACH2,000.002,000.001,950.001,950.002,030.002,030.002,420.002,420.00
0027704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 2     EACH2,500.005,000.002,650.005,300.002,760.005,520.002,750.005,500.00
0028707-01-00100Concrete Curb 40.5   LNFT110.004,455.0065.002,632.5050.002,025.00101.334,103.87
0029713-01-00100Temporary Signs and Barricades 1     LUMP140,000.00140,000.0020,000.0020,000.00150,000.00150,000.0085,880.0085,880.00
0030713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 14.395 MILE300.004,318.50425.006,117.88200.002,879.0057.31824.98
0031713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 7.745 MILE800.006,196.00750.005,808.75300.002,323.50500.003,872.50
0032713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 18.242 MILE1,300.0023,714.601,250.0022,802.501,000.0018,242.001,000.0018,242.00
0033713-11-00100Portable Changeable Message Signs 2     EACH2,800.005,600.005,000.0010,000.005,000.0010,000.004,675.009,350.00
0034726-01-00100Bedding Material 104.3   CUYD110.0011,473.001.00104.3066.006,883.8066.006,883.80
0035727-01-00100Mobilization 1     LUMP70,000.0070,000.0015,000.0015,000.00200,000.00200,000.00185,000.00185,000.00
0036729-16-00200Object Marker Assembly (Type 2) 22     EACH75.001,650.0065.001,430.0047.001,034.0055.001,210.00
0037729-16-00300Object Marker Assembly (Type 3) 4     EACH75.00300.0075.00300.0078.00312.00104.50418.00
0038731-02-00100Reflectorized Raised Pavement Markers 1,269     EACH8.0010,152.007.509,517.508.0010,152.008.2510,469.25
0039732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 6.081 MILE4,500.0027,364.504,500.0027,364.504,000.0024,324.005,000.0030,405.00
0040732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.582 MILE1,400.003,614.801,650.004,260.301,500.003,873.002,000.005,164.00
0041735-01-00100Mailboxes 133     EACH15.001,995.0015.001,995.0015.001,995.005.50731.50
0042735-02-00100Mailbox Supports (Single) 133     EACH125.0016,625.00130.0017,290.00115.0015,295.00154.0020,482.00
0043739-01-00100Hydro-Seeding 5.813 ACRE1,500.008,719.502,500.0014,532.501,200.006,975.601,501.738,729.56
0044740-01-00100Construction Layout 1     LUMP10,000.0010,000.0015,000.0015,000.0015,000.0015,000.0025,000.0025,000.00
0045NS-700-00830Impact Attenuator (Reusable, Test Level 2) 1     EACH28,000.0028,000.0030,000.0030,000.0026,000.0026,000.0024,200.0024,200.00
             
  CONTRACTOR TOTAL   2,054,829.70 2,175,343.40 2,362,184.40 2,393,699.92



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
Diamond B Construction Co., L.L.C.
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1.5   LUMP22,000.0022,000.00
0002202-02-00020Removal of Existing Aggregate Shoulders1,642     SQYD7.0011,494.00
0003202-02-14500Removal of Guard Rail 342     LNFT14.004,788.00
0004202-02-32100Removal of Pipe (Cross Drain) 24" EQ CMPA359     LNFT20.007,180.00
0005202-02-32100Removal of Pipe (Cross Drain) 36" EQ CMPA142     LNFT30.004,260.00
0006202-02-38300Removal of Sign and U-Channel Post 4     EACH0.502.00
0007203-07-00100Borrow (Vehicular Measurement) 293     CUYD13.003,809.00
0008203-10-00100Cleaning Existing Ditches 2,200     LNFT6.0013,200.00
0009204-02-00100Temporary Hay Bales 144     EACH25.003,600.00
0010204-05-00100Temporary Sediment Check Dams (Hay) 65     EACH135.008,775.00
0011204-06-00100Temporary Silt Fencing 12,402     LNFT1.9924,679.98
0012401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 1,916     CUYD71.00136,036.00
0013502-01-00100Asphalt Concrete 11,071.7   TON81.00896,807.70
0014502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 1,339.4   TON145.00194,213.00
0015509-01-00100Milling Asphalt Pavement 56,543     SQYD3.15178,110.45
0016509-02-00100Contractor Retained Reclaimed Asphalt Pavement -5,363     CUYD1.00-5,363.00
0017510-01-00300Pavement Patching (18" Minimum Thickness) 3,991.5   SQYD109.00435,073.50
0018701-02-02000Cross Drain Pipe Arch (24" Equiv. RCPA or 30" Equiv. CMPA) 372     LNFT230.0085,560.00
0019701-02-02080Cross Drain Pipe Arch (36" Equiv. RCPA or 42" Equiv. CMPA) 156     LNFT250.0039,000.00
0020701-10-01060Reinforced Concrete Pipe (Extension) (24") 4     LNFT600.002,400.00
0021701-15-00100Concrete Collar 1     EACH920.00920.00
0022701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 268     LNFT5.001,340.00
0023704-01-01000Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 75     LNFT60.004,500.00
0024704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 156     LNFT87.0013,572.00
0025704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 25     LNFT32.00800.00
0026704-10-00110Guard Rail End Treatment (Flared 18' - 9" Length) 1     EACH3,100.003,100.00
0027704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 2     EACH3,445.006,890.00
0028707-01-00100Concrete Curb 40.5   LNFT56.002,268.00
0029713-01-00100Temporary Signs and Barricades 1     LUMP43,000.0043,000.00
0030713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 14.395 MILE154.002,216.83
0031713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 7.745 MILE750.005,808.75
0032713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 18.242 MILE1,250.0022,802.50
0033713-11-00100Portable Changeable Message Signs 2     EACH2,400.004,800.00
0034726-01-00100Bedding Material 104.3   CUYD55.005,736.50
0035727-01-00100Mobilization 1     LUMP127,000.00127,000.00
0036729-16-00200Object Marker Assembly (Type 2) 22     EACH97.002,134.00
0037729-16-00300Object Marker Assembly (Type 3) 4     EACH105.00420.00
0038731-02-00100Reflectorized Raised Pavement Markers 1,269     EACH8.0010,152.00
0039732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 6.081 MILE4,150.0025,236.15
0040732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.582 MILE1,500.003,873.00
0041735-01-00100Mailboxes 133     EACH1.00133.00
0042735-02-00100Mailbox Supports (Single) 133     EACH130.0017,290.00
0043739-01-00100Hydro-Seeding 5.813 ACRE2,000.0011,626.00
0044740-01-00100Construction Layout 1     LUMP9,500.009,500.00
0045NS-700-00830Impact Attenuator (Reusable, Test Level 2) 1     EACH26,500.0026,500.00
       
  CONTRACTOR TOTAL   2,417,244.36