Bid Tabulations for the Letting of 8/12/2020 LA DOTD Headquarters

Proposal:H.013798.6
Parish:Ouachita
Description:HARRELL ROAD (US 80 - ARKANSAS RD)
Type Construction:CLEARING AND GRUBBING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,687,049.50
Rank License BidderConstruction Bid
105789D & J CONSTRUCTION CO., LLC$1,430,955.75
212312GILCHRIST CONSTRUCTION CO. LLC$1,753,519.26
312487Diamond B Construction Co., L.L.C.$1,820,972.68
415099Amethyst Construction, Inc.$1,822,228.95


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
D & J CONSTRUCTION CO., LLC
- 2 -
GILCHRIST CONSTRUCTION CO. LLC
- 3 -
Diamond B Construction Co., L.L.C.
- 4 -
Amethyst Construction, Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00200Clearing and Grubbing (Selective) 1     LUMP6,000.006,000.00115,000.00115,000.00100,000.00100,000.0025,000.0025,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP3,000.003,000.0010,000.0010,000.0010,000.0010,000.0045,000.0045,000.00
0003202-02-00050Removal of Brick Columns and Walls at STA. 124+50 RT.1     LUMP2,000.002,000.0015,000.0015,000.006,500.006,500.00500.00500.00
0004202-02-00050Removal of Brick Columns at STA. 141+80 LT.1     LUMP1,500.001,500.005,000.005,000.003,500.003,500.00500.00500.00
0005202-02-02000Removal of Asphalt Drives 64     SQYD15.00960.0040.002,560.0070.004,480.0015.00960.00
0006202-02-06100Removal of Concrete Walks and Drives 95     SQYD7.00665.0050.004,750.0025.002,375.0018.001,710.00
0007202-02-14500Removal of Guard Rail 175     LNFT25.004,375.0021.003,675.0040.007,000.0020.003,500.00
0008203-07-00100Borrow (Vehicular Measurement) 255     CUYD36.009,180.0060.0015,300.0020.005,100.0065.0016,575.00
0009203-10-00100Cleaning Existing Ditches 120     LNFT6.00720.0050.006,000.0075.009,000.0055.006,600.00
0010204-02-00100Temporary Hay Bales 32     EACH25.00800.0030.00960.0030.00960.0024.00768.00
0011204-06-00100Temporary Silt Fencing 1,200     LNFT2.503,000.006.007,200.002.503,000.005.256,300.00
0012401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 485     CUYD28.0013,580.0060.0029,100.0020.009,700.0040.0019,400.00
0013402-01-00100Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 135     CUYD53.007,155.0060.008,100.0085.0011,475.0075.0010,125.00
0014402-03-00100Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 50     CUYD53.002,650.0060.003,000.00200.0010,000.0065.003,250.00
0015502-01-00100Asphalt Concrete 4,403.3   TON100.00440,330.00110.00484,363.00110.00484,363.00125.00550,412.50
0016502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 322.7   TON170.0054,859.00110.0035,497.00260.0083,902.00155.0050,018.50
0017507-01-00100Asphalt Material (CRS-2P Emulsion) 14,163     GAL3.1043,905.303.0042,489.003.2546,029.753.1544,613.45
0018507-02-00200Aggregate (S2) 20,827     SQYD1.9039,571.301.8538,529.952.5052,067.502.0542,695.35
0019507-02-00300Aggregate (S3) 20,827     SQYD1.7035,405.901.5031,240.502.0041,654.001.7536,447.25
0020509-01-00100Milling Asphalt Pavement 21,598     SQYD1.5032,397.002.0043,196.003.5075,593.004.0086,392.00
0021510-01-00250Pavement Patching (14 inch Minimum Thickness) 2,425     SQYD140.00339,500.00110.00266,750.00125.00303,125.00115.00278,875.00
0022701-01-01021Cross Drain Pipe (30" RCP) 56     LNFT110.006,160.00140.007,840.00165.009,240.00165.009,240.00
0023701-02-01000Cross Drain Pipe Arch (24" Equiv. RCPA) 40     LNFT105.004,200.00140.005,600.00250.0010,000.00185.007,400.00
0024701-02-01060Cross Drain Pipe Arch (42" Equiv. RCPA) 92     LNFT165.0015,180.00170.0015,640.00300.0027,600.00200.0018,400.00
0025701-02-01080Cross Drain Pipe Arch (48" Equiv. RCPA) 140     LNFT185.0025,900.00250.0035,000.00300.0042,000.00220.0030,800.00
0026701-03-01002Storm Drain Pipe (15" RCP/RPVCP) 48     LNFT95.004,560.0085.004,080.00100.004,800.0065.003,120.00
0027701-03-01082Storm Drain Pipe (36" RCP/RPVCP) 90     LNFT125.0011,250.00140.0012,600.00220.0019,800.0095.008,550.00
0028701-04-01080Storm Drain Pipe Arch (36" Equiv. RCPA) 64     LNFT140.008,960.00140.008,960.00175.0011,200.00155.009,920.00
0029701-05-01042Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CMP) 24     LNFT95.002,280.0090.002,160.00100.002,400.00148.003,552.00
0030701-05-01061Side Drain Pipe (24" RCP/RPVCP/CPEPDW/CMP) 72     LNFT100.007,200.00100.007,200.00105.007,560.00112.008,064.00
0031701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 402     LNFT1.00402.006.002,412.006.002,412.000.50201.00
0032702-03-00100Catch Basins (CB-01) 2     EACH3,300.006,600.006,500.0013,000.004,400.008,800.004,800.009,600.00
0033702-03-00200Catch Basins (CB-02) 2     EACH5,000.0010,000.006,800.0013,600.005,000.0010,000.005,000.0010,000.00
0034702-04-00100Adjusting Manholes 6     EACH1,700.0010,200.002,500.0015,000.002,000.0012,000.001,800.0010,800.00
0035704-01-01000Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 100     LNFT65.006,500.0077.007,700.0090.009,000.00125.0012,500.00
0036704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 86     LNFT90.007,740.00115.009,890.00130.0011,180.00105.009,030.00
0037704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 37.5   LNFT35.001,312.5026.00975.0030.001,125.00108.004,050.00
0038704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 1     EACH5,000.005,000.003,800.003,800.004,200.004,200.003,600.003,600.00
0039704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 3     EACH4,000.0012,000.003,000.009,000.003,500.0010,500.003,800.0011,400.00
0040706-02-00200Concrete Drive (6" Thick) 95.1   SQYD75.007,132.5090.008,559.00125.0011,887.50115.0010,936.50
0041710-01-00100Flowable Fill 348     CUYD150.0052,200.00135.0046,980.00175.0060,900.00225.0078,300.00
0042711-01-03020Riprap (30 lb, 18" Thick) 270     SQYD75.0020,250.0085.0022,950.00110.0029,700.00100.0027,000.00
0043711-04-00100Geotextile Fabric 270     SQYD2.00540.003.00810.005.001,350.002.25607.50
0044713-01-00100Temporary Signs and Barricades 1     LUMP28,000.0028,000.0045,000.0045,000.0030,000.0030,000.0045,000.0045,000.00
0045713-02-00500Temporary Pavement Markings (24" Width) 369     LNFT0.2592.250.30110.700.30110.702.50922.50
0046713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 5.226 MILE200.001,045.20225.001,175.85175.00914.55350.001,829.10
0047713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 20.904 MILE100.002,090.401.0020.90770.0016,096.081,200.0025,084.80
0048713-06-00200Temporary Reflectorized Raised Pavement Markers (Tabs) 460     EACH2.501,150.001.00460.002.501,150.0010.004,600.00
0049716-01-00100Mulch (Vegetative) 6.8   TON750.005,100.00725.004,930.001,100.007,480.001,400.009,520.00
0050717-01-00100Seeding 153     LB12.001,836.0015.002,295.0020.003,060.001.50229.50
0051718-01-00100Fertilizer 3,400     LB0.652,210.000.752,550.001.003,400.000.752,550.00
0052726-01-00100Bedding Material 149     CUYD95.0014,155.00110.0016,390.00125.0018,625.00100.0014,900.00
0053727-01-00100Mobilization 1     LUMP60,000.0060,000.00175,000.00175,000.00102,000.00102,000.0090,000.0090,000.00
0054729-16-00300Object Marker Assembly (Type 3) 19     EACH105.001,995.0080.001,520.00100.001,900.00250.004,750.00
0055731-02-00100Reflectorized Raised Pavement Markers 460     EACH6.002,760.007.003,220.007.003,220.0010.004,600.00
0056732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 123     LNFT15.001,845.0016.001,968.0017.002,091.0022.002,706.00
0057732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 6.968 MILE3,800.0026,478.403,900.0027,175.204,200.0029,265.605,000.0034,840.00
0058735-01-00100Mailboxes 54     EACH5.00270.0025.001,350.0010.00540.00125.006,750.00
0059735-02-00100Mailbox Supports (Single) 54     EACH135.007,290.00160.008,640.00175.009,450.00185.009,990.00
0060740-01-00100Construction Layout 1     LUMP5,000.005,000.0025,000.0025,000.0010,000.0010,000.0045,000.0045,000.00
0061742-01-00400Sanitary Sewer Pipe (8") 16     LNFT100.001,600.00500.008,000.00150.002,400.0075.001,200.00
0062NS-500-00340Saw Cutting Asphalt Concrete Pavement 90     INLF3.00270.0029.742,676.605.50495.002.00180.00
0063NS-600-00220Saw Cutting Portland Cement Concrete Pavement 216     INLF3.00648.0021.164,570.566.001,296.004.00864.00
             
  CONTRACTOR TOTAL   1,430,955.75 1,753,519.26 1,820,972.68 1,822,228.95