Proposal:H.010207.6
Parish:Lafayette
Routes:LA 31, LA 94
Description:LA 94: LA 353 - LA 328
Type Construction:GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, IN-PLACE CEMENT STABILIZED BASE COURSE, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE OVERLAY, PORTLAND CEMENT CONCRETE PAVEMENT, DRILLED SHAFT FOUNDATIONS, TRAFFIC SIGNALIZATION, AND RELATED WORK.
Estimated Construction Cost:$3,408,611.44
| Rank | License | Bidder | Construction Bid |
| 1 | 34356 | Prairie Contractors LLC | $2,987,840.99 |
| 2 | 06276 | Barriere Construction Co., LLC | $3,644,769.21 |
| 3 | 51821 | Elliott Construction, LLC | $3,911,726.24 |
| 4 | 33663 | Glenn Lege Construction LLC | $4,657,134.60 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Prairie Contractors LLC | - 2 - Barriere Construction Co., LLC | - 3 - Elliott Construction, LLC | - 4 - Glenn Lege Construction LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-02020 | Removal of Asphalt Pavement | 2,544.2 | SQYD | 11.50 | 29,258.30 | 7.00 | 17,809.40 | 6.50 | 16,537.30 | 5.94 | 15,112.55 | | 0002 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 13,950.2 | SQYD | 6.10 | 85,096.22 | 2.00 | 27,900.40 | 5.00 | 69,751.00 | 5.75 | 80,213.65 | | 0003 | 202-02-06060 | Removal of Concrete Catch Basin | 4 | EACH | 600.00 | 2,400.00 | 1,000.00 | 4,000.00 | 650.00 | 2,600.00 | 1,010.00 | 4,040.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 846 | SQYD | 11.00 | 9,306.00 | 21.00 | 17,766.00 | 10.00 | 8,460.00 | 17.81 | 15,067.26 | | 0005 | 202-02-14500 | Removal of Guard Rail | 808 | LNFT | 15.00 | 12,120.00 | 5.25 | 4,242.00 | 14.50 | 11,716.00 | 6.31 | 5,098.48 | | 0006 | 202-02-32120 | Removal of Pipe (Side Drain) 15" - 18" | 169 | LNFT | 47.00 | 7,943.00 | 16.00 | 2,704.00 | 25.00 | 4,225.00 | 33.46 | 5,654.74 | | 0007 | 202-02-32120 | Removal of Pipe (Side Drain) 18" - 24" | 233 | LNFT | 29.00 | 6,757.00 | 16.00 | 3,728.00 | 25.00 | 5,825.00 | 32.38 | 7,544.54 | | 0008 | 202-02-32140 | Removal of Pipe (Storm Drain) 18" | 93 | LNFT | 22.00 | 2,046.00 | 16.00 | 1,488.00 | 25.00 | 2,325.00 | 40.53 | 3,769.29 | | 0009 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 1,600.00 | 1,600.00 | 1,800.00 | 1,800.00 | 1,650.00 | 1,650.00 | 2,855.27 | 2,855.27 | | 0010 | 202-02-40120 | Removal of Traffic Detectors and Associated Equipment | 1 | LUMP | 2,100.00 | 2,100.00 | 2,500.00 | 2,500.00 | 2,200.00 | 2,200.00 | 3,467.43 | 3,467.43 | | 0011 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 1,000.00 | 1,000.00 | 20,000.00 | 20,000.00 | 45,000.00 | 45,000.00 | 60,600.00 | 60,600.00 | | 0012 | 204-02-00100 | Temporary Hay Bales | 80 | EACH | 24.00 | 1,920.00 | 23.00 | 1,840.00 | 30.00 | 2,400.00 | 25.25 | 2,020.00 | | 0013 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 12 | EACH | 130.00 | 1,560.00 | 130.00 | 1,560.00 | 100.00 | 1,200.00 | 126.25 | 1,515.00 | | 0014 | 204-06-00100 | Temporary Silt Fencing | 13,040 | LNFT | 1.50 | 19,560.00 | 1.45 | 18,908.00 | 1.65 | 21,516.00 | 1.90 | 24,776.00 | | 0015 | 303-01-00200 | In-Place Cement Stabilized Base Course (8-1/2" Thick) | 12,302 | SQYD | 9.55 | 117,484.10 | 10.00 | 123,020.00 | 16.00 | 196,832.00 | 14.33 | 176,287.66 | | 0016 | 402-03-00100 | Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 680 | CUYD | 35.00 | 23,800.00 | 20.00 | 13,600.00 | 30.00 | 20,400.00 | 82.88 | 56,358.40 | | 0017 | 502-01-00100 | Asphalt Concrete | 15,556.8 | TON | 75.00 | 1,166,760.00 | 102.00 | 1,586,793.60 | 105.00 | 1,633,464.00 | 97.98 | 1,524,255.26 | | 0018 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,134.7 | TON | 140.00 | 158,858.00 | 102.00 | 115,739.40 | 125.00 | 141,837.50 | 134.14 | 152,208.66 | | 0019 | 507-01-00100 | Asphalt Material (CRS-2P Emulsion) | 17,526 | GAL | 2.80 | 49,072.80 | 3.00 | 52,578.00 | 3.00 | 52,578.00 | 3.33 | 58,361.58 | | 0020 | 507-02-00200 | Aggregate (S2) | 25,773 | SQYD | 2.65 | 68,298.45 | 2.65 | 68,298.45 | 2.90 | 74,741.70 | 3.06 | 78,865.38 | | 0021 | 507-02-00300 | Aggregate (S3) | 25,773 | SQYD | 2.40 | 61,855.20 | 2.40 | 61,855.20 | 2.75 | 70,875.75 | 2.78 | 71,648.94 | | 0022 | 509-01-00100 | Milling Asphalt Pavement | 101,533 | SQYD | 2.10 | 213,219.30 | 3.00 | 304,599.00 | 2.00 | 203,066.00 | 2.72 | 276,169.76 | | 0023 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -4,967 | CUYD | 0.01 | -49.67 | 15.00 | -74,505.00 | 0.01 | -49.67 | 0.13 | -645.71 | | 0024 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 650 | SQYD | 115.00 | 74,750.00 | 145.00 | 94,250.00 | 180.00 | 117,000.00 | 173.47 | 112,755.50 | | 0025 | 601-02-01300 | Portland Cement Concrete Pavement (11" Thick) (Crossovers & Turnouts) | 228.2 | SQYD | 220.00 | 50,204.00 | 145.00 | 33,089.00 | 115.00 | 26,243.00 | 151.50 | 34,572.30 | | 0026 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 62 | LNFT | 130.00 | 8,060.00 | 90.00 | 5,580.00 | 80.00 | 4,960.00 | 98.28 | 6,093.36 | | 0027 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 167 | LNFT | 110.00 | 18,370.00 | 100.00 | 16,700.00 | 90.00 | 15,030.00 | 98.67 | 16,477.89 | | 0028 | 701-03-01062 | Storm Drain Pipe (30" RCP/RPVCP) | 90 | LNFT | 110.00 | 9,900.00 | 135.00 | 12,150.00 | 130.00 | 11,700.00 | 130.73 | 11,765.70 | | 0029 | 701-03-01082 | Storm Drain Pipe (36" RCP/RPVCP) | 104 | LNFT | 162.00 | 16,848.00 | 160.00 | 16,640.00 | 135.00 | 14,040.00 | 147.34 | 15,323.36 | | 0030 | 701-03-01092 | Storm Drain Pipe (42" RCP/RPVCP) | 22 | LNFT | 210.00 | 4,620.00 | 200.00 | 4,400.00 | 245.00 | 5,390.00 | 234.20 | 5,152.40 | | 0031 | 701-05-01082 | Side Drain Pipe (30" RCP/RPVCP/CMP) | 102 | LNFT | 128.00 | 13,056.00 | 130.00 | 13,260.00 | 130.00 | 13,260.00 | 126.31 | 12,883.62 | | 0032 | 701-05-01102 | Side Drain Pipe (36" RCP/RPVCP/CMP) | 60 | LNFT | 115.00 | 6,900.00 | 155.00 | 9,300.00 | 135.00 | 8,100.00 | 178.77 | 10,726.20 | | 0033 | 701-05-02102 | Side Drain Pipe (Erosion) (36" RPVCP/CMP) | 80 | LNFT | 115.00 | 9,200.00 | 165.00 | 13,200.00 | 150.00 | 12,000.00 | 154.91 | 12,392.80 | | 0034 | 701-15-00100 | Concrete Collar | 5 | EACH | 1,050.00 | 5,250.00 | 2,000.00 | 10,000.00 | 2,275.00 | 11,375.00 | 2,095.75 | 10,478.75 | | 0035 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 458 | LNFT | 7.75 | 3,549.50 | 7.50 | 3,435.00 | 20.00 | 9,160.00 | 12.63 | 5,784.54 | | 0036 | 702-02-00100 | Manholes (MH-06) | 1 | EACH | 8,200.00 | 8,200.00 | 6,500.00 | 6,500.00 | 5,500.00 | 5,500.00 | 5,460.31 | 5,460.31 | | 0037 | 702-03-00100 | Catch Basins (CB-01) | 7 | EACH | 3,300.00 | 23,100.00 | 3,600.00 | 25,200.00 | 3,250.00 | 22,750.00 | 2,850.63 | 19,954.41 | | 0038 | 702-03-00200 | Catch Basins (CB-02) | 1 | EACH | 4,500.00 | 4,500.00 | 5,000.00 | 5,000.00 | 4,125.00 | 4,125.00 | 4,955.31 | 4,955.31 | | 0039 | 702-03-00500 | Catch Basins (CB-06) | 5 | EACH | 5,000.00 | 25,000.00 | 5,500.00 | 27,500.00 | 5,815.00 | 29,075.00 | 5,921.13 | 29,605.65 | | 0040 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 5 | EACH | 550.00 | 2,750.00 | 350.00 | 1,750.00 | 500.00 | 2,500.00 | 1,111.00 | 5,555.00 | | 0041 | 702-04-00200 | Adjusting Catch Basins | 2 | EACH | 2,650.00 | 5,300.00 | 2,800.00 | 5,600.00 | 2,150.00 | 4,300.00 | 3,566.56 | 7,133.12 | | 0042 | 702-04-00210 | Convert Catch Basins to Manholes | 1 | EACH | 3,700.00 | 3,700.00 | 3,000.00 | 3,000.00 | 3,850.00 | 3,850.00 | 7,764.38 | 7,764.38 | | 0043 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 312.5 | LNFT | 62.00 | 19,375.00 | 45.00 | 14,062.50 | 42.00 | 13,125.00 | 38.89 | 12,153.13 | | 0044 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 187.5 | LNFT | 31.00 | 5,812.50 | 28.00 | 5,250.00 | 28.00 | 5,250.00 | 26.11 | 4,895.63 | | 0045 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 175 | LNFT | 97.00 | 16,975.00 | 95.00 | 16,625.00 | 107.00 | 18,725.00 | 99.99 | 17,498.25 | | 0046 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 7 | EACH | 3,500.00 | 24,500.00 | 3,500.00 | 24,500.00 | 3,520.00 | 24,640.00 | 3,333.00 | 23,331.00 | | 0047 | 706-01-00100 | Concrete Walk (4" Thick) | 3 | SQYD | 750.00 | 2,250.00 | 200.00 | 600.00 | 500.00 | 1,500.00 | 111.10 | 333.30 | | 0048 | 706-02-00200 | Concrete Drive (6" Thick) | 1,528.8 | SQYD | 55.00 | 84,084.00 | 80.00 | 122,304.00 | 85.00 | 129,948.00 | 83.33 | 127,394.90 | | 0049 | 706-04-00100 | Handicapped Curb Ramps | 1 | EACH | 1,600.00 | 1,600.00 | 2,500.00 | 2,500.00 | 2,500.00 | 2,500.00 | 2,222.00 | 2,222.00 | | 0050 | 707-01-00200 | Concrete Curb (Barrier) | 269.8 | LNFT | 40.00 | 10,792.00 | 20.00 | 5,396.00 | 22.00 | 5,935.60 | 22.22 | 5,994.96 | | 0051 | 707-03-00100 | Combination Concrete Curb and Gutter | 629 | LNFT | 52.00 | 32,708.00 | 48.00 | 30,192.00 | 49.50 | 31,135.50 | 50.00 | 31,450.00 | | 0052 | 711-01-05000 | Riprap (130 lb, 24" Thick) | 350 | SQYD | 92.00 | 32,200.00 | 150.00 | 52,500.00 | 138.00 | 48,300.00 | 138.88 | 48,608.00 | | 0053 | 712-02-00100 | Sacked Concrete Revetment Ditch @ State Trooper Office | 300 | SQYD | 120.00 | 36,000.00 | 188.00 | 56,400.00 | 150.00 | 45,000.00 | 166.65 | 49,995.00 | | 0054 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 40,000.00 | 40,000.00 | 225,000.00 | 225,000.00 | 80,000.00 | 80,000.00 | 327,745.00 | 327,745.00 | | 0055 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 5.12 | MILE | 5,885.00 | 30,131.20 | 190.00 | 972.80 | 800.00 | 4,096.00 | 777.70 | 3,981.82 | | 0056 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.362 | MILE | 1.00 | 4.36 | 550.00 | 2,399.10 | 825.00 | 3,598.65 | 555.50 | 2,423.09 | | 0057 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 15.069 | MILE | 2,700.00 | 40,686.30 | 750.00 | 11,301.75 | 1,320.00 | 19,891.08 | 777.70 | 11,719.16 | | 0058 | 724-01-00100 | Rumble Strips (Centerline) | 2.888 | MILE | 1,300.00 | 3,754.40 | 2,500.00 | 7,220.00 | 715.00 | 2,064.92 | 599.94 | 1,732.63 | | 0059 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 8.144 | MILE | 1,300.00 | 10,587.20 | 1,200.00 | 9,772.80 | 625.00 | 5,090.00 | 599.94 | 4,885.91 | | 0060 | 726-01-00100 | Bedding Material | 81.1 | CUYD | 122.00 | 9,894.20 | 100.00 | 8,110.00 | 100.00 | 8,110.00 | 138.94 | 11,268.03 | | 0061 | 727-01-00100 | Mobilization | 1 | LUMP | 35,000.00 | 35,000.00 | 160,000.00 | 160,000.00 | 300,000.00 | 300,000.00 | 460,812.50 | 460,812.50 | | 0062 | 729-01-00100 | Sign (Type A) | 30 | SQFT | 40.00 | 1,200.00 | 55.00 | 1,650.00 | 55.00 | 1,650.00 | 49.61 | 1,488.30 | | 0063 | 731-02-00100 | Reflectorized Raised Pavement Markers | 741 | EACH | 5.10 | 3,779.10 | 5.50 | 4,075.50 | 7.00 | 5,187.00 | 5.56 | 4,119.96 | | 0064 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 7,606 | LNFT | 0.52 | 3,955.12 | 0.55 | 4,183.30 | 1.00 | 7,606.00 | 0.56 | 4,259.36 | | 0065 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,053 | LNFT | 1.55 | 1,632.15 | 1.60 | 1,684.80 | 3.50 | 3,685.50 | 1.67 | 1,758.51 | | 0066 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 207 | LNFT | 12.20 | 2,525.40 | 13.00 | 2,691.00 | 15.00 | 3,105.00 | 13.33 | 2,759.31 | | 0067 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 16.108 | MILE | 3,450.00 | 55,572.60 | 3,600.00 | 57,988.80 | 4,015.00 | 64,673.62 | 3,777.40 | 60,846.36 | | 0068 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.471 | MILE | 760.00 | 3,397.96 | 850.00 | 3,800.35 | 1,485.00 | 6,639.44 | 833.25 | 3,725.46 | | 0069 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.349 | MILE | 4,100.00 | 1,430.90 | 4,500.00 | 1,570.50 | 13,750.00 | 4,798.75 | 4,444.00 | 1,550.96 | | 0070 | 732-04-00001 | Plastic Pavement Legends and Symbols (Message) ONLY | 3 | EACH | 415.00 | 1,245.00 | 400.00 | 1,200.00 | 385.00 | 1,155.00 | 444.40 | 1,333.20 | | 0071 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 14 | EACH | 280.00 | 3,920.00 | 300.00 | 4,200.00 | 385.00 | 5,390.00 | 305.53 | 4,277.42 | | 0072 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 6 | EACH | 280.00 | 1,680.00 | 300.00 | 1,800.00 | 385.00 | 2,310.00 | 305.53 | 1,833.18 | | 0073 | 736-01-00100 | Trenching and Backfilling | 60 | LNFT | 9.00 | 540.00 | 9.00 | 540.00 | 9.50 | 570.00 | 5.17 | 310.20 | | 0074 | 736-03-00100 | Jacking or Boring | 240 | LNFT | 13.70 | 3,288.00 | 14.00 | 3,360.00 | 15.00 | 3,600.00 | 15.00 | 3,600.00 | | 0075 | 736-04-10400 | Signal Pole (Single Mast Arm, 40ft) | 1 | EACH | 14,000.00 | 14,000.00 | 14,000.00 | 14,000.00 | 15,020.00 | 15,020.00 | 13,502.82 | 13,502.82 | | 0076 | 736-05-30000 | Signal Heads (3 Section, 12 inch Led Lens, R, Y, G) | 2 | EACH | 845.00 | 1,690.00 | 850.00 | 1,700.00 | 920.00 | 1,840.00 | 1,330.42 | 2,660.84 | | 0077 | 736-05-35001 | Signal Heads (3 Sec, 12 inch Led Lens, RT. R, RT. Y, RT. G) | 2 | EACH | 845.00 | 1,690.00 | 850.00 | 1,700.00 | 920.00 | 1,840.00 | 1,330.42 | 2,660.84 | | 0078 | 736-05-41200 | Signal Heads (4 Section, 12 inch Led Lens, LT. R, LT. Y, FLT. Y, LT. G) | 1 | EACH | 1,100.00 | 1,100.00 | 1,200.00 | 1,200.00 | 1,150.00 | 1,150.00 | 1,504.02 | 1,504.02 | | 0079 | 736-10-00300 | Underground Junction Box (Type F) | 1 | EACH | 1,050.00 | 1,050.00 | 1,000.00 | 1,000.00 | 1,100.00 | 1,100.00 | 699.93 | 699.93 | | 0080 | 736-11-00300 | Conduit (3" HDPE, Schedule 80) | 280 | LNFT | 6.60 | 1,848.00 | 7.00 | 1,960.00 | 7.25 | 2,030.00 | 6.18 | 1,730.40 | | 0081 | 736-12-06014 | Conductor (6c, #14 awg) | 90 | LNFT | 1.60 | 144.00 | 1.75 | 157.50 | 2.00 | 180.00 | 3.47 | 312.30 | | 0082 | 736-12-10014 | Conductor (10c, #14 awg) | 1,220 | LNFT | 2.35 | 2,867.00 | 2.25 | 2,745.00 | 2.50 | 3,050.00 | 3.82 | 4,660.40 | | 0083 | 736-15-03600 | Signal Support (Foundation, 36 inch Minimum Diameter) | 1 | EACH | 3,950.00 | 3,950.00 | 4,000.00 | 4,000.00 | 4,235.00 | 4,235.00 | 3,624.64 | 3,624.64 | | 0084 | 740-01-00100 | Construction Layout | 1 | LUMP | 100.00 | 100.00 | 30,000.00 | 30,000.00 | 20,000.00 | 20,000.00 | 334,562.50 | 334,562.50 | | 0085 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 23,006 | INLF | 1.90 | 43,711.40 | 0.01 | 230.06 | 1.10 | 25,306.60 | 1.26 | 28,987.56 | | 0086 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,324 | INLF | 2.00 | 4,648.00 | 2.00 | 4,648.00 | 1.50 | 3,486.00 | 1.90 | 4,415.60 | | 0087 | NS-700-00830 | Impact Attenuator (Reusable, Test Level 2) | 1 | EACH | 24,500.00 | 24,500.00 | 22,000.00 | 22,000.00 | 28,500.00 | 28,500.00 | 23,331.00 | 23,331.00 | | 0088 | NS-736-00022 | Wireless Magnetometer Vehicle Detection System (Magnetometers) | 44 | EACH | 700.00 | 30,800.00 | 700.00 | 30,800.00 | 800.00 | 35,200.00 | 774.92 | 34,096.48 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,987,840.99 | | 3,644,769.21 | | 3,911,726.24 | | 4,657,134.60 |
|