Proposal:H.006339.6
Parish:Vernon
Description:SECTION LINE ROAD BRIDGE
Type Construction:CLEARING AND GRUBBING, REMOVAL OF BRIDGE, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE CURVED SLAB SPAN BRIDGE, AND RELATED WORK..
Estimated Construction Cost:$1,123,389.40
| Rank | License | Bidder | Construction Bid |
| 1 | 55505 | MERRICK, LLC | $1,168,095.83 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $1,255,006.13 |
| 3 | 56217 | Williams Equipment Services, LLC | $1,295,601.27 |
| 4 | 55950 | Brown Industrial Construction, LLC | $1,464,827.92 |
| 5 | 59705 | NORTHERN STATE CONSTRUCTION LLC | $1,557,219.65 |
| 6 | 00044 | Guinn Construction, LLC | $1,889,551.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - MERRICK, LLC | - 2 - Diamond B Construction Co., L.L.C. | - 3 - Williams Equipment Services, LLC | - 4 - Brown Industrial Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.881 | LUMP | 20,000.00 | 20,000.00 | 30,000.00 | 30,000.00 | 14,880.28 | 14,880.28 | 175,000.00 | 175,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,500.00 | 2,500.00 | 4,900.00 | 4,900.00 | 2,471.18 | 2,471.18 | 5,000.00 | 5,000.00 | | 0003 | 202-02-02020 | Removal of Asphalt Pavement | 1,954.6 | SQYD | 6.00 | 11,727.60 | 5.25 | 10,261.65 | 5.09 | 9,948.91 | 2.00 | 3,909.20 | | 0004 | 202-02-04501 | Removal of Bridge (TIMBER BRIDGE) | 1,674.4 | LUMP | 17,000.00 | 17,000.00 | 23,000.00 | 23,000.00 | 18,733.31 | 18,733.31 | 70,000.00 | 70,000.00 | | 0005 | 203-02-00100 | Drainage Excavation | 267 | CUYD | 16.00 | 4,272.00 | 40.00 | 10,680.00 | 13.83 | 3,692.61 | 12.00 | 3,204.00 | | 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 70,000.00 | 70,000.00 | 83,000.00 | 83,000.00 | 136,923.06 | 136,923.06 | 100,000.00 | 100,000.00 | | 0007 | 204-03-00100 | Temporary Slope Drains | 30 | LNFT | 31.00 | 930.00 | 24.00 | 720.00 | 136.98 | 4,109.40 | 25.00 | 750.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 90.00 | 360.00 | 147.00 | 588.00 | 187.33 | 749.32 | 150.00 | 600.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 2,205 | LNFT | 1.75 | 3,858.75 | 2.75 | 6,063.75 | 2.50 | 5,512.50 | 2.00 | 4,410.00 | | 0010 | 302-01-00300 | Class II Base Course (Crushed Stone) | 523.6 | CUYD | 105.00 | 54,978.00 | 45.00 | 23,562.00 | 116.67 | 61,088.41 | 125.00 | 65,450.00 | | 0011 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 90 | CUYD | 105.00 | 9,450.00 | 94.00 | 8,460.00 | 115.56 | 10,400.40 | 130.00 | 11,700.00 | | 0012 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 150 | CUYD | 100.00 | 15,000.00 | 15.75 | 2,362.50 | 128.74 | 19,311.00 | 130.00 | 19,500.00 | | 0013 | 502-01-00100 | Asphalt Concrete | 433.8 | TON | 165.00 | 71,577.00 | 123.00 | 53,357.40 | 136.89 | 59,382.88 | 160.00 | 69,408.00 | | 0014 | 701-02-02001 | Cross Drain Pipe Arch (24" Equiv. RCPA or 24" Equiv. CMPA) | 66 | LNFT | 105.00 | 6,930.00 | 170.00 | 11,220.00 | 185.60 | 12,249.60 | 100.00 | 6,600.00 | | 0015 | 701-05-01042 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CMP) | 64 | LNFT | 77.00 | 4,928.00 | 155.00 | 9,920.00 | 126.15 | 8,073.60 | 80.00 | 5,120.00 | | 0016 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 34.00 | 1,700.00 | 34.00 | 1,700.00 | 62.44 | 3,122.00 | 22.00 | 1,100.00 | | 0017 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 114.00 | 11,400.00 | 74.00 | 7,400.00 | 122.39 | 12,239.00 | 98.00 | 9,800.00 | | 0018 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 4 | EACH | 2,750.00 | 11,000.00 | 3,250.00 | 13,000.00 | 2,997.33 | 11,989.32 | 2,400.00 | 9,600.00 | | 0019 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 1,257 | SQYD | 50.00 | 62,850.00 | 67.00 | 84,219.00 | 91.17 | 114,600.69 | 85.00 | 106,845.00 | | 0020 | 711-04-00100 | Geotextile Fabric | 1,257 | SQYD | 1.95 | 2,451.15 | 2.25 | 2,828.25 | 1.25 | 1,571.25 | 3.00 | 3,771.00 | | 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 25,000.00 | 25,000.00 | 14,217.97 | 14,217.97 | 25,000.00 | 25,000.00 | | 0022 | 716-01-00100 | Mulch (Vegetative) | 1.8 | TON | 945.00 | 1,701.00 | 1,250.00 | 2,250.00 | 999.11 | 1,798.40 | 1,900.00 | 3,420.00 | | 0023 | 717-01-00100 | Seeding | 40 | LB | 28.00 | 1,120.00 | 15.00 | 600.00 | 31.22 | 1,248.80 | 18.00 | 720.00 | | 0024 | 718-01-00100 | Fertilizer | 881 | LB | 0.85 | 748.85 | 0.80 | 704.80 | 0.94 | 828.14 | 0.80 | 704.80 | | 0025 | 726-01-00100 | Bedding Material | 14.1 | CUYD | 112.00 | 1,579.20 | 115.00 | 1,621.50 | 98.44 | 1,388.00 | 140.00 | 1,974.00 | | 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 110,000.00 | 110,000.00 | 126,000.00 | 126,000.00 | 42,653.36 | 42,653.36 | 145,000.00 | 145,000.00 | | 0027 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 110.00 | 440.00 | 97.00 | 388.00 | 118.65 | 474.60 | 100.00 | 400.00 | | 0028 | 735-01-00100 | Mailboxes | 2 | EACH | 35.00 | 70.00 | 28.50 | 57.00 | 12.49 | 24.98 | 10.00 | 20.00 | | 0029 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 175.00 | 175.00 | 342.00 | 342.00 | 218.56 | 218.56 | 200.00 | 200.00 | | 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 16,000.00 | 16,000.00 | 17,896.38 | 17,896.38 | 15,000.00 | 15,000.00 | | 0031 | 804-01-00300 | Precast Concrete Piles (16") | 1,960 | LNFT | 105.00 | 205,800.00 | 77.00 | 150,920.00 | 134.67 | 263,953.20 | 88.00 | 172,480.00 | | 0032 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 20,000.00 | 20,000.00 | 17,000.00 | 17,000.00 | 4,474.09 | 4,474.09 | 4,000.00 | 4,000.00 | | 0033 | 804-18-00100 | Vibration Monitoring | 14 | DAY | 800.00 | 11,200.00 | 570.00 | 7,980.00 | 624.44 | 8,742.16 | 450.00 | 6,300.00 | | 0034 | 805-12-00600 | Bridge Superstructure and Substructure (28' Roadway, 75 Degree Crossing) (CAST-IN-PLACE, CURVED) | 3,360 | SQFT | 105.00 | 352,800.00 | 126.00 | 423,360.00 | 106.16 | 356,697.60 | 98.00 | 329,280.00 | | 0035 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 1,442 | SQFT | 2.00 | 2,884.00 | 1.25 | 1,802.50 | 1.50 | 2,163.00 | 1.20 | 1,730.40 | | 0036 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,442 | SQFT | 2.45 | 3,532.90 | 2.15 | 3,100.30 | 1.25 | 1,802.50 | 2.00 | 2,884.00 | | 0037 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 1,158.66 | SQFT | 43.00 | 49,822.38 | 78.00 | 90,375.48 | 56.20 | 65,116.69 | 72.00 | 83,423.52 | | 0038 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 262 | INLF | 5.00 | 1,310.00 | 1.00 | 262.00 | 3.26 | 854.12 | 2.00 | 524.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,168,095.83 | | 1,255,006.13 | | 1,295,601.27 | | 1,464,827.92 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - NORTHERN STATE CONSTRUCTION LLC | - 6 - Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.881 | LUMP | 90,000.00 | 90,000.00 | 120,000.00 | 120,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | | 0003 | 202-02-02020 | Removal of Asphalt Pavement | 1,954.6 | SQYD | 8.50 | 16,614.10 | 8.00 | 15,636.80 | | 0004 | 202-02-04501 | Removal of Bridge (TIMBER BRIDGE) | 1,674.4 | LUMP | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | | 0005 | 203-02-00100 | Drainage Excavation | 267 | CUYD | 50.00 | 13,350.00 | 25.00 | 6,675.00 | | 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 87,500.00 | 87,500.00 | 142,000.00 | 142,000.00 | | 0007 | 204-03-00100 | Temporary Slope Drains | 30 | LNFT | 50.00 | 1,500.00 | 10.00 | 300.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 150.00 | 600.00 | 500.00 | 2,000.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 2,205 | LNFT | 2.00 | 4,410.00 | 3.00 | 6,615.00 | | 0010 | 302-01-00300 | Class II Base Course (Crushed Stone) | 523.6 | CUYD | 125.00 | 65,450.00 | 150.00 | 78,540.00 | | 0011 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 90 | CUYD | 125.00 | 11,250.00 | 165.00 | 14,850.00 | | 0012 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 150 | CUYD | 125.00 | 18,750.00 | 0.00 | 0.00 | | 0013 | 502-01-00100 | Asphalt Concrete | 433.8 | TON | 250.00 | 108,450.00 | 225.00 | 97,605.00 | | 0014 | 701-02-02001 | Cross Drain Pipe Arch (24" Equiv. RCPA or 24" Equiv. CMPA) | 66 | LNFT | 125.00 | 8,250.00 | 200.00 | 13,200.00 | | 0015 | 701-05-01042 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CMP) | 64 | LNFT | 95.00 | 6,080.00 | 150.00 | 9,600.00 | | 0016 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 23.00 | 1,150.00 | 28.00 | 1,400.00 | | 0017 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 92.00 | 9,200.00 | 125.00 | 12,500.00 | | 0018 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 4 | EACH | 2,850.00 | 11,400.00 | 3,500.00 | 14,000.00 | | 0019 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 1,257 | SQYD | 95.00 | 119,415.00 | 90.00 | 113,130.00 | | 0020 | 711-04-00100 | Geotextile Fabric | 1,257 | SQYD | 8.00 | 10,056.00 | 5.00 | 6,285.00 | | 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 24,000.00 | 24,000.00 | | 0022 | 716-01-00100 | Mulch (Vegetative) | 1.8 | TON | 800.00 | 1,440.00 | 2,000.00 | 3,600.00 | | 0023 | 717-01-00100 | Seeding | 40 | LB | 25.00 | 1,000.00 | 50.00 | 2,000.00 | | 0024 | 718-01-00100 | Fertilizer | 881 | LB | 0.75 | 660.75 | 1.00 | 881.00 | | 0025 | 726-01-00100 | Bedding Material | 14.1 | CUYD | 150.00 | 2,115.00 | 150.00 | 2,115.00 | | 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 137,500.00 | 137,500.00 | 190,000.00 | 190,000.00 | | 0027 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 75.00 | 300.00 | 100.00 | 400.00 | | 0028 | 735-01-00100 | Mailboxes | 2 | EACH | 15.00 | 30.00 | 200.00 | 400.00 | | 0029 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 150.00 | 150.00 | 250.00 | 250.00 | | 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 | | 0031 | 804-01-00300 | Precast Concrete Piles (16") | 1,960 | LNFT | 125.00 | 245,000.00 | 95.00 | 186,200.00 | | 0032 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 25,000.00 | 25,000.00 | 18,500.00 | 18,500.00 | | 0033 | 804-18-00100 | Vibration Monitoring | 14 | DAY | 1,000.00 | 14,000.00 | 1,500.00 | 21,000.00 | | 0034 | 805-12-00600 | Bridge Superstructure and Substructure (28' Roadway, 75 Degree Crossing) (CAST-IN-PLACE, CURVED) | 3,360 | SQFT | 110.00 | 369,600.00 | 180.00 | 604,800.00 | | 0035 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 1,442 | SQFT | 2.50 | 3,605.00 | 3.00 | 4,326.00 | | 0036 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,442 | SQFT | 2.50 | 3,605.00 | 3.00 | 4,326.00 | | 0037 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 1,158.66 | SQFT | 80.00 | 92,692.80 | 70.00 | 81,106.20 | | 0038 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 262 | INLF | 8.00 | 2,096.00 | 5.00 | 1,310.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,557,219.65 | | 1,889,551.00 |
|