Proposal:H.006170.6
Parish:Morehouse
Description:MARTIN LUTHER KING SOUTH BRIDGE
Type Construction:CLEARING AND GRUBBING, REMOVAL OF TIMBER BRIDGE, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$1,248,755.00
| Rank | License | Bidder | Construction Bid |
| 1 | 23112 | BEN ALLEN, INC. | $1,478,661.40 |
| 2 | 49239 | WL Bass Construction Inc. | $1,896,702.35 |
| 3 | 39462 | JB JAMES CONSTRUCTION LLC | $2,208,309.40 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - BEN ALLEN, INC. | - 2 - WL Bass Construction Inc. | - 3 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 50,000.00 | 50,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 86 | SQYD | 10.00 | 860.00 | 4.00 | 344.00 | 6.00 | 516.00 | | 0004 | 202-02-02020 | Removal of Asphalt Pavement | 846.2 | SQYD | 7.00 | 5,923.40 | 1.00 | 846.20 | 7.00 | 5,923.40 | | 0005 | 202-02-04501 | Removal of Bridge (8-SPAN TIMBER BRIDGE W/ ASPHALT OVERLAY) | 2,780 | LUMP | 15,000.00 | 15,000.00 | 35,000.00 | 35,000.00 | 350,000.00 | 350,000.00 | | 0006 | 202-02-06100 | Removal of Concrete Walks and Drives | 43 | SQYD | 10.00 | 430.00 | 5.00 | 215.00 | 20.00 | 860.00 | | 0007 | 203-02-00100 | Drainage Excavation | 777 | CUYD | 15.00 | 11,655.00 | 15.00 | 11,655.00 | 20.00 | 15,540.00 | | 0008 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 30,000.00 | 30,000.00 | 44,000.00 | 44,000.00 | 60,000.00 | 60,000.00 | | 0009 | 204-02-00100 | Temporary Hay Bales | 17 | EACH | 100.00 | 1,700.00 | 30.00 | 510.00 | 30.00 | 510.00 | | 0010 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 100.00 | 400.00 | 200.00 | 800.00 | 200.00 | 800.00 | | 0011 | 204-06-00100 | Temporary Silt Fencing | 1,234 | LNFT | 3.00 | 3,702.00 | 3.25 | 4,010.50 | 3.00 | 3,702.00 | | 0012 | 302-01-00300 | Class II Base Course (Crushed Stone) | 222.9 | CUYD | 115.00 | 25,633.50 | 224.00 | 49,929.60 | 140.00 | 31,206.00 | | 0013 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 50 | CUYD | 115.00 | 5,750.00 | 85.00 | 4,250.00 | 100.00 | 5,000.00 | | 0014 | 502-01-00100 | Asphalt Concrete | 178 | TON | 185.00 | 32,930.00 | 187.00 | 33,286.00 | 185.00 | 32,930.00 | | 0015 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 80.2 | TON | 190.00 | 15,238.00 | 212.00 | 17,002.40 | 210.00 | 16,842.00 | | 0016 | 701-01-01004 | Cross Drain Pipe (24" RCP/RPVCP) | 55 | LNFT | 65.00 | 3,575.00 | 90.00 | 4,950.00 | 170.00 | 9,350.00 | | 0017 | 701-05-01042 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CMP) | 113 | LNFT | 65.00 | 7,345.00 | 70.00 | 7,910.00 | 95.00 | 10,735.00 | | 0018 | 701-05-01081 | Side Drain Pipe (30" RCP/RPVCP/CPEPDW/CMP) | 209 | LNFT | 85.00 | 17,765.00 | 105.00 | 21,945.00 | 125.00 | 26,125.00 | | 0019 | 701-05-02061 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CMP) | 50 | LNFT | 65.00 | 3,250.00 | 100.00 | 5,000.00 | 135.00 | 6,750.00 | | 0020 | 701-05-02081 | Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CMP) | 150 | LNFT | 85.00 | 12,750.00 | 104.00 | 15,600.00 | 125.00 | 18,750.00 | | 0021 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 192 | LNFT | 10.00 | 1,920.00 | 25.00 | 4,800.00 | 2.00 | 384.00 | | 0022 | 702-03-00100 | Catch Basins (CB-01) | 7 | EACH | 3,500.00 | 24,500.00 | 5,000.00 | 35,000.00 | 5,000.00 | 35,000.00 | | 0023 | 702-08-00100 | Side Drain Safety End (Type 1) | 1 | EACH | 3,500.00 | 3,500.00 | 1,500.00 | 1,500.00 | 2,500.00 | 2,500.00 | | 0024 | 702-08-00200 | Side Drain Safety End (Type 2) | 2 | EACH | 6,500.00 | 13,000.00 | 3,500.00 | 7,000.00 | 4,500.00 | 9,000.00 | | 0025 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 26.00 | 1,300.00 | 28.00 | 1,400.00 | 25.00 | 1,250.00 | | 0026 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 100.00 | 10,000.00 | 95.00 | 9,500.00 | 100.00 | 10,000.00 | | 0027 | 704-10-00100 | Guard Rail End Treatment (Flared) | 3 | EACH | 3,000.00 | 9,000.00 | 3,900.00 | 11,700.00 | 2,800.00 | 8,400.00 | | 0028 | 704-10-00105 | Guard Rail End Treatment (Flared, 12' - 6" Length) | 1 | EACH | 2,900.00 | 2,900.00 | 4,500.00 | 4,500.00 | 2,700.00 | 2,700.00 | | 0029 | 705-01-00100 | Barbed Wire Fence | 36 | LNFT | 20.00 | 720.00 | 25.00 | 900.00 | 25.00 | 900.00 | | 0030 | 705-06-00300 | Chain Link Fence (6-Foot Height) | 163 | LNFT | 25.00 | 4,075.00 | 45.00 | 7,335.00 | 45.00 | 7,335.00 | | 0031 | 706-01-00100 | Concrete Walk (4" Thick) | 59.9 | SQYD | 75.00 | 4,492.50 | 70.00 | 4,193.00 | 70.00 | 4,193.00 | | 0032 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 1,225 | SQYD | 73.00 | 89,425.00 | 75.00 | 91,875.00 | 80.00 | 98,000.00 | | 0033 | 711-04-00100 | Geotextile Fabric | 1,225 | SQYD | 3.00 | 3,675.00 | 2.25 | 2,756.25 | 3.00 | 3,675.00 | | 0034 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 28,300.00 | 28,300.00 | 35,000.00 | 35,000.00 | | 0035 | 716-01-00100 | Mulch (Vegetative) | 0.9 | TON | 1,200.00 | 1,080.00 | 1,500.00 | 1,350.00 | 1,500.00 | 1,350.00 | | 0036 | 717-01-00100 | Seeding | 19 | LB | 50.00 | 950.00 | 55.00 | 1,045.00 | 55.00 | 1,045.00 | | 0037 | 718-01-00100 | Fertilizer | 430 | LB | 3.00 | 1,290.00 | 3.00 | 1,290.00 | 3.00 | 1,290.00 | | 0038 | 720-01-01020 | Erosion Control System (Slope Protection) (Type B) | 250 | SQYD | 5.00 | 1,250.00 | 10.00 | 2,500.00 | 10.00 | 2,500.00 | | 0039 | 726-01-00100 | Bedding Material | 22.4 | CUYD | 115.00 | 2,576.00 | 120.00 | 2,688.00 | 100.00 | 2,240.00 | | 0040 | 727-01-00100 | Mobilization | 1 | LUMP | 130,000.00 | 130,000.00 | 187,000.00 | 187,000.00 | 197,000.00 | 197,000.00 | | 0041 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | 105.00 | 420.00 | 75.00 | 300.00 | | 0042 | 735-01-00100 | Mailboxes | 2 | EACH | 150.00 | 300.00 | 100.00 | 200.00 | 25.00 | 50.00 | | 0043 | 735-02-00100 | Mailbox Supports (Single) | 2 | EACH | 150.00 | 300.00 | 200.00 | 400.00 | 200.00 | 400.00 | | 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 45,000.00 | 45,000.00 | 20,000.00 | 20,000.00 | | 0045 | 804-01-00300 | Precast Concrete Piles (16") | 3,360 | LNFT | 84.00 | 282,240.00 | 115.00 | 386,400.00 | 160.00 | 537,600.00 | | 0046 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 10,000.00 | 10,000.00 | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 | | 0047 | 804-18-00100 | Vibration Monitoring | 16 | DAY | 800.00 | 12,800.00 | 265.00 | 4,240.00 | 950.00 | 15,200.00 | | 0048 | 805-12-00900 | Bridge Superstructure and Substructure (CAST-IN-PLACE) (28 FT. CLR. RDWY,; 6 FT. CLR. SIDEWALK; 45 DEGREE CROSSING; W/O ASPHALT) | 3,920 | SQFT | 140.00 | 548,800.00 | 150.00 | 588,000.00 | 125.00 | 490,000.00 | | 0049 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 2,363 | SQFT | 2.00 | 4,726.00 | 1.30 | 3,071.90 | 1.00 | 2,363.00 | | 0050 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 2,815 | SQFT | 2.00 | 5,630.00 | 1.80 | 5,067.00 | 1.00 | 2,815.00 | | 0051 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 733 | SQFT | 65.00 | 47,645.00 | 200.00 | 146,600.00 | 60.00 | 43,980.00 | | 0052 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 630 | INLF | 2.00 | 1,260.00 | 2.25 | 1,417.50 | 10.00 | 6,300.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,478,661.40 | | 1,896,702.35 | | 2,208,309.40 |
|