Proposal:H.003184.6
Parish:Calcasieu
Routes:I-10
Description:I-10: TEXAS STATE LINE - E. OF COONE GULLLY
Type Construction:CLEARING AND GRUBBING, REMOVAL OF CONCRETE DECK GIRDER BRIDGE, REMOVAL OF SLAB SPAN BRIDGES, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, SUBGRADE TREATMENT, CLASS II BASE COURSE, THIN ASPHALT CONCRETE (OGFC), ASPHALT CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, PRECAST PRESTRESSED CONCRETE GIRDER SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$161,650,339.24
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$20,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 58134 | Johnson Bros. Corp. A Southland Co. | $152,221,212.63 | 1473.00 | $181,681,212.63 |
| 2 | 39462 | JB JAMES CONSTRUCTION LLC | $154,850,853.96 | 1500.00 | $184,850,853.96 |
| 3 | 34567 | James Construction Group LLC | $153,274,566.30 | 2039.00 | $194,054,566.30 |
| 4 | 47347 | Kiewit Louisiana Co. | $192,908,688.15 | 800.00 | $208,908,688.15 |
| 5 | 12312 | GILCHRIST CONSTRUCTION CO. LLC | $182,726,111.10 | 1325.00 | $209,226,111.10 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Johnson Bros. Corp. A Southland Co. | - 2 - JB JAMES CONSTRUCTION LLC | - 3 - James Construction Group LLC | - 4 - Kiewit Louisiana Co. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 32.25 | LUMP | 1,000,000.00 | 1,000,000.00 | 600,000.00 | 600,000.00 | 1,500,000.00 | 1,500,000.00 | 1,000,000.00 | 1,000,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 150,000.00 | 150,000.00 | 200,000.00 | 200,000.00 | 70,000.00 | 70,000.00 | 300,000.00 | 300,000.00 | | 0003 | 202-02-00030 | Removal of (CONCRETE MEDIAN BARRIER) | 2,412 | LNFT | 14.00 | 33,768.00 | 250.00 | 603,000.00 | 20.00 | 48,240.00 | 40.00 | 96,480.00 | | 0004 | 202-02-02020 | Removal of Asphalt Pavement | 130,605.7 | SQYD | 3.50 | 457,119.95 | 7.00 | 914,239.90 | 4.00 | 522,422.80 | 5.00 | 653,028.50 | | 0005 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 166,329.9 | SQYD | 6.00 | 997,979.40 | 8.00 | 1,330,639.20 | 2.00 | 332,659.80 | 10.00 | 1,663,299.00 | | 0006 | 202-02-03010 | Removal of Base – Recycled PCC or Stone | 53,018.4 | SQYD | 3.00 | 159,055.20 | 7.00 | 371,128.80 | 3.00 | 159,055.20 | 12.00 | 636,220.80 | | 0007 | 202-02-04501 | Removal of Bridge (STA. 184+61.63, 69.5' X 722' CONCRETE DECK GIRDER BRIDGE) | 50,179 | LUMP | 599,000.00 | 599,000.00 | 1,500,000.00 | 1,500,000.00 | 733,000.00 | 733,000.00 | 500,000.00 | 500,000.00 | | 0008 | 202-02-04501 | Removal of Bridge (STA. 353+35.49 EB, 45.5' X 100' SLAB SPAN BRIDGE) | 4,550 | LUMP | 200,000.00 | 200,000.00 | 300,000.00 | 300,000.00 | 90,000.00 | 90,000.00 | 150,000.00 | 150,000.00 | | 0009 | 202-02-04501 | Removal of Bridge (STA. 353+35.59 WB, 45.5' X 100' SLAB SPAN BRIDGE) | 4,547 | LUMP | 200,000.00 | 200,000.00 | 300,000.00 | 300,000.00 | 90,000.00 | 90,000.00 | 150,000.00 | 150,000.00 | | 0010 | 202-02-04501 | Removal of Bridge (STA. 527+39.64 WB, 54.75' X 240' SLAB SPAN BRIDGE) | 13,140 | LUMP | 500,000.00 | 500,000.00 | 200,000.00 | 200,000.00 | 200,000.00 | 200,000.00 | 500,000.00 | 500,000.00 | | 0011 | 202-02-04501 | Removal of Bridge (STA. 528+05.89 EB, 42.75' X 240' SLAB SPAN BRIDGE) | 10,260 | LUMP | 400,000.00 | 400,000.00 | 200,000.00 | 200,000.00 | 200,000.00 | 200,000.00 | 500,000.00 | 500,000.00 | | 0012 | 202-02-04501 | Removal of Bridge (STA. 544+00.20 EB, 45.75' X 140' SLAB SPAN BRIDGE) | 6,405 | LUMP | 225,000.00 | 225,000.00 | 100,000.00 | 100,000.00 | 85,000.00 | 85,000.00 | 150,000.00 | 150,000.00 | | 0013 | 202-02-04501 | Removal of Bridge (STA. 544+00.27 WB, 45.75' X 140' SLAB SPAN BRIDGE) | 6,405 | LUMP | 225,000.00 | 225,000.00 | 100,000.00 | 100,000.00 | 85,000.00 | 85,000.00 | 150,000.00 | 150,000.00 | | 0014 | 202-02-04501 | Removal of Bridge (STA. 575+76.19 EB, 45.75' X 120' SLAB SPAN BRIDGE) | 5,490 | LUMP | 200,000.00 | 200,000.00 | 100,000.00 | 100,000.00 | 75,000.00 | 75,000.00 | 150,000.00 | 150,000.00 | | 0015 | 202-02-04501 | Removal of Bridge (STA. 576+64.97 WB, 45.75' X 120' SLAB SPAN BRIDGE) | 5,490 | LUMP | 200,000.00 | 200,000.00 | 100,000.00 | 100,000.00 | 75,000.00 | 75,000.00 | 150,000.00 | 150,000.00 | | 0016 | 202-02-06101 | Removal of Concrete Median Barrier and Footing | 5,532 | SQYD | 50.00 | 276,600.00 | 200.00 | 1,106,400.00 | 50.00 | 276,600.00 | 60.00 | 331,920.00 | | 0017 | 202-02-14500 | Removal of Guard Rail | 15,460.7 | LNFT | 6.00 | 92,764.20 | 7.00 | 108,224.90 | 5.00 | 77,303.50 | 6.00 | 92,764.20 | | 0018 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 10,636 | SQYD | 11.00 | 116,996.00 | 20.00 | 212,720.00 | 5.00 | 53,180.00 | 9.00 | 95,724.00 | | 0019 | 202-02-38220 | Removal of Sign Supports | 183 | EACH | 71.00 | 12,993.00 | 300.00 | 54,900.00 | 250.00 | 45,750.00 | 272.71 | 49,906.48 | | 0020 | 202-02-38300 | Removal of Sign and U-Channel Post | 32 | EACH | 71.00 | 2,272.00 | 10.00 | 320.00 | 10.00 | 320.00 | 10.91 | 349.09 | | 0021 | 202-02-38360 | Removal of Sign Faces | 123 | EACH | 71.00 | 8,733.00 | 50.00 | 6,150.00 | 50.00 | 6,150.00 | 54.54 | 6,708.79 | | 0022 | 203-01-00100 | General Excavation | 149,907 | CUYD | 16.00 | 2,398,512.00 | 12.00 | 1,798,884.00 | 3.00 | 449,721.00 | 25.00 | 3,747,675.00 | | 0023 | 203-02-00100 | Drainage Excavation | 6,737 | CUYD | 3.50 | 23,579.50 | 22.00 | 148,214.00 | 10.00 | 67,370.00 | 40.00 | 269,480.00 | | 0024 | 203-03-00100 | Embankment | 357,869 | CUYD | 25.00 | 8,946,725.00 | 30.00 | 10,736,070.00 | 23.00 | 8,230,987.00 | 50.00 | 17,893,450.00 | | 0025 | 203-04-00300 | Nonplastic Embankment (Stone) | 1,147 | CUYD | 56.00 | 64,232.00 | 125.00 | 143,375.00 | 400.00 | 458,800.00 | 100.00 | 114,700.00 | | 0026 | 203-08-00100 | Geotextile Fabric | 4,009 | SQYD | 4.00 | 16,036.00 | 3.00 | 12,027.00 | 2.00 | 8,018.00 | 1.00 | 4,009.00 | | 0027 | 203-10-00100 | Cleaning Existing Ditches | 5,000 | LNFT | 10.00 | 50,000.00 | 12.00 | 60,000.00 | 20.00 | 100,000.00 | 11.00 | 55,000.00 | | 0028 | 204-02-00100 | Temporary Hay Bales | 140 | EACH | 20.00 | 2,800.00 | 20.00 | 2,800.00 | 30.00 | 4,200.00 | 22.25 | 3,115.42 | | 0029 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 664 | EACH | 110.00 | 73,040.00 | 110.00 | 73,040.00 | 130.00 | 86,320.00 | 122.39 | 81,268.95 | | 0030 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 55 | EACH | 750.00 | 41,250.00 | 900.00 | 49,500.00 | 630.00 | 34,650.00 | 654.51 | 35,998.05 | | 0031 | 204-06-00100 | Temporary Silt Fencing | 164,831 | LNFT | 1.65 | 271,971.15 | 3.00 | 494,493.00 | 2.50 | 412,077.50 | 1.84 | 302,629.72 | | 0032 | 204-07-00100 | Temporary Stone Construction Entrance | 6 | EACH | 3,000.00 | 18,000.00 | 10,000.00 | 60,000.00 | 3,000.00 | 18,000.00 | 4,363.40 | 26,180.40 | | 0033 | 302-02-04070 | Class II Base Course (4" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 180,220.4 | SQYD | 17.00 | 3,063,746.80 | 11.00 | 1,982,424.40 | 15.00 | 2,703,306.00 | 13.00 | 2,342,865.20 | | 0034 | 302-02-06010 | Class II Base Course (6" Thick) (Soil Cement) | 326,774.8 | SQYD | 18.00 | 5,881,946.40 | 10.00 | 3,267,748.00 | 10.00 | 3,267,748.00 | 12.00 | 3,921,297.60 | | 0035 | 302-02-10075 | Class II Base Course (10" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 155,083.2 | SQYD | 40.00 | 6,203,328.00 | 25.00 | 3,877,080.00 | 30.00 | 4,652,496.00 | 31.00 | 4,807,579.20 | | 0036 | 302-02-14070 | Class II Base Course (14" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 73,150.3 | SQYD | 55.00 | 4,023,266.50 | 50.00 | 3,657,515.00 | 40.00 | 2,926,012.00 | 34.00 | 2,487,110.20 | | 0037 | 302-02-16070 | Class II Base Course (16" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 6,584.1 | SQYD | 56.00 | 368,709.60 | 50.00 | 329,205.00 | 45.00 | 296,284.50 | 69.00 | 454,302.90 | | 0038 | 302-02-18070 | Class II Base Course (18" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 18,262.1 | SQYD | 65.00 | 1,187,036.50 | 65.00 | 1,187,036.50 | 55.00 | 1,004,415.50 | 60.00 | 1,095,726.00 | | 0039 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 429,771 | SQYD | 7.00 | 3,008,397.00 | 12.00 | 5,157,252.00 | 12.00 | 5,157,252.00 | 12.00 | 5,157,252.00 | | 0040 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 39 | CUYD | 155.00 | 6,045.00 | 120.00 | 4,680.00 | 165.00 | 6,435.00 | 400.00 | 15,600.00 | | 0041 | 402-02-00100 | Mainline Traffic Maintenance Surfacing (Hard) | 300 | SQYD | 25.00 | 7,500.00 | 100.00 | 30,000.00 | 175.00 | 52,500.00 | 156.40 | 46,920.60 | | 0042 | 501-03-00100 | Thin Asphalt Concrete (OGFC) | 26,110.9 | TON | 125.00 | 3,263,862.50 | 150.00 | 3,916,635.00 | 150.00 | 3,916,635.00 | 157.00 | 4,099,411.30 | | 0043 | 502-01-00100 | Asphalt Concrete | 287,733.4 | TON | 97.00 | 27,910,139.80 | 95.00 | 27,334,673.00 | 130.00 | 37,405,342.00 | 109.15 | 31,404,949.68 | | 0044 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,147.2 | TON | 200.00 | 229,440.00 | 200.00 | 229,440.00 | 235.00 | 269,592.00 | 205.87 | 236,168.33 | | 0045 | 509-01-00100 | Milling Asphalt Pavement | 271,419 | SQYD | 3.00 | 814,257.00 | 4.00 | 1,085,676.00 | 1.00 | 271,419.00 | 2.08 | 564,822.94 | | 0046 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,985 | SQYD | 100.00 | 198,500.00 | 140.00 | 277,900.00 | 135.00 | 267,975.00 | 150.00 | 297,750.00 | | 0047 | 601-01-01100 | Portland Cement Concrete Pavement (13" Thick) | 17,571.6 | SQYD | 85.00 | 1,493,586.00 | 125.00 | 2,196,450.00 | 110.00 | 1,932,876.00 | 128.00 | 2,249,164.80 | | 0048 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 20 | EACH | 150.00 | 3,000.00 | 125.00 | 2,500.00 | 250.00 | 5,000.00 | 1,000.00 | 20,000.00 | | 0049 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 1,300 | LNFT | 4.00 | 5,200.00 | 5.00 | 6,500.00 | 3.00 | 3,900.00 | 1.00 | 1,300.00 | | 0050 | 701-01-01003 | Cross Drain Pipe (24" RCP/RPVCP/CPEPDW) | 128 | LNFT | 150.00 | 19,200.00 | 120.00 | 15,360.00 | 240.00 | 30,720.00 | 240.00 | 30,720.00 | | 0051 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 634 | LNFT | 170.00 | 107,780.00 | 70.00 | 44,380.00 | 165.00 | 104,610.00 | 270.00 | 171,180.00 | | 0052 | 701-02-01060 | Cross Drain Pipe Arch (42" Equiv. RCPA) | 400 | LNFT | 250.00 | 100,000.00 | 150.00 | 60,000.00 | 225.00 | 90,000.00 | 475.00 | 190,000.00 | | 0053 | 701-02-01100 | Cross Drain Pipe Arch (54" Equiv. RCPA) | 64 | LNFT | 400.00 | 25,600.00 | 210.00 | 13,440.00 | 275.00 | 17,600.00 | 575.00 | 36,800.00 | | 0054 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 781 | LNFT | 100.00 | 78,100.00 | 90.00 | 70,290.00 | 120.00 | 93,720.00 | 130.00 | 101,530.00 | | 0055 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 565 | LNFT | 130.00 | 73,450.00 | 80.00 | 45,200.00 | 135.00 | 76,275.00 | 100.00 | 56,500.00 | | 0056 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 471 | LNFT | 120.00 | 56,520.00 | 70.00 | 32,970.00 | 135.00 | 63,585.00 | 105.00 | 49,455.00 | | 0057 | 701-05-02061 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CMP) (CMP IS NOT ALLOWED) | 40 | LNFT | 85.00 | 3,400.00 | 90.00 | 3,600.00 | 425.00 | 17,000.00 | 255.00 | 10,200.00 | | 0058 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 66 | LNFT | 190.00 | 12,540.00 | 110.00 | 7,260.00 | 430.00 | 28,380.00 | 244.00 | 16,104.00 | | 0059 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 580 | LNFT | 190.00 | 110,200.00 | 110.00 | 63,800.00 | 290.00 | 168,200.00 | 190.00 | 110,200.00 | | 0060 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 154 | LNFT | 200.00 | 30,800.00 | 130.00 | 20,020.00 | 265.00 | 40,810.00 | 200.00 | 30,800.00 | | 0061 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 48 | LNFT | 325.00 | 15,600.00 | 125.00 | 6,000.00 | 470.00 | 22,560.00 | 300.00 | 14,400.00 | | 0062 | 701-11-01020 | Reinforced Concrete Pipe Arch (Extension) (18" Equiv.) | 342 | LNFT | 120.00 | 41,040.00 | 55.00 | 18,810.00 | 120.00 | 41,040.00 | 115.00 | 39,330.00 | | 0063 | 701-14-00100 | Cleaning Existing Pipes | 5,000 | LNFT | 22.00 | 110,000.00 | 21.00 | 105,000.00 | 30.00 | 150,000.00 | 20.00 | 100,000.00 | | 0064 | 701-15-00100 | Concrete Collar | 38 | EACH | 900.00 | 34,200.00 | 1,000.00 | 38,000.00 | 2,000.00 | 76,000.00 | 1,900.00 | 72,200.00 | | 0065 | 702-02-00200 | Manholes (R-CB-11) | 11 | EACH | 5,000.00 | 55,000.00 | 2,900.00 | 31,900.00 | 8,000.00 | 88,000.00 | 8,400.00 | 92,400.00 | | 0066 | 702-02-00900 | Manholes (MH-14X Open) | 11 | EACH | 7,500.00 | 82,500.00 | 17,800.00 | 195,800.00 | 30,000.00 | 330,000.00 | 24,000.00 | 264,000.00 | | 0067 | 702-03-00100 | Catch Basins (CB-01) | 22 | EACH | 5,200.00 | 114,400.00 | 3,000.00 | 66,000.00 | 7,500.00 | 165,000.00 | 8,400.00 | 184,800.00 | | 0068 | 702-03-00200 | Catch Basins (CB-02) | 1 | EACH | 6,200.00 | 6,200.00 | 3,500.00 | 3,500.00 | 8,000.00 | 8,000.00 | 9,900.00 | 9,900.00 | | 0069 | 702-04-00200 | Adjusting Catch Basins | 2 | EACH | 1,000.00 | 2,000.00 | 2,000.00 | 4,000.00 | 4,500.00 | 9,000.00 | 6,300.00 | 12,600.00 | | 0070 | 702-04-01000 | Capping Existing Catch Basin or Manhole | 5 | EACH | 1,300.00 | 6,500.00 | 500.00 | 2,500.00 | 4,000.00 | 20,000.00 | 4,300.00 | 21,500.00 | | 0071 | 702-07-00100 | Cross Drain Safety End (Type 1) | 14 | EACH | 3,600.00 | 50,400.00 | 1,500.00 | 21,000.00 | 2,200.00 | 30,800.00 | 2,700.00 | 37,800.00 | | 0072 | 702-07-00200 | Cross Drain Safety End (Type 2) | 2 | EACH | 9,000.00 | 18,000.00 | 5,800.00 | 11,600.00 | 3,800.00 | 7,600.00 | 8,700.00 | 17,400.00 | | 0073 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 4,262.9 | LNFT | 25.00 | 106,572.50 | 23.00 | 98,046.70 | 23.00 | 98,046.70 | 25.09 | 106,956.16 | | 0074 | 704-03-00300 | Blocked Out Guard Rail – 31”, (3’-1 ½ ” Post Spacing) | 206.8 | LNFT | 35.00 | 7,238.00 | 32.00 | 6,617.60 | 32.50 | 6,721.00 | 36.00 | 7,444.39 | | 0075 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 29.7 | LNFT | 100.00 | 2,970.00 | 90.00 | 2,673.00 | 90.00 | 2,673.00 | 103.63 | 3,077.84 | | 0076 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 425 | LNFT | 95.00 | 40,375.00 | 85.00 | 36,125.00 | 85.00 | 36,125.00 | 92.72 | 39,406.85 | | 0077 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 16 | EACH | 3,250.00 | 52,000.00 | 3,000.00 | 48,000.00 | 2,950.00 | 47,200.00 | 3,299.82 | 52,797.14 | | 0078 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 11 | EACH | 2,750.00 | 30,250.00 | 2,500.00 | 27,500.00 | 2,500.00 | 27,500.00 | 2,727.13 | 29,998.38 | | 0079 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 399.4 | SQYD | 45.00 | 17,973.00 | 115.00 | 45,931.00 | 55.00 | 21,967.00 | 100.00 | 39,940.00 | | 0080 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 417 | SQYD | 100.00 | 41,700.00 | 125.00 | 52,125.00 | 90.00 | 37,530.00 | 125.00 | 52,125.00 | | 0081 | 710-01-00100 | Flowable Fill | 38.76 | CUYD | 200.00 | 7,752.00 | 165.00 | 6,395.40 | 200.00 | 7,752.00 | 450.00 | 17,442.00 | | 0082 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 125 | SQYD | 100.00 | 12,500.00 | 53.00 | 6,625.00 | 215.00 | 26,875.00 | 104.00 | 13,000.00 | | 0083 | 711-04-00100 | Geotextile Fabric | 125 | SQYD | 6.00 | 750.00 | 2.45 | 306.25 | 15.00 | 1,875.00 | 3.80 | 475.00 | | 0084 | 712-04-00100 | Flexible Revetment | 14,682 | SQYD | 90.00 | 1,321,380.00 | 50.00 | 734,100.00 | 100.00 | 1,468,200.00 | 81.81 | 1,201,193.15 | | 0085 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,000,000.00 | 1,000,000.00 | 1,100,000.00 | 1,100,000.00 | 1,200,000.00 | 1,200,000.00 | 5,000,000.00 | 5,000,000.00 | | 0086 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 311.317 | MILE | 5,800.00 | 1,805,638.60 | 7,000.00 | 2,179,219.00 | 5,000.00 | 1,556,585.00 | 7,417.78 | 2,309,281.02 | | 0087 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) (STA. 99+12.46 - STA. 102+17.82) | 0.174 | MILE | 5,700.00 | 991.80 | 7,100.00 | 1,235.40 | 5,000.00 | 870.00 | 7,854.12 | 1,366.62 | | 0088 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 129,361 | EACH | 7.00 | 905,527.00 | 5.00 | 646,805.00 | 4.00 | 517,444.00 | 4.91 | 635,033.15 | | 0089 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers (STA. 99+12.46 - STA. 102+17.82) | 92 | EACH | 7.00 | 644.00 | 5.00 | 460.00 | 4.00 | 368.00 | 4.91 | 451.63 | | 0090 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 3,212 | EACH | 950.00 | 3,051,400.00 | 1,300.00 | 4,175,600.00 | 465.00 | 1,493,580.00 | 1,200.00 | 3,854,400.00 | | 0091 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 13,857 | EACH | 46.00 | 637,422.00 | 60.00 | 831,420.00 | 65.00 | 900,705.00 | 75.00 | 1,039,275.00 | | 0092 | 713-11-00100 | Portable Changeable Message Signs | 4 | EACH | 15,000.00 | 60,000.00 | 50,000.00 | 200,000.00 | 16,500.00 | 66,000.00 | 20,435.98 | 81,743.94 | | 0093 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 22,397 | SQYD | 1.15 | 25,756.55 | 1.00 | 22,397.00 | 1.00 | 22,397.00 | 1.22 | 27,413.93 | | 0094 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 1,201 | SQYD | 1.25 | 1,501.25 | 1.27 | 1,525.27 | 1.50 | 1,801.50 | 1.39 | 1,670.59 | | 0095 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 1,264 | SQYD | 1.30 | 1,643.20 | 1.32 | 1,668.48 | 1.50 | 1,896.00 | 1.45 | 1,827.74 | | 0096 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 32,500.00 | 32,500.00 | 140,000.00 | 140,000.00 | 130,000.00 | 130,000.00 | 500,000.00 | 500,000.00 | | 0097 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 37.182 | MILE | 340.00 | 12,641.88 | 270.00 | 10,039.14 | 270.00 | 10,039.14 | 2,454.41 | 91,259.98 | | 0098 | 725-01-00100 | Temporary Detour Roads | 12,764.2 | SQYD | 54.00 | 689,266.80 | 120.00 | 1,531,704.00 | 100.00 | 1,276,420.00 | 165.00 | 2,106,093.00 | | 0099 | 726-01-00100 | Bedding Material | 1,101.6 | CUYD | 67.00 | 73,807.20 | 105.00 | 115,668.00 | 90.00 | 99,144.00 | 80.00 | 88,128.00 | | 0100 | 727-01-00100 | Mobilization | 1 | LUMP | 15,000,000.00 | 15,000,000.00 | 15,000,000.00 | 15,000,000.00 | 15,300,000.00 | 15,300,000.00 | 17,555,000.00 | 17,555,000.00 | | 0101 | 729-01-00100 | Sign (Type A) | 1,484.6 | SQFT | 22.00 | 32,661.20 | 25.00 | 37,115.00 | 25.00 | 37,115.00 | 30.54 | 45,345.62 | | 0102 | 729-02-00100 | Sign (Type B) | 27 | SQFT | 24.00 | 648.00 | 40.00 | 1,080.00 | 40.00 | 1,080.00 | 43.63 | 1,178.12 | | 0103 | 729-04-00100 | Sign (Type D) | 4,469 | SQFT | 28.00 | 125,132.00 | 27.00 | 120,663.00 | 27.00 | 120,663.00 | 30.54 | 136,501.14 | | 0104 | 729-04-00103 | Sign (Type D)(Relocate) | 161.3 | SQFT | 18.00 | 2,903.40 | 47.00 | 7,581.10 | 47.00 | 7,581.10 | 60.00 | 9,677.52 | | 0105 | 729-05-00100 | Sign (Type E) | 288 | SQFT | 37.00 | 10,656.00 | 30.00 | 8,640.00 | 30.00 | 8,640.00 | 32.73 | 9,424.80 | | 0106 | 729-06-00100 | Sign (Overhead Mounted) | 293 | SQFT | 30.00 | 8,790.00 | 30.00 | 8,790.00 | 30.00 | 8,790.00 | 32.73 | 9,588.43 | | 0107 | 729-08-00100 | Mounting (2 1/2" Size Post) | 2 | EACH | 1,200.00 | 2,400.00 | 960.00 | 1,920.00 | 950.00 | 1,900.00 | 981.77 | 1,963.53 | | 0108 | 729-08-00200 | Mounting (3 1/2" Size Post) | 35 | EACH | 2,000.00 | 70,000.00 | 1,300.00 | 45,500.00 | 1,275.00 | 44,625.00 | 1,254.48 | 43,906.73 | | 0109 | 729-08-00220 | Mounting (3 1/2" Size Post)(Median Barrier Mount) | 12 | EACH | 2,350.00 | 28,200.00 | 1,700.00 | 20,400.00 | 1,750.00 | 21,000.00 | 2,454.41 | 29,452.96 | | 0110 | 729-08-00300 | Mounting (5" Size Post) | 21 | EACH | 1,600.00 | 33,600.00 | 1,700.00 | 35,700.00 | 1,650.00 | 34,650.00 | 1,827.17 | 38,370.65 | | 0111 | 729-08-00310 | Mounting (5" Size Post)(Structure Mount) | 1 | EACH | 9,000.00 | 9,000.00 | 5,051.02 | 5,051.02 | 4,950.00 | 4,950.00 | 5,394.25 | 5,394.25 | | 0112 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 62 | EACH | 1,600.00 | 99,200.00 | 1,500.00 | 93,000.00 | 1,525.00 | 94,550.00 | 1,772.63 | 109,903.12 | | 0113 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 32 | EACH | 2,200.00 | 70,400.00 | 1,900.00 | 60,800.00 | 1,925.00 | 61,600.00 | 2,208.97 | 70,687.07 | | 0114 | 729-08-00800 | Mounting (W8 x 24 Size Post) | 14 | EACH | 2,600.00 | 36,400.00 | 2,700.00 | 37,800.00 | 2,625.00 | 36,750.00 | 2,934.39 | 41,081.42 | | 0115 | 729-11-00100 | Mounting (Overhead Cantilever) (Ground Mounted) | 2 | EACH | 42,500.00 | 85,000.00 | 40,000.00 | 80,000.00 | 40,050.00 | 80,100.00 | 56,178.78 | 112,357.55 | | 0116 | 729-16-00200 | Object Marker Assembly (Type 2) | 12 | EACH | 90.00 | 1,080.00 | 45.00 | 540.00 | 45.00 | 540.00 | 49.09 | 589.06 | | 0117 | 729-16-00300 | Object Marker Assembly (Type 3) | 35 | EACH | 100.00 | 3,500.00 | 75.00 | 2,625.00 | 75.00 | 2,625.00 | 81.81 | 2,863.49 | | 0118 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 5 | EACH | 300.00 | 1,500.00 | 340.00 | 1,700.00 | 340.00 | 1,700.00 | 354.53 | 1,772.63 | | 0119 | 729-18-00200 | Milepost Assembly (Structure Mounted) (Secondary) | 8 | EACH | 300.00 | 2,400.00 | 350.00 | 2,800.00 | 350.00 | 2,800.00 | 436.34 | 3,490.72 | | 0120 | 729-20-00600 | Footings for Overhead Mountings (Cantilever) | 2 | EACH | 45,000.00 | 90,000.00 | 44,000.00 | 88,000.00 | 43,750.00 | 87,500.00 | 50,539.08 | 101,078.16 | | 0121 | 731-02-00100 | Reflectorized Raised Pavement Markers | 11,720 | EACH | 15.00 | 175,800.00 | 6.00 | 70,320.00 | 12.50 | 146,500.00 | 6.00 | 70,320.00 | | 0122 | 731-02-00100 | Reflectorized Raised Pavement Markers (STA. 99+12.46 - STA. 102+17.82) | 31 | EACH | 8.00 | 248.00 | 6.00 | 186.00 | 12.50 | 387.50 | 6.00 | 186.00 | | 0123 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 1,611 | LNFT | 23.00 | 37,053.00 | 11.00 | 17,721.00 | 20.00 | 32,220.00 | 12.00 | 19,330.39 | | 0124 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 41.068 | MILE | 7,500.00 | 308,010.00 | 3,300.00 | 135,524.40 | 6,500.00 | 266,942.00 | 3,599.81 | 147,836.79 | | 0125 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) (STA. 99+12.46 - STA. 102+17.82) | 0.116 | MILE | 7,250.00 | 841.00 | 3,400.00 | 394.40 | 6,200.00 | 719.20 | 3,599.81 | 417.58 | | 0126 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 2.721 | MILE | 29,000.00 | 78,909.00 | 14,000.00 | 38,094.00 | 25,000.00 | 68,025.00 | 14,726.48 | 40,070.74 | | 0127 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 38.652 | MILE | 2,900.00 | 112,090.80 | 1,300.00 | 50,247.60 | 2,500.00 | 96,630.00 | 1,390.83 | 53,758.52 | | 0128 | 732-03-02002 | Plastic Pav't Striping (Broken) (4" Width) (Thermo 90 mil)(Black and White Cont) | 1.012 | MILE | 18,000.00 | 18,216.00 | 2,500.00 | 2,530.00 | 15,000.00 | 15,180.00 | 2,727.13 | 2,759.85 | | 0129 | 732-03-02002 | Plastic Pav't Striping (Broken) (4" Width) (Thermo 90 mil)(Black and White Cont) (STA. 99+12.46 - STA. 102+17.82) | 0.116 | MILE | 16,500.00 | 1,914.00 | 2,600.00 | 301.60 | 14,250.00 | 1,653.00 | 2,727.13 | 316.35 | | 0130 | 732-03-02012 | Plastic Pavement Striping (Dotted Line)(4" W)(3' L)(Thermo 90 mil) | 0.337 | MILE | 3,400.00 | 1,145.80 | 2,200.00 | 741.40 | 3,000.00 | 1,011.00 | 2,399.87 | 808.76 | | 0131 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 1.461 | MILE | 8,600.00 | 12,564.60 | 10,000.00 | 14,610.00 | 7,500.00 | 10,957.50 | 11,126.67 | 16,256.06 | | 0132 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | EACH | 465.00 | 930.00 | 800.00 | 1,600.00 | 400.00 | 800.00 | 872.68 | 1,745.36 | | 0133 | 732-04-05040 | Plastic Pavement Legends and Symbols (EXIT ONLY) | 2 | EACH | 870.00 | 1,740.00 | 1,000.00 | 2,000.00 | 750.00 | 1,500.00 | 1,090.85 | 2,181.70 | | 0134 | 732-05-00100 | Removal of Existing Markings | 20.381 | MILE | 8,700.00 | 177,314.70 | 5,900.00 | 120,247.90 | 5,000.00 | 101,905.00 | 6,381.47 | 130,060.80 | | 0135 | 739-01-00100 | Hydro-Seeding | 91.52 | ACRE | 1,710.00 | 156,499.20 | 1,725.00 | 157,872.00 | 1,700.00 | 155,584.00 | 1,891.53 | 173,113.19 | | 0136 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 1,000,000.00 | 1,000,000.00 | 2,000,000.00 | 2,000,000.00 | 2,000,000.00 | 2,000,000.00 | | 0138 | 802-03-00100 | Temporary Sheeting (Steel) | 42,456 | SQFT | 35.00 | 1,485,960.00 | 38.00 | 1,613,328.00 | 30.00 | 1,273,680.00 | 55.00 | 2,335,080.00 | | 0139 | 804-01-00600 | Precast Concrete Piles (24") | 47,141 | LNFT | 200.00 | 9,428,200.00 | 140.00 | 6,599,740.00 | 148.00 | 6,976,868.00 | 135.00 | 6,364,035.00 | | 0140 | 804-01-00700 | Precast Concrete Piles (30") | 14,624 | LNFT | 265.00 | 3,875,360.00 | 160.00 | 2,339,840.00 | 180.00 | 2,632,320.00 | 185.00 | 2,705,440.00 | | 0141 | 804-10-00600 | Precast Concrete Indicator Piles (24") | 5 | EACH | 40,000.00 | 200,000.00 | 200,000.00 | 1,000,000.00 | 40,000.00 | 200,000.00 | 300,000.00 | 1,500,000.00 | | 0142 | 804-10-00700 | Precast Concrete Indicator Piles (30") | 1 | EACH | 50,000.00 | 50,000.00 | 400,000.00 | 400,000.00 | 45,000.00 | 45,000.00 | 400,000.00 | 400,000.00 | | 0143 | 804-14-00100 | Dynamic Monitoring Assistance | 52 | EACH | 2,500.00 | 130,000.00 | 2,250.00 | 117,000.00 | 1,450.00 | 75,400.00 | 3,152.83 | 163,947.26 | | 0144 | 804-15-00100 | Dynamic Monitoring Instrumentation | 1 | LUMP | 200,000.00 | 200,000.00 | 9,000.00 | 9,000.00 | 3,000.00 | 3,000.00 | 10,000.00 | 10,000.00 | | 0145 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 1,236,315.00 | 1,236,315.00 | 200,000.00 | 200,000.00 | 15,000.00 | 15,000.00 | 100,000.00 | 100,000.00 | | 0146 | 804-18-00100 | Vibration Monitoring | 10 | DAY | 15,000.00 | 150,000.00 | 10,000.00 | 100,000.00 | 950.00 | 9,500.00 | 10,908.50 | 109,085.00 | | 0147 | 805-01-00100 | Class A1 Concrete (Slab Span) | 4,169.53 | CUYD | 700.00 | 2,918,671.00 | 750.00 | 3,127,147.50 | 900.00 | 3,752,577.00 | 2,200.00 | 9,172,966.00 | | 0148 | 805-01-00200 | Class A1 Concrete (Deck) | 3,748.24 | CUYD | 950.00 | 3,560,828.00 | 940.00 | 3,523,345.60 | 850.00 | 3,186,004.00 | 1,800.00 | 6,746,832.00 | | 0149 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 2,726.59 | CUYD | 1,250.00 | 3,408,237.50 | 1,250.00 | 3,408,237.50 | 1,200.00 | 3,271,908.00 | 2,500.00 | 6,816,475.00 | | 0150 | 805-01-00900 | Class A1 Concrete RETAINING WALL (STA. 547+67.08 - STA. 548+57.08) | 15.03 | CUYD | 2,500.00 | 37,575.00 | 1,900.00 | 28,557.00 | 5,000.00 | 75,150.00 | 3,000.00 | 45,090.00 | | 0151 | 805-08-01200 | Precast-Prestressed Concrete Girder (Type LG-36) | 12,376 | LNFT | 250.00 | 3,094,000.00 | 400.00 | 4,950,400.00 | 240.00 | 2,970,240.00 | 375.00 | 4,641,000.00 | | 0152 | 805-16-00100 | Reinforced Concrete Box Culverts (Extension) (4' x 4') | 225 | LNFT | 1,000.00 | 225,000.00 | 300.00 | 67,500.00 | 1,200.00 | 270,000.00 | 700.00 | 157,500.00 | | 0153 | 805-16-00600 | Reinforced Concrete Box Culverts (Extension) (5' x 5') | 150 | LNFT | 1,200.00 | 180,000.00 | 400.00 | 60,000.00 | 1,200.00 | 180,000.00 | 825.00 | 123,750.00 | | 0154 | 805-16-00800 | Reinforced Concrete Box Culverts (Extension) (7' x 5') | 12 | LNFT | 4,500.00 | 54,000.00 | 1,250.00 | 15,000.00 | 4,000.00 | 48,000.00 | 2,400.00 | 28,800.00 | | 0155 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 300,706 | SQFT | 3.00 | 902,118.00 | 1.00 | 300,706.00 | 1.00 | 300,706.00 | 3.00 | 902,118.00 | | 0156 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 310,813 | SQFT | 0.60 | 186,487.80 | 0.40 | 124,325.20 | 1.00 | 310,813.00 | 0.50 | 155,406.50 | | 0157 | 806-01-00100 | Deformed Reinforcing Steel | 2,339,336 | LB | 1.25 | 2,924,170.00 | 1.25 | 2,924,170.00 | 1.00 | 2,339,336.00 | 1.10 | 2,573,269.60 | | 0158 | 806-03-00100 | Deformed Reinforcing Steel Mechanical Splice (BUTT SPLICE) | 1,226 | EACH | 75.00 | 91,950.00 | 75.00 | 91,950.00 | 45.00 | 55,170.00 | 75.00 | 91,950.00 | | 0159 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 114 | LUMP | 2,500.00 | 2,500.00 | 23,000.00 | 23,000.00 | 1,600.00 | 1,600.00 | 15,000.00 | 15,000.00 | | 0160 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 6,571 | LNFT | 65.00 | 427,115.00 | 120.00 | 788,520.00 | 120.00 | 788,520.00 | 175.00 | 1,149,925.00 | | 0161 | 810-05-00330 | Concrete Roadway Barrier (Double Face) (42 inch Height) | 23,632 | LNFT | 120.00 | 2,835,840.00 | 145.00 | 3,426,640.00 | 170.00 | 4,017,440.00 | 185.00 | 4,371,920.00 | | 0162 | 810-05-00400 | Concrete Roadway Barrier (DOUBLE FACE) (TRANSITION) | 3,753 | LNFT | 265.00 | 994,545.00 | 300.00 | 1,125,900.00 | 300.00 | 1,125,900.00 | 400.00 | 1,501,200.00 | | 0163 | 810-05-00400 | Concrete Roadway Barrier (WITH FOOTING) | 3,708 | LNFT | 465.00 | 1,724,220.00 | 470.00 | 1,742,760.00 | 400.00 | 1,483,200.00 | 450.00 | 1,668,600.00 | | 0164 | 810-06-00100 | Concrete Pier Protection System (Vehicle) Median Pier Protection | 838 | LNFT | 635.00 | 532,130.00 | 630.00 | 527,940.00 | 700.00 | 586,600.00 | 900.00 | 754,200.00 | | 0165 | 810-06-00100 | Concrete Pier Protection System (Vehicle) Outside Pier Protection | 532 | LNFT | 475.00 | 252,700.00 | 370.00 | 196,840.00 | 700.00 | 372,400.00 | 700.00 | 372,400.00 | | 0166 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 54,048 | SQFT | 50.00 | 2,702,400.00 | 80.00 | 4,323,840.00 | 60.00 | 3,242,880.00 | 70.00 | 3,783,360.00 | | 0167 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 3,570 | SFIN | 52.00 | 185,640.00 | 75.00 | 267,750.00 | 65.00 | 232,050.00 | 80.00 | 285,600.00 | | 0168 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 2,600 | SFIN | 65.00 | 169,000.00 | 90.00 | 234,000.00 | 60.00 | 156,000.00 | 78.00 | 202,800.00 | | 0169 | 815-02-00100 | Sealed Expansion Joint (End Dams and Preformed Neoprene Seal) | 560 | LNFT | 200.00 | 112,000.00 | 500.00 | 280,000.00 | 325.00 | 182,000.00 | 400.00 | 224,000.00 | | 0170 | 815-03-00300 | Joint Seal (Poured) | 5,265 | LNFT | 30.00 | 157,950.00 | 13.00 | 68,445.00 | 11.00 | 57,915.00 | 27.00 | 142,155.00 | | 0171 | 816-02-00100 | Bridge End Drain System (Open Drain) | 18 | EACH | 4,000.00 | 72,000.00 | 9,400.00 | 169,200.00 | 7,500.00 | 135,000.00 | 4,500.00 | 81,000.00 | | 0172 | 822-01-00100 | Trenching and Backfilling | 14,600 | LNFT | 1.00 | 14,600.00 | 5.00 | 73,000.00 | 5.00 | 73,000.00 | 4.94 | 72,153.20 | | 0173 | 822-02-00100 | Conduit w Conductors (PVC/HDPE) (3/4") (1#2 BARE STRANDED GROUND) | 400 | LNFT | 6.00 | 2,400.00 | 5.00 | 2,000.00 | 4.50 | 1,800.00 | 4.94 | 1,976.80 | | 0174 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (2#2, 1#2 BARE STRANDED GROUND) | 50 | LNFT | 12.00 | 600.00 | 10.00 | 500.00 | 6.00 | 300.00 | 11.24 | 561.80 | | 0175 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (2#8, 1#8 BARE STRANDED GROUND) | 1,150 | LNFT | 9.00 | 10,350.00 | 8.00 | 9,200.00 | 6.00 | 6,900.00 | 8.57 | 9,860.10 | | 0176 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (EMPTY HDPE DUCT WITH PULL LINE) | 13,400 | LNFT | 6.00 | 80,400.00 | 5.00 | 67,000.00 | 6.00 | 80,400.00 | 5.57 | 74,691.60 | | 0177 | 822-02-01000 | Conduit w Conductors (PVC/HDPE) (6") (VERTICAL CONDUIT CASING) | 500 | LNFT | 45.00 | 22,500.00 | 36.00 | 18,000.00 | 36.00 | 18,000.00 | 39.93 | 19,962.50 | | 0178 | 822-04-00200 | Jacked or Bored Casing (6" Dia) (PVC/HDPE) | 1,100 | LNFT | 61.00 | 67,100.00 | 53.00 | 58,300.00 | 45.00 | 49,500.00 | 57.46 | 63,200.50 | | 0179 | 822-05-00700 | Light Pole (40') (Alum) (Single Arm) | 6 | EACH | 6,100.00 | 36,600.00 | 5,200.00 | 31,200.00 | 5,700.00 | 34,200.00 | 5,715.39 | 34,292.33 | | 0180 | 822-07-01900 | Luminaire (400 Watt) (High Pressure Sodium) | 6 | EACH | 775.00 | 4,650.00 | 660.00 | 3,960.00 | 662.00 | 3,972.00 | 722.24 | 4,333.45 | | 0181 | 822-07-02500 | Luminaire (1000 Watt) (High Pressure Sodium) | 32 | EACH | 2,200.00 | 70,400.00 | 1,900.00 | 60,800.00 | 1,220.00 | 39,040.00 | 2,025.80 | 64,825.47 | | 0182 | 822-08-00200 | Electrical Service Point (Structure) | 1 | EACH | 27,511.00 | 27,511.00 | 24,000.00 | 24,000.00 | 9,800.00 | 9,800.00 | 50,000.00 | 50,000.00 | | 0183 | 822-09-00100 | Electrical System (MEDIAN POLE FOUNDATIONS & ANCHOR BOLTS) | 1 | LUMP | 85,000.00 | 85,000.00 | 72,000.00 | 72,000.00 | 72,000.00 | 72,000.00 | 100,000.00 | 100,000.00 | | 0184 | 822-09-00100 | Electrical System (Temporary Weigh-In-Motion Station) | 1 | LUMP | 56,000.00 | 56,000.00 | 65,000.00 | 65,000.00 | 47,500.00 | 47,500.00 | 75,000.00 | 75,000.00 | | 0185 | 822-09-00100 | Electrical System Weigh-In-Motion (Components, Conduit and Conductors) | 1 | LUMP | 1,000,000.00 | 1,000,000.00 | 750,000.00 | 750,000.00 | 647,200.00 | 647,200.00 | 800,000.00 | 800,000.00 | | 0186 | 822-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 | 15,300.00 | 15,300.00 | 25,000.00 | 25,000.00 | | 0187 | 822-11-00100 | Removal and Disposal of Electrical Equipment (Weigh-In-Motion Signs) | 1 | LUMP | 15,000.00 | 15,000.00 | 12,000.00 | 12,000.00 | 12,300.00 | 12,300.00 | 20,000.00 | 20,000.00 | | 0188 | 822-11-00100 | Removal and Disposal of Electrical Equipment (Weigh-In-Motion) | 1 | LUMP | 11,000.00 | 11,000.00 | 9,000.00 | 9,000.00 | 9,170.00 | 9,170.00 | 15,000.00 | 15,000.00 | | 0189 | 822-12-00100 | Removal and Storage of Light Pole (Ground Mount) (40' STEEL) (SINGLE ARM) | 75 | EACH | 225.00 | 16,875.00 | 190.00 | 14,250.00 | 190.00 | 14,250.00 | 206.81 | 15,511.05 | | 0190 | 822-12-00100 | Removal and Storage of Light Pole (Ground Mount) (49' STEEL) | 6 | EACH | 250.00 | 1,500.00 | 215.00 | 1,290.00 | 215.00 | 1,290.00 | 234.63 | 1,407.79 | | 0191 | 822-13-00100 | Removal and Disposal of Light Pole Foundation (HIGH MAST) | 1 | EACH | 10,000.00 | 10,000.00 | 8,200.00 | 8,200.00 | 8,200.00 | 8,200.00 | 8,945.89 | 8,945.89 | | 0192 | 822-13-00100 | Removal and Disposal of Light Pole Foundation (LOW MAST) | 56 | EACH | 410.00 | 22,960.00 | 350.00 | 19,600.00 | 350.00 | 19,600.00 | 382.21 | 21,403.87 | | 0193 | 822-14-00100 | Removal and Disposal of Luminaire | 113 | EACH | 67.00 | 7,571.00 | 57.00 | 6,441.00 | 57.00 | 6,441.00 | 62.29 | 7,038.54 | | 0194 | 822-15-00700 | Relocate Light Poles (40') (Aluminum) (Single Arm) | 2 | EACH | 3,500.00 | 7,000.00 | 3,000.00 | 6,000.00 | 3,000.00 | 6,000.00 | 3,265.85 | 6,531.70 | | 0195 | 822-15-02100 | Relocate Light Poles (HIGH MAST) | 1 | EACH | 150,000.00 | 150,000.00 | 125,000.00 | 125,000.00 | 125,000.00 | 125,000.00 | 136,442.73 | 136,442.73 | | 0196 | 822-16-00100 | Underground Junction Box (12" x 12") | 8 | EACH | 550.00 | 4,400.00 | 470.00 | 3,760.00 | 470.00 | 3,760.00 | 513.44 | 4,107.53 | | 0197 | 822-16-00200 | Underground Junction Box (11" x 18") | 63 | EACH | 600.00 | 37,800.00 | 500.00 | 31,500.00 | 515.00 | 32,445.00 | 562.68 | 35,448.97 | | 0198 | 822-16-00300 | Underground Junction Box (13" x 24") | 8 | EACH | 700.00 | 5,600.00 | 580.00 | 4,640.00 | 580.00 | 4,640.00 | 635.61 | 5,084.85 | | 0199 | 822-19-00100 | Modular Breakaway Cable System | 6 | EACH | 2,500.00 | 15,000.00 | 2,000.00 | 12,000.00 | 2,000.00 | 12,000.00 | 2,179.51 | 13,077.04 | | 0200 | 822-21-00100 | Duct Marker (Concrete) | 7 | EACH | 500.00 | 3,500.00 | 380.00 | 2,660.00 | 382.84 | 2,679.88 | 417.62 | 2,923.35 | | 0201 | 822-22-00300 | Underground Marker Tape (6")(Detectable) | 1,200 | LNFT | 0.75 | 900.00 | 0.60 | 720.00 | 0.63 | 756.00 | 0.69 | 824.40 | | 0202 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 3,936 | LNFT | 2.00 | 7,872.00 | 1.50 | 5,904.00 | 2.00 | 7,872.00 | 1.64 | 6,439.30 | | 0203 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 6,560 | LNFT | 2.00 | 13,120.00 | 3.00 | 19,680.00 | 1.00 | 6,560.00 | 0.55 | 3,575.20 | | 0204 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 1,090,613 | INLF | 0.20 | 218,122.60 | 0.20 | 218,122.60 | 0.63 | 687,086.19 | 0.33 | 356,630.45 | | 0205 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 464,288 | INLF | 0.50 | 232,144.00 | 0.30 | 139,286.40 | 2.00 | 928,576.00 | 1.09 | 506,538.21 | | 0206 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 66,733 | INLF | 0.75 | 50,049.75 | 0.60 | 40,039.80 | 0.63 | 42,041.79 | 0.98 | 65,398.34 | | 0207 | NS-602-00011 | Expansion Joint Rehabilitation | 57 | LNFT | 500.00 | 28,500.00 | 730.00 | 41,610.00 | 600.00 | 34,200.00 | 340.28 | 19,395.90 | | 0208 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 9 | EACH | 8,000.00 | 72,000.00 | 7,000.00 | 63,000.00 | 6,950.00 | 62,550.00 | 9,054.06 | 81,486.50 | | 0209 | NS-700-00820 | Impact Attenuator Relocation (Construction Zone) | 49 | EACH | 1,500.00 | 73,500.00 | 1,300.00 | 63,700.00 | 1,250.00 | 61,250.00 | 1,636.28 | 80,177.48 | | 0210 | NS-704-00001 | High Tension Cable Barrier | 12,764 | LNFT | 11.00 | 140,404.00 | 10.00 | 127,640.00 | 9.75 | 124,449.00 | 11.45 | 146,198.86 | | 0211 | NS-704-00002 | Cable Barrier Gated End Terminal | 10 | EACH | 4,500.00 | 45,000.00 | 4,000.00 | 40,000.00 | 4,000.00 | 40,000.00 | 3,817.98 | 38,179.75 | | 0212 | NS-704-00003 | Concrete Strip | 17,019 | SQYD | 60.00 | 1,021,140.00 | 54.00 | 919,026.00 | 50.00 | 850,950.00 | 49.09 | 835,428.67 | | 0213 | NS-729-00031 | Breakaway Square Tubing Sign Support (Surface Mount) | 30 | EACH | 175.00 | 5,250.00 | 400.00 | 12,000.00 | 395.00 | 11,850.00 | 436.34 | 13,090.20 | | 0214 | NS-822-00001 | High Mast Luminaire Lowering Device Replacement | 4 | EACH | 22,000.00 | 88,000.00 | 17,000.00 | 68,000.00 | 17,000.00 | 68,000.00 | 18,470.69 | 73,882.75 | | 0215 | 721-01-00100 | Mowing | 24 | CYCL | 10,000.00 | 240,000.00 | 24,300.00 | 583,200.00 | 5,800.00 | 139,200.00 | 5,000.00 | 120,000.00 | | 0216 | 805-16-02700 | Reinforced Concrete Box Culverts (Extension) (3' x 3') | 18 | LNFT | 1,602.00 | 28,836.00 | 650.00 | 11,700.00 | 3,000.00 | 54,000.00 | 1,400.00 | 25,200.00 | | 0217 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 1,182 | SQYD | 90.00 | 106,380.00 | 95.00 | 112,290.00 | 80.00 | 94,560.00 | 110.00 | 130,020.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 152,221,212.63 | | 154,850,853.96 | | 153,274,566.30 | | 192,908,688.15 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - GILCHRIST CONSTRUCTION CO. LLC | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 32.25 | LUMP | 3,500,000.00 | 3,500,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 250,000.00 | 250,000.00 | | 0003 | 202-02-00030 | Removal of (CONCRETE MEDIAN BARRIER) | 2,412 | LNFT | 100.00 | 241,200.00 | | 0004 | 202-02-02020 | Removal of Asphalt Pavement | 130,605.7 | SQYD | 4.50 | 587,725.65 | | 0005 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 166,329.9 | SQYD | 4.50 | 748,484.55 | | 0006 | 202-02-03010 | Removal of Base – Recycled PCC or Stone | 53,018.4 | SQYD | 4.50 | 238,582.80 | | 0007 | 202-02-04501 | Removal of Bridge (STA. 184+61.63, 69.5' X 722' CONCRETE DECK GIRDER BRIDGE) | 50,179 | LUMP | 1,000,000.00 | 1,000,000.00 | | 0008 | 202-02-04501 | Removal of Bridge (STA. 353+35.49 EB, 45.5' X 100' SLAB SPAN BRIDGE) | 4,550 | LUMP | 100,000.00 | 100,000.00 | | 0009 | 202-02-04501 | Removal of Bridge (STA. 353+35.59 WB, 45.5' X 100' SLAB SPAN BRIDGE) | 4,547 | LUMP | 100,000.00 | 100,000.00 | | 0010 | 202-02-04501 | Removal of Bridge (STA. 527+39.64 WB, 54.75' X 240' SLAB SPAN BRIDGE) | 13,140 | LUMP | 200,000.00 | 200,000.00 | | 0011 | 202-02-04501 | Removal of Bridge (STA. 528+05.89 EB, 42.75' X 240' SLAB SPAN BRIDGE) | 10,260 | LUMP | 200,000.00 | 200,000.00 | | 0012 | 202-02-04501 | Removal of Bridge (STA. 544+00.20 EB, 45.75' X 140' SLAB SPAN BRIDGE) | 6,405 | LUMP | 100,000.00 | 100,000.00 | | 0013 | 202-02-04501 | Removal of Bridge (STA. 544+00.27 WB, 45.75' X 140' SLAB SPAN BRIDGE) | 6,405 | LUMP | 100,000.00 | 100,000.00 | | 0014 | 202-02-04501 | Removal of Bridge (STA. 575+76.19 EB, 45.75' X 120' SLAB SPAN BRIDGE) | 5,490 | LUMP | 100,000.00 | 100,000.00 | | 0015 | 202-02-04501 | Removal of Bridge (STA. 576+64.97 WB, 45.75' X 120' SLAB SPAN BRIDGE) | 5,490 | LUMP | 100,000.00 | 100,000.00 | | 0016 | 202-02-06101 | Removal of Concrete Median Barrier and Footing | 5,532 | SQYD | 100.00 | 553,200.00 | | 0017 | 202-02-14500 | Removal of Guard Rail | 15,460.7 | LNFT | 6.00 | 92,764.20 | | 0018 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 10,636 | SQYD | 20.00 | 212,720.00 | | 0019 | 202-02-38220 | Removal of Sign Supports | 183 | EACH | 260.00 | 47,580.00 | | 0020 | 202-02-38300 | Removal of Sign and U-Channel Post | 32 | EACH | 11.00 | 352.00 | | 0021 | 202-02-38360 | Removal of Sign Faces | 123 | EACH | 55.00 | 6,765.00 | | 0022 | 203-01-00100 | General Excavation | 149,907 | CUYD | 10.00 | 1,499,070.00 | | 0023 | 203-02-00100 | Drainage Excavation | 6,737 | CUYD | 24.00 | 161,688.00 | | 0024 | 203-03-00100 | Embankment | 357,869 | CUYD | 35.00 | 12,525,415.00 | | 0025 | 203-04-00300 | Nonplastic Embankment (Stone) | 1,147 | CUYD | 200.00 | 229,400.00 | | 0026 | 203-08-00100 | Geotextile Fabric | 4,009 | SQYD | 2.00 | 8,018.00 | | 0027 | 203-10-00100 | Cleaning Existing Ditches | 5,000 | LNFT | 10.00 | 50,000.00 | | 0028 | 204-02-00100 | Temporary Hay Bales | 140 | EACH | 23.00 | 3,220.00 | | 0029 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 664 | EACH | 120.00 | 79,680.00 | | 0030 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 55 | EACH | 1,100.00 | 60,500.00 | | 0031 | 204-06-00100 | Temporary Silt Fencing | 164,831 | LNFT | 3.25 | 535,700.75 | | 0032 | 204-07-00100 | Temporary Stone Construction Entrance | 6 | EACH | 5,000.00 | 30,000.00 | | 0033 | 302-02-04070 | Class II Base Course (4" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 180,220.4 | SQYD | 13.00 | 2,342,865.20 | | 0034 | 302-02-06010 | Class II Base Course (6" Thick) (Soil Cement) | 326,774.8 | SQYD | 13.25 | 4,329,766.10 | | 0035 | 302-02-10075 | Class II Base Course (10" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 155,083.2 | SQYD | 29.00 | 4,497,412.80 | | 0036 | 302-02-14070 | Class II Base Course (14" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 73,150.3 | SQYD | 40.00 | 2,926,012.00 | | 0037 | 302-02-16070 | Class II Base Course (16" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 6,584.1 | SQYD | 55.00 | 362,125.50 | | 0038 | 302-02-18070 | Class II Base Course (18" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 18,262.1 | SQYD | 70.00 | 1,278,347.00 | | 0039 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 429,771 | SQYD | 11.80 | 5,071,297.80 | | 0040 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 39 | CUYD | 200.00 | 7,800.00 | | 0041 | 402-02-00100 | Mainline Traffic Maintenance Surfacing (Hard) | 300 | SQYD | 60.00 | 18,000.00 | | 0042 | 501-03-00100 | Thin Asphalt Concrete (OGFC) | 26,110.9 | TON | 150.00 | 3,916,635.00 | | 0043 | 502-01-00100 | Asphalt Concrete | 287,733.4 | TON | 98.00 | 28,197,873.20 | | 0044 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,147.2 | TON | 200.00 | 229,440.00 | | 0045 | 509-01-00100 | Milling Asphalt Pavement | 271,419 | SQYD | 2.00 | 542,838.00 | | 0046 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,985 | SQYD | 150.00 | 297,750.00 | | 0047 | 601-01-01100 | Portland Cement Concrete Pavement (13" Thick) | 17,571.6 | SQYD | 130.00 | 2,284,308.00 | | 0048 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 20 | EACH | 325.00 | 6,500.00 | | 0049 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 1,300 | LNFT | 8.00 | 10,400.00 | | 0050 | 701-01-01003 | Cross Drain Pipe (24" RCP/RPVCP/CPEPDW) | 128 | LNFT | 175.00 | 22,400.00 | | 0051 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 634 | LNFT | 200.00 | 126,800.00 | | 0052 | 701-02-01060 | Cross Drain Pipe Arch (42" Equiv. RCPA) | 400 | LNFT | 215.00 | 86,000.00 | | 0053 | 701-02-01100 | Cross Drain Pipe Arch (54" Equiv. RCPA) | 64 | LNFT | 350.00 | 22,400.00 | | 0054 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 781 | LNFT | 130.00 | 101,530.00 | | 0055 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 565 | LNFT | 150.00 | 84,750.00 | | 0056 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 471 | LNFT | 130.00 | 61,230.00 | | 0057 | 701-05-02061 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CMP) (CMP IS NOT ALLOWED) | 40 | LNFT | 90.00 | 3,600.00 | | 0058 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 66 | LNFT | 170.00 | 11,220.00 | | 0059 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 580 | LNFT | 200.00 | 116,000.00 | | 0060 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 154 | LNFT | 215.00 | 33,110.00 | | 0061 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 48 | LNFT | 240.00 | 11,520.00 | | 0062 | 701-11-01020 | Reinforced Concrete Pipe Arch (Extension) (18" Equiv.) | 342 | LNFT | 85.00 | 29,070.00 | | 0063 | 701-14-00100 | Cleaning Existing Pipes | 5,000 | LNFT | 11.00 | 55,000.00 | | 0064 | 701-15-00100 | Concrete Collar | 38 | EACH | 1,000.00 | 38,000.00 | | 0065 | 702-02-00200 | Manholes (R-CB-11) | 11 | EACH | 7,000.00 | 77,000.00 | | 0066 | 702-02-00900 | Manholes (MH-14X Open) | 11 | EACH | 30,000.00 | 330,000.00 | | 0067 | 702-03-00100 | Catch Basins (CB-01) | 22 | EACH | 5,200.00 | 114,400.00 | | 0068 | 702-03-00200 | Catch Basins (CB-02) | 1 | EACH | 6,200.00 | 6,200.00 | | 0069 | 702-04-00200 | Adjusting Catch Basins | 2 | EACH | 3,200.00 | 6,400.00 | | 0070 | 702-04-01000 | Capping Existing Catch Basin or Manhole | 5 | EACH | 2,200.00 | 11,000.00 | | 0071 | 702-07-00100 | Cross Drain Safety End (Type 1) | 14 | EACH | 3,100.00 | 43,400.00 | | 0072 | 702-07-00200 | Cross Drain Safety End (Type 2) | 2 | EACH | 13,500.00 | 27,000.00 | | 0073 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 4,262.9 | LNFT | 25.00 | 106,572.50 | | 0074 | 704-03-00300 | Blocked Out Guard Rail – 31”, (3’-1 ½ ” Post Spacing) | 206.8 | LNFT | 36.00 | 7,444.80 | | 0075 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 29.7 | LNFT | 95.00 | 2,821.50 | | 0076 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 425 | LNFT | 90.00 | 38,250.00 | | 0077 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 16 | EACH | 3,200.00 | 51,200.00 | | 0078 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 11 | EACH | 2,800.00 | 30,800.00 | | 0079 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 399.4 | SQYD | 125.00 | 49,925.00 | | 0080 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 417 | SQYD | 70.00 | 29,190.00 | | 0081 | 710-01-00100 | Flowable Fill | 38.76 | CUYD | 300.00 | 11,628.00 | | 0082 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 125 | SQYD | 130.00 | 16,250.00 | | 0083 | 711-04-00100 | Geotextile Fabric | 125 | SQYD | 4.00 | 500.00 | | 0084 | 712-04-00100 | Flexible Revetment | 14,682 | SQYD | 100.00 | 1,468,200.00 | | 0085 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,000,000.00 | 4,000,000.00 | | 0086 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 311.317 | MILE | 2,500.00 | 778,292.50 | | 0087 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) (STA. 99+12.46 - STA. 102+17.82) | 0.174 | MILE | 5,000.00 | 870.00 | | 0088 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 129,361 | EACH | 4.25 | 549,784.25 | | 0089 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers (STA. 99+12.46 - STA. 102+17.82) | 92 | EACH | 4.25 | 391.00 | | 0090 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 3,212 | EACH | 2,400.00 | 7,708,800.00 | | 0091 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 13,857 | EACH | 100.00 | 1,385,700.00 | | 0092 | 713-11-00100 | Portable Changeable Message Signs | 4 | EACH | 35,000.00 | 140,000.00 | | 0093 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 22,397 | SQYD | 1.25 | 27,996.25 | | 0094 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 1,201 | SQYD | 1.40 | 1,681.40 | | 0095 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 1,264 | SQYD | 1.40 | 1,769.60 | | 0096 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 100,000.00 | 100,000.00 | | 0097 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 37.182 | MILE | 925.00 | 34,393.35 | | 0098 | 725-01-00100 | Temporary Detour Roads | 12,764.2 | SQYD | 200.00 | 2,552,840.00 | | 0099 | 726-01-00100 | Bedding Material | 1,101.6 | CUYD | 100.00 | 110,160.00 | | 0100 | 727-01-00100 | Mobilization | 1 | LUMP | 18,300,000.00 | 18,300,000.00 | | 0101 | 729-01-00100 | Sign (Type A) | 1,484.6 | SQFT | 28.00 | 41,568.80 | | 0102 | 729-02-00100 | Sign (Type B) | 27 | SQFT | 42.00 | 1,134.00 | | 0103 | 729-04-00100 | Sign (Type D) | 4,469 | SQFT | 30.00 | 134,070.00 | | 0104 | 729-04-00103 | Sign (Type D)(Relocate) | 161.3 | SQFT | 50.00 | 8,065.00 | | 0105 | 729-05-00100 | Sign (Type E) | 288 | SQFT | 33.00 | 9,504.00 | | 0106 | 729-06-00100 | Sign (Overhead Mounted) | 293 | SQFT | 33.00 | 9,669.00 | | 0107 | 729-08-00100 | Mounting (2 1/2" Size Post) | 2 | EACH | 1,000.00 | 2,000.00 | | 0108 | 729-08-00200 | Mounting (3 1/2" Size Post) | 35 | EACH | 1,400.00 | 49,000.00 | | 0109 | 729-08-00220 | Mounting (3 1/2" Size Post)(Median Barrier Mount) | 12 | EACH | 1,850.00 | 22,200.00 | | 0110 | 729-08-00300 | Mounting (5" Size Post) | 21 | EACH | 1,750.00 | 36,750.00 | | 0111 | 729-08-00310 | Mounting (5" Size Post)(Structure Mount) | 1 | EACH | 5,200.00 | 5,200.00 | | 0112 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 62 | EACH | 1,650.00 | 102,300.00 | | 0113 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 32 | EACH | 2,100.00 | 67,200.00 | | 0114 | 729-08-00800 | Mounting (W8 x 24 Size Post) | 14 | EACH | 2,700.00 | 37,800.00 | | 0115 | 729-11-00100 | Mounting (Overhead Cantilever) (Ground Mounted) | 2 | EACH | 42,000.00 | 84,000.00 | | 0116 | 729-16-00200 | Object Marker Assembly (Type 2) | 12 | EACH | 50.00 | 600.00 | | 0117 | 729-16-00300 | Object Marker Assembly (Type 3) | 35 | EACH | 80.00 | 2,800.00 | | 0118 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 5 | EACH | 360.00 | 1,800.00 | | 0119 | 729-18-00200 | Milepost Assembly (Structure Mounted) (Secondary) | 8 | EACH | 400.00 | 3,200.00 | | 0120 | 729-20-00600 | Footings for Overhead Mountings (Cantilever) | 2 | EACH | 45,000.00 | 90,000.00 | | 0121 | 731-02-00100 | Reflectorized Raised Pavement Markers | 11,720 | EACH | 13.00 | 152,360.00 | | 0122 | 731-02-00100 | Reflectorized Raised Pavement Markers (STA. 99+12.46 - STA. 102+17.82) | 31 | EACH | 13.00 | 403.00 | | 0123 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 1,611 | LNFT | 22.00 | 35,442.00 | | 0124 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 41.068 | MILE | 6,700.00 | 275,155.60 | | 0125 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) (STA. 99+12.46 - STA. 102+17.82) | 0.116 | MILE | 6,500.00 | 754.00 | | 0126 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 2.721 | MILE | 26,000.00 | 70,746.00 | | 0127 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 38.652 | MILE | 2,700.00 | 104,360.40 | | 0128 | 732-03-02002 | Plastic Pav't Striping (Broken) (4" Width) (Thermo 90 mil)(Black and White Cont) | 1.012 | MILE | 16,000.00 | 16,192.00 | | 0129 | 732-03-02002 | Plastic Pav't Striping (Broken) (4" Width) (Thermo 90 mil)(Black and White Cont) (STA. 99+12.46 - STA. 102+17.82) | 0.116 | MILE | 16,000.00 | 1,856.00 | | 0130 | 732-03-02012 | Plastic Pavement Striping (Dotted Line)(4" W)(3' L)(Thermo 90 mil) | 0.337 | MILE | 3,200.00 | 1,078.40 | | 0131 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 1.461 | MILE | 7,800.00 | 11,395.80 | | 0132 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | EACH | 425.00 | 850.00 | | 0133 | 732-04-05040 | Plastic Pavement Legends and Symbols (EXIT ONLY) | 2 | EACH | 775.00 | 1,550.00 | | 0134 | 732-05-00100 | Removal of Existing Markings | 20.381 | MILE | 5,500.00 | 112,095.50 | | 0135 | 739-01-00100 | Hydro-Seeding | 91.52 | ACRE | 1,800.00 | 164,736.00 | | 0136 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000,000.00 | 2,000,000.00 | | 0138 | 802-03-00100 | Temporary Sheeting (Steel) | 42,456 | SQFT | 45.00 | 1,910,520.00 | | 0139 | 804-01-00600 | Precast Concrete Piles (24") | 47,141 | LNFT | 176.00 | 8,296,816.00 | | 0140 | 804-01-00700 | Precast Concrete Piles (30") | 14,624 | LNFT | 275.00 | 4,021,600.00 | | 0141 | 804-10-00600 | Precast Concrete Indicator Piles (24") | 5 | EACH | 250,000.00 | 1,250,000.00 | | 0142 | 804-10-00700 | Precast Concrete Indicator Piles (30") | 1 | EACH | 350,000.00 | 350,000.00 | | 0143 | 804-14-00100 | Dynamic Monitoring Assistance | 52 | EACH | 2,000.00 | 104,000.00 | | 0144 | 804-15-00100 | Dynamic Monitoring Instrumentation | 1 | LUMP | 100,000.00 | 100,000.00 | | 0145 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 250,000.00 | 250,000.00 | | 0146 | 804-18-00100 | Vibration Monitoring | 10 | DAY | 2,000.00 | 20,000.00 | | 0147 | 805-01-00100 | Class A1 Concrete (Slab Span) | 4,169.53 | CUYD | 1,500.00 | 6,254,295.00 | | 0148 | 805-01-00200 | Class A1 Concrete (Deck) | 3,748.24 | CUYD | 1,200.00 | 4,497,888.00 | | 0149 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 2,726.59 | CUYD | 1,500.00 | 4,089,885.00 | | 0150 | 805-01-00900 | Class A1 Concrete RETAINING WALL (STA. 547+67.08 - STA. 548+57.08) | 15.03 | CUYD | 2,000.00 | 30,060.00 | | 0151 | 805-08-01200 | Precast-Prestressed Concrete Girder (Type LG-36) | 12,376 | LNFT | 250.00 | 3,094,000.00 | | 0152 | 805-16-00100 | Reinforced Concrete Box Culverts (Extension) (4' x 4') | 225 | LNFT | 650.00 | 146,250.00 | | 0153 | 805-16-00600 | Reinforced Concrete Box Culverts (Extension) (5' x 5') | 150 | LNFT | 700.00 | 105,000.00 | | 0154 | 805-16-00800 | Reinforced Concrete Box Culverts (Extension) (7' x 5') | 12 | LNFT | 2,200.00 | 26,400.00 | | 0155 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 300,706 | SQFT | 1.50 | 451,059.00 | | 0156 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 310,813 | SQFT | 2.00 | 621,626.00 | | 0157 | 806-01-00100 | Deformed Reinforcing Steel | 2,339,336 | LB | 1.30 | 3,041,136.80 | | 0158 | 806-03-00100 | Deformed Reinforcing Steel Mechanical Splice (BUTT SPLICE) | 1,226 | EACH | 72.00 | 88,272.00 | | 0159 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 114 | LUMP | 250,000.00 | 250,000.00 | | 0160 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 6,571 | LNFT | 145.00 | 952,795.00 | | 0161 | 810-05-00330 | Concrete Roadway Barrier (Double Face) (42 inch Height) | 23,632 | LNFT | 185.00 | 4,371,920.00 | | 0162 | 810-05-00400 | Concrete Roadway Barrier (DOUBLE FACE) (TRANSITION) | 3,753 | LNFT | 540.00 | 2,026,620.00 | | 0163 | 810-05-00400 | Concrete Roadway Barrier (WITH FOOTING) | 3,708 | LNFT | 400.00 | 1,483,200.00 | | 0164 | 810-06-00100 | Concrete Pier Protection System (Vehicle) Median Pier Protection | 838 | LNFT | 650.00 | 544,700.00 | | 0165 | 810-06-00100 | Concrete Pier Protection System (Vehicle) Outside Pier Protection | 532 | LNFT | 650.00 | 345,800.00 | | 0166 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 54,048 | SQFT | 90.00 | 4,864,320.00 | | 0167 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 3,570 | SFIN | 55.00 | 196,350.00 | | 0168 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 2,600 | SFIN | 125.00 | 325,000.00 | | 0169 | 815-02-00100 | Sealed Expansion Joint (End Dams and Preformed Neoprene Seal) | 560 | LNFT | 500.00 | 280,000.00 | | 0170 | 815-03-00300 | Joint Seal (Poured) | 5,265 | LNFT | 26.00 | 136,890.00 | | 0171 | 816-02-00100 | Bridge End Drain System (Open Drain) | 18 | EACH | 12,000.00 | 216,000.00 | | 0172 | 822-01-00100 | Trenching and Backfilling | 14,600 | LNFT | 5.00 | 73,000.00 | | 0173 | 822-02-00100 | Conduit w Conductors (PVC/HDPE) (3/4") (1#2 BARE STRANDED GROUND) | 400 | LNFT | 5.00 | 2,000.00 | | 0174 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (2#2, 1#2 BARE STRANDED GROUND) | 50 | LNFT | 11.00 | 550.00 | | 0175 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (2#8, 1#8 BARE STRANDED GROUND) | 1,150 | LNFT | 8.00 | 9,200.00 | | 0176 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (EMPTY HDPE DUCT WITH PULL LINE) | 13,400 | LNFT | 5.50 | 73,700.00 | | 0177 | 822-02-01000 | Conduit w Conductors (PVC/HDPE) (6") (VERTICAL CONDUIT CASING) | 500 | LNFT | 39.00 | 19,500.00 | | 0178 | 822-04-00200 | Jacked or Bored Casing (6" Dia) (PVC/HDPE) | 1,100 | LNFT | 55.00 | 60,500.00 | | 0179 | 822-05-00700 | Light Pole (40') (Alum) (Single Arm) | 6 | EACH | 6,000.00 | 36,000.00 | | 0180 | 822-07-01900 | Luminaire (400 Watt) (High Pressure Sodium) | 6 | EACH | 700.00 | 4,200.00 | | 0181 | 822-07-02500 | Luminaire (1000 Watt) (High Pressure Sodium) | 32 | EACH | 2,000.00 | 64,000.00 | | 0182 | 822-08-00200 | Electrical Service Point (Structure) | 1 | EACH | 25,000.00 | 25,000.00 | | 0183 | 822-09-00100 | Electrical System (MEDIAN POLE FOUNDATIONS & ANCHOR BOLTS) | 1 | LUMP | 75,000.00 | 75,000.00 | | 0184 | 822-09-00100 | Electrical System (Temporary Weigh-In-Motion Station) | 1 | LUMP | 85,000.00 | 85,000.00 | | 0185 | 822-09-00100 | Electrical System Weigh-In-Motion (Components, Conduit and Conductors) | 1 | LUMP | 1,300,000.00 | 1,300,000.00 | | 0186 | 822-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 16,000.00 | 16,000.00 | | 0187 | 822-11-00100 | Removal and Disposal of Electrical Equipment (Weigh-In-Motion Signs) | 1 | LUMP | 13,000.00 | 13,000.00 | | 0188 | 822-11-00100 | Removal and Disposal of Electrical Equipment (Weigh-In-Motion) | 1 | LUMP | 10,000.00 | 10,000.00 | | 0189 | 822-12-00100 | Removal and Storage of Light Pole (Ground Mount) (40' STEEL) (SINGLE ARM) | 75 | EACH | 200.00 | 15,000.00 | | 0190 | 822-12-00100 | Removal and Storage of Light Pole (Ground Mount) (49' STEEL) | 6 | EACH | 225.00 | 1,350.00 | | 0191 | 822-13-00100 | Removal and Disposal of Light Pole Foundation (HIGH MAST) | 1 | EACH | 9,000.00 | 9,000.00 | | 0192 | 822-13-00100 | Removal and Disposal of Light Pole Foundation (LOW MAST) | 56 | EACH | 400.00 | 22,400.00 | | 0193 | 822-14-00100 | Removal and Disposal of Luminaire | 113 | EACH | 65.00 | 7,345.00 | | 0194 | 822-15-00700 | Relocate Light Poles (40') (Aluminum) (Single Arm) | 2 | EACH | 3,200.00 | 6,400.00 | | 0195 | 822-15-02100 | Relocate Light Poles (HIGH MAST) | 1 | EACH | 130,000.00 | 130,000.00 | | 0196 | 822-16-00100 | Underground Junction Box (12" x 12") | 8 | EACH | 500.00 | 4,000.00 | | 0197 | 822-16-00200 | Underground Junction Box (11" x 18") | 63 | EACH | 600.00 | 37,800.00 | | 0198 | 822-16-00300 | Underground Junction Box (13" x 24") | 8 | EACH | 600.00 | 4,800.00 | | 0199 | 822-19-00100 | Modular Breakaway Cable System | 6 | EACH | 2,100.00 | 12,600.00 | | 0200 | 822-21-00100 | Duct Marker (Concrete) | 7 | EACH | 400.00 | 2,800.00 | | 0201 | 822-22-00300 | Underground Marker Tape (6")(Detectable) | 1,200 | LNFT | 0.70 | 840.00 | | 0202 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 3,936 | LNFT | 7.00 | 27,552.00 | | 0203 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 6,560 | LNFT | 2.50 | 16,400.00 | | 0204 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 1,090,613 | INLF | 0.20 | 218,122.60 | | 0205 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 464,288 | INLF | 1.00 | 464,288.00 | | 0206 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 66,733 | INLF | 1.50 | 100,099.50 | | 0207 | NS-602-00011 | Expansion Joint Rehabilitation | 57 | LNFT | 900.00 | 51,300.00 | | 0208 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 9 | EACH | 11,000.00 | 99,000.00 | | 0209 | NS-700-00820 | Impact Attenuator Relocation (Construction Zone) | 49 | EACH | 400.00 | 19,600.00 | | 0210 | NS-704-00001 | High Tension Cable Barrier | 12,764 | LNFT | 11.00 | 140,404.00 | | 0211 | NS-704-00002 | Cable Barrier Gated End Terminal | 10 | EACH | 6,000.00 | 60,000.00 | | 0212 | NS-704-00003 | Concrete Strip | 17,019 | SQYD | 95.00 | 1,616,805.00 | | 0213 | NS-729-00031 | Breakaway Square Tubing Sign Support (Surface Mount) | 30 | EACH | 425.00 | 12,750.00 | | 0214 | NS-822-00001 | High Mast Luminaire Lowering Device Replacement | 4 | EACH | 18,000.00 | 72,000.00 | | 0215 | 721-01-00100 | Mowing | 24 | CYCL | 10,000.00 | 240,000.00 | | 0216 | 805-16-02700 | Reinforced Concrete Box Culverts (Extension) (3' x 3') | 18 | LNFT | 1,100.00 | 19,800.00 | | 0217 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 1,182 | SQYD | 120.00 | 141,840.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 182,726,111.10 |
|