Proposal:H.011752.6
Parish:Jefferson
Description:SEVERN AVE: VETERANS - W. ESPLANADE
Type Construction:GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY, PORTLAND CEMENT CONCRETE PAVEMENT, DRILLED SHAFT FOUNDATIONS, LANDSCAPING, TRAFFIC SIGNALIZATION, PAVERS, WATER SUPPLY, AND RELATED WORK.
Estimated Construction Cost:$10,789,523.65
Maximum Number of Days Allowed for Construction:430
Calculated Daily User Cost:$12,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 48896 | Command Construction Industries LLC | $11,590,744.76 | 390.00 | $16,270,744.76 |
| 2 | 24901 | Hard Rock Construction LLC | $13,206,674.16 | 268.00 | $16,422,674.16 |
| 3 | 49356 | KORT's CONSTRUCTION SERVICES, INC. | $12,411,103.32 | 430.00 | $17,571,103.32 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $14,786,054.98 | 358.00 | $19,082,054.98 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Command Construction Industries LLC | - 2 - Hard Rock Construction LLC | - 3 - KORT's CONSTRUCTION SERVICES, INC. | - 4 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 10,828.12 | 10,828.12 | 60,000.00 | 60,000.00 | 8,000.00 | 8,000.00 | | 0002 | 202-02-06060 | Removal of Concrete Catch Basin and Inlets | 66 | EACH | 1,000.00 | 66,000.00 | 236.18 | 15,588.14 | 540.00 | 35,640.00 | 490.00 | 32,340.00 | | 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 59 | LNFT | 10.00 | 590.00 | 8.26 | 487.10 | 8.00 | 472.00 | 16.00 | 944.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 5,803 | SQYD | 10.00 | 58,030.00 | 16.18 | 93,886.74 | 8.00 | 46,424.00 | 20.00 | 116,060.00 | | 0005 | 202-02-12020 | Removal of Fence (Chain Link) | 85 | LNFT | 10.00 | 850.00 | 5.75 | 489.09 | 4.00 | 340.00 | 10.00 | 850.00 | | 0006 | 202-02-14500 | Removal of Guard Rail | 85 | LNFT | 10.00 | 850.00 | 17.05 | 1,449.08 | 11.00 | 935.00 | 20.00 | 1,700.00 | | 0007 | 202-02-26000 | Removal of Manholes | 6 | EACH | 1,000.00 | 6,000.00 | 649.51 | 3,897.03 | 550.00 | 3,300.00 | 900.00 | 5,400.00 | | 0008 | 202-02-32140 | Removal of Pipe (Storm Drain) (10") | 53 | LNFT | 10.00 | 530.00 | 17.61 | 933.49 | 10.00 | 530.00 | 9.00 | 477.00 | | 0009 | 202-02-32140 | Removal of Pipe (Storm Drain) (12") | 1,190 | LNFT | 10.00 | 11,900.00 | 14.28 | 16,996.77 | 10.00 | 11,900.00 | 23.00 | 27,370.00 | | 0010 | 202-02-32140 | Removal of Pipe (Storm Drain) (15") | 617 | LNFT | 10.00 | 6,170.00 | 17.35 | 10,703.10 | 10.00 | 6,170.00 | 10.00 | 6,170.00 | | 0011 | 202-02-32140 | Removal of Pipe (Storm Drain) (18") | 753 | LNFT | 10.00 | 7,530.00 | 17.98 | 13,541.95 | 10.00 | 7,530.00 | 11.00 | 8,283.00 | | 0012 | 202-02-32140 | Removal of Pipe (Storm Drain) (21") | 129 | LNFT | 10.00 | 1,290.00 | 17.81 | 2,297.36 | 10.00 | 1,290.00 | 12.00 | 1,548.00 | | 0013 | 202-02-32140 | Removal of Pipe (Storm Drain) (24") | 375 | LNFT | 10.00 | 3,750.00 | 19.86 | 7,445.63 | 10.00 | 3,750.00 | 13.00 | 4,875.00 | | 0014 | 202-02-32140 | Removal of Pipe (Storm Drain) (30") | 256 | LNFT | 10.00 | 2,560.00 | 21.72 | 5,560.32 | 10.00 | 2,560.00 | 17.00 | 4,352.00 | | 0015 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 31,899 | SQYD | 25.00 | 797,475.00 | 20.31 | 647,964.39 | 11.00 | 350,889.00 | 10.00 | 318,990.00 | | 0016 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,000.00 | 10,000.00 | 61,956.23 | 61,956.23 | 50,000.00 | 50,000.00 | 28,000.00 | 28,000.00 | | 0017 | 203-08-00100 | Geotextile Fabric | 9,224 | SQYD | 1.00 | 9,224.00 | 1.16 | 10,727.51 | 1.00 | 9,224.00 | 1.70 | 15,680.80 | | 0018 | 204-02-00100 | Temporary Hay Bales | 189 | EACH | 1.00 | 189.00 | 16.63 | 3,142.50 | 15.00 | 2,835.00 | 21.00 | 3,969.00 | | 0019 | 204-06-00100 | Temporary Silt Fencing | 8,300 | LNFT | 0.01 | 83.00 | 1.64 | 13,587.10 | 1.75 | 14,525.00 | 2.00 | 16,600.00 | | 0020 | 302-02-06020 | Class II Base Course (6" Thick) (Crushed Stone) | 210.5 | SQYD | 50.00 | 10,525.00 | 45.16 | 9,505.97 | 24.00 | 5,052.00 | 20.00 | 4,210.00 | | 0021 | 306-02-00100 | Scarifying and Compacting Roadbed (6" Thick) | 33,424 | SQYD | 0.01 | 334.24 | 2.61 | 87,236.64 | 5.00 | 167,120.00 | 2.00 | 66,848.00 | | 0022 | 402-02-00100 | Mainline Traffic Maintenance Surfacing (Hard) | 1,000 | SQYD | 50.00 | 50,000.00 | 47.13 | 47,125.00 | 75.00 | 75,000.00 | 63.00 | 63,000.00 | | 0023 | 402-03-00100 | Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 750 | CUYD | 50.00 | 37,500.00 | 61.38 | 46,031.25 | 100.00 | 75,000.00 | 80.00 | 60,000.00 | | 0024 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous (2" Thick Mainline Wearing Course) | 25.4 | TON | 500.00 | 12,700.00 | 269.50 | 6,845.35 | 655.00 | 16,637.00 | 375.00 | 9,525.00 | | 0025 | 509-01-00100 | Milling Asphalt Pavement (2" Depth) | 226 | SQYD | 25.00 | 5,650.00 | 9.48 | 2,141.80 | 50.00 | 11,300.00 | 30.00 | 6,780.00 | | 0026 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -13 | CUYD | 1.00 | -13.00 | 9.47 | -123.11 | 0.01 | -0.13 | 0.10 | -1.30 | | 0027 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 226 | SQYD | 200.00 | 45,200.00 | 133.08 | 30,074.95 | 175.00 | 39,550.00 | 125.00 | 28,250.00 | | 0028 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) (24 Hour High Early Strength) | 814.5 | SQYD | 100.00 | 81,450.00 | 133.07 | 108,385.52 | 140.00 | 114,030.00 | 169.00 | 137,650.50 | | 0029 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) (72 Hour High Early Strength) | 29,055.2 | SQYD | 80.00 | 2,324,416.00 | 88.15 | 2,561,215.88 | 95.00 | 2,760,244.00 | 124.00 | 3,602,844.80 | | 0030 | 601-02-00500 | Portland Cement Concrete Pavement (7" Thick) (Crossovers & Turnouts) (24 Hour High Early Strength) | 213 | SQYD | 85.00 | 18,105.00 | 204.22 | 43,499.50 | 120.00 | 25,560.00 | 149.00 | 31,737.00 | | 0031 | 601-02-00500 | Portland Cement Concrete Pavement (7" Thick) (Crossovers & Turnouts) (72 Hour High Early Strength) | 924.2 | SQYD | 75.00 | 69,315.00 | 164.51 | 152,040.14 | 100.00 | 92,420.00 | 137.00 | 126,615.40 | | 0032 | 601-02-00700 | Portland Cement Concrete Pavement (8" Thick) (Crossovers & Turnouts) (24 Hour High Early Strength) | 221.6 | SQYD | 90.00 | 19,944.00 | 169.50 | 37,562.09 | 130.00 | 28,808.00 | 154.00 | 34,126.40 | | 0033 | 601-02-00700 | Portland Cement Concrete Pavement (8" Thick) (Crossovers & Turnouts) (72 Hour High Early Strength) | 630.5 | SQYD | 80.00 | 50,440.00 | 103.70 | 65,380.96 | 105.00 | 66,202.50 | 142.00 | 89,531.00 | | 0034 | 601-02-00900 | Portland Cement Concrete Pavement (9" Thick) (Crossovers & Turnouts) (24 Hour High Early Strength) | 114.1 | SQYD | 100.00 | 11,410.00 | 130.23 | 14,859.24 | 140.00 | 15,974.00 | 162.00 | 18,484.20 | | 0035 | 601-02-00900 | Portland Cement Concrete Pavement (9" Thick) (Crossovers & Turnouts) (72 Hour High Early Strength) | 1,713.6 | SQYD | 80.00 | 137,088.00 | 88.44 | 151,554.21 | 95.00 | 162,792.00 | 130.00 | 222,768.00 | | 0036 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 10 | EACH | 500.00 | 5,000.00 | 113.65 | 1,136.50 | 650.00 | 6,500.00 | 130.00 | 1,300.00 | | 0037 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 881 | LNFT | 85.00 | 74,885.00 | 187.72 | 165,380.44 | 100.00 | 88,100.00 | 130.00 | 114,530.00 | | 0038 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 325 | LNFT | 90.00 | 29,250.00 | 181.68 | 59,045.35 | 110.00 | 35,750.00 | 176.00 | 57,200.00 | | 0039 | 701-03-01062 | Storm Drain Pipe (30" RCP/RPVCP) | 284 | LNFT | 250.00 | 71,000.00 | 241.15 | 68,485.18 | 150.00 | 42,600.00 | 250.00 | 71,000.00 | | 0040 | 701-03-01082 | Storm Drain Pipe (36" RCP/RPVCP) | 190 | LNFT | 290.00 | 55,100.00 | 231.38 | 43,962.77 | 190.00 | 36,100.00 | 273.00 | 51,870.00 | | 0041 | 701-03-01092 | Storm Drain Pipe (42" RCP/RPVCP) | 507 | LNFT | 300.00 | 152,100.00 | 279.51 | 141,709.04 | 240.00 | 121,680.00 | 344.00 | 174,408.00 | | 0042 | 701-03-01102 | Storm Drain Pipe (48" RCP/RPVCP) | 466 | LNFT | 305.00 | 142,130.00 | 323.10 | 150,564.13 | 275.00 | 128,150.00 | 380.00 | 177,080.00 | | 0043 | 701-03-01120 | Storm Drain Pipe (54" RCP) | 1,026 | LNFT | 310.00 | 318,060.00 | 353.53 | 362,718.70 | 320.00 | 328,320.00 | 412.00 | 422,712.00 | | 0044 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 194 | LNFT | 125.00 | 24,250.00 | 145.80 | 28,285.39 | 120.00 | 23,280.00 | 246.00 | 47,724.00 | | 0045 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 278 | LNFT | 150.00 | 41,700.00 | 172.42 | 47,932.76 | 125.00 | 34,750.00 | 154.00 | 42,812.00 | | 0046 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 314 | LNFT | 200.00 | 62,800.00 | 183.43 | 57,596.08 | 140.00 | 43,960.00 | 193.00 | 60,602.00 | | 0047 | 701-04-01060 | Storm Drain Pipe Arch (30" Equiv. RCPA) | 129 | LNFT | 250.00 | 32,250.00 | 203.69 | 26,276.53 | 155.00 | 19,995.00 | 276.00 | 35,604.00 | | 0048 | 701-04-01100 | Storm Drain Pipe Arch (42" Equiv. RCPA) | 565 | LNFT | 300.00 | 169,500.00 | 302.38 | 170,845.83 | 240.00 | 135,600.00 | 371.00 | 209,615.00 | | 0049 | 701-04-01140 | Storm Drain Pipe Arch (54" Equiv. RCPA) | 326 | LNFT | 310.00 | 101,060.00 | 374.96 | 122,238.26 | 320.00 | 104,320.00 | 467.00 | 152,242.00 | | 0050 | 701-04-01160 | Storm Drain Pipe Arch (60" Equiv. RCPA) | 107 | LNFT | 1,000.00 | 107,000.00 | 469.38 | 50,223.45 | 375.00 | 40,125.00 | 547.00 | 58,529.00 | | 0051 | 701-15-00100 | Concrete Collar | 1 | EACH | 50,000.00 | 50,000.00 | 137,787.76 | 137,787.76 | 150,000.00 | 150,000.00 | 60,100.00 | 60,100.00 | | 0052 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 5,592 | LNFT | 1.00 | 5,592.00 | 6.42 | 35,911.82 | 5.00 | 27,960.00 | 15.30 | 85,557.60 | | 0053 | 702-02-00100 | Manholes (MH-06) | 20 | EACH | 5,000.00 | 100,000.00 | 8,116.00 | 162,320.00 | 7,600.00 | 152,000.00 | 15,000.00 | 300,000.00 | | 0054 | 702-04-00100 | Adjusting Manholes | 18 | EACH | 400.00 | 7,200.00 | 445.56 | 8,020.08 | 1,400.00 | 25,200.00 | 800.00 | 14,400.00 | | 0055 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 5 | EACH | 175.00 | 875.00 | 279.88 | 1,399.39 | 850.00 | 4,250.00 | 690.00 | 3,450.00 | | 0056 | 702-04-00200 | Adjusting Catch Basins (Catch Basins and Inlets) | 35 | EACH | 500.00 | 17,500.00 | 555.13 | 19,429.52 | 1,900.00 | 66,500.00 | 800.00 | 28,000.00 | | 0057 | 702-04-00300 | Adjusting Junction Boxes | 12 | EACH | 500.00 | 6,000.00 | 1,786.38 | 21,436.60 | 1,700.00 | 20,400.00 | 1,160.00 | 13,920.00 | | 0058 | 705-06-00200 | Chain Link Fence (5-Foot Height) | 85 | LNFT | 25.00 | 2,125.00 | 39.78 | 3,381.13 | 30.00 | 2,550.00 | 25.00 | 2,125.00 | | 0059 | 706-01-00100 | Concrete Walk (4" Thick) | 5,621.9 | SQYD | 50.00 | 281,095.00 | 84.13 | 472,970.45 | 55.00 | 309,204.50 | 85.00 | 477,861.50 | | 0060 | 706-02-00200 | Concrete Drive (6" Thick) (72 Hour High Early Strength) | 1,030.9 | SQYD | 60.00 | 61,854.00 | 97.15 | 100,151.94 | 65.00 | 67,008.50 | 110.00 | 113,399.00 | | 0061 | 706-02-00300 | Concrete Drive (8" Thick) (72 Hour High Early Strength) | 1,500.8 | SQYD | 75.00 | 112,560.00 | 166.92 | 250,513.54 | 80.00 | 120,064.00 | 120.00 | 180,096.00 | | 0062 | 706-03-00100 | Incidental Concrete Paving (4" Thick) (WITH 6x6x#6x#6 MWF) | 210.3 | SQYD | 75.00 | 15,772.50 | 120.72 | 25,388.05 | 55.00 | 11,566.50 | 90.00 | 18,927.00 | | 0063 | 706-04-00100 | Handicapped Curb Ramps (Alternate #1) | 29 | EACH | 1,000.00 | 29,000.00 | 2,626.00 | 76,154.00 | 760.00 | 22,040.00 | 4,800.00 | 139,200.00 | | 0064 | 706-04-00100 | Handicapped Curb Ramps (Alternate #2) | 3 | EACH | 1,000.00 | 3,000.00 | 3,040.12 | 9,120.35 | 1,300.00 | 3,900.00 | 9,100.00 | 27,300.00 | | 0065 | 706-04-00100 | Handicapped Curb Ramps (Alternate #3) | 3 | EACH | 1,000.00 | 3,000.00 | 3,065.73 | 9,197.20 | 1,500.00 | 4,500.00 | 4,400.00 | 13,200.00 | | 0066 | 706-04-00100 | Handicapped Curb Ramps (Alternate #4) | 5 | EACH | 1,000.00 | 5,000.00 | 3,948.72 | 19,743.60 | 1,800.00 | 9,000.00 | 7,900.00 | 39,500.00 | | 0067 | 706-04-00100 | Handicapped Curb Ramps (Alternate #5) | 2 | EACH | 1,000.00 | 2,000.00 | 3,318.59 | 6,637.18 | 1,500.00 | 3,000.00 | 4,600.00 | 9,200.00 | | 0068 | 706-04-00100 | Handicapped Curb Ramps (Alternate #6) | 7 | EACH | 1,000.00 | 7,000.00 | 2,356.23 | 16,493.62 | 1,500.00 | 10,500.00 | 2,200.00 | 15,400.00 | | 0069 | 706-04-00100 | Handicapped Curb Ramps (Alternate #7) | 4 | EACH | 1,000.00 | 4,000.00 | 2,192.63 | 8,770.51 | 1,600.00 | 6,400.00 | 2,160.00 | 8,640.00 | | 0070 | 707-01-00200 | Concrete Curb (Barrier) (6" High)(6" Wide)(24 Hour High Early Strength) | 166.8 | LNFT | 1.00 | 166.80 | 17.76 | 2,961.70 | 11.50 | 1,918.20 | 29.00 | 4,837.20 | | 0071 | 707-01-00200 | Concrete Curb (Barrier) (6" High)(6" Wide)(72 Hour High Early Strength) | 14,251.3 | LNFT | 1.00 | 14,251.30 | 13.83 | 197,109.73 | 12.00 | 171,015.60 | 20.00 | 285,026.00 | | 0072 | 707-01-00200 | Concrete Curb (Barrier) (8" High)(6" Wide)(72 Hour High Early Strength) | 106 | LNFT | 1.00 | 106.00 | 21.34 | 2,262.25 | 14.00 | 1,484.00 | 22.00 | 2,332.00 | | 0073 | 707-01-00300 | Concrete Curb (Mountable) (6' High)(15" Wide)(72 Hour High Early Strength) | 192.4 | LNFT | 1.00 | 192.40 | 34.37 | 6,612.02 | 15.00 | 2,886.00 | 23.00 | 4,425.20 | | 0074 | 707-03-00100 | Combination Concrete Curb and Gutter (6" High Barrier)(24 Hour High Early Strength) | 59 | LNFT | 30.00 | 1,770.00 | 68.19 | 4,023.21 | 43.00 | 2,537.00 | 100.00 | 5,900.00 | | 0075 | 710-01-00100 | Flowable Fill | 25 | CUYD | 250.00 | 6,250.00 | 245.00 | 6,125.03 | 250.00 | 6,250.00 | 540.00 | 13,500.00 | | 0076 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 68,350.70 | 68,350.70 | 240,000.00 | 240,000.00 | 316,000.00 | 316,000.00 | | 0077 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 4,500 | LNFT | 0.50 | 2,250.00 | 0.57 | 2,556.00 | 0.75 | 3,375.00 | 1.05 | 4,725.00 | | 0078 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 350 | LNFT | 2.00 | 700.00 | 2.27 | 795.55 | 2.00 | 700.00 | 3.20 | 1,120.00 | | 0079 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 3.074 | MILE | 600.00 | 1,844.40 | 568.25 | 1,746.80 | 500.00 | 1,537.00 | 2,120.00 | 6,516.88 | | 0080 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.074 | MILE | 1,200.00 | 3,688.80 | 568.25 | 1,746.80 | 500.00 | 1,537.00 | 2,120.00 | 6,516.88 | | 0081 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 3.074 | MILE | 55.00 | 169.07 | 1,250.15 | 3,842.96 | 1,100.00 | 3,381.40 | 2,650.00 | 8,146.10 | | 0082 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 10 | EACH | 55.00 | 550.00 | 56.83 | 568.25 | 55.00 | 550.00 | 213.00 | 2,130.00 | | 0083 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 75 | EACH | 5.00 | 375.00 | 13.07 | 980.25 | 6.50 | 487.50 | 21.00 | 1,575.00 | | 0084 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 25,000.00 | 50,000.00 | 13,744.38 | 27,488.75 | 15,000.00 | 30,000.00 | 10,500.00 | 21,000.00 | | 0085 | 714-01-00300 | Slab Sodding (Tiffway Bermuda) Cynodon Dactylon 'Tifway 419' | 3,895 | SQYD | 5.00 | 19,475.00 | 7.58 | 29,524.10 | 2.75 | 10,711.25 | 2.70 | 10,516.50 | | 0086 | 715-01-00100 | Topsoil | 100 | CUYD | 50.00 | 5,000.00 | 66.00 | 6,599.70 | 55.00 | 5,500.00 | 53.00 | 5,300.00 | | 0087 | 719-01-01040 | Plants (Tree) (Balled and Burlapped) (2 inch cal) ILEX XATTENUATA 'EAGLESTON',EAGLESTON HOLLY, 8'-10' HT MIN, FULL TO GROUND AND STAKED | 21 | EACH | 175.00 | 3,675.00 | 333.70 | 7,007.68 | 155.00 | 3,255.00 | 159.00 | 3,339.00 | | 0088 | 719-01-01080 | Plants (Tree) (Balled and Burlapped) (3 inch cal) ILEX XATTENUATA 'EAGLESTON',EAGLESTON HOLLY, 10'-12' HT MIN, FULL AND MATCHED | 22 | EACH | 250.00 | 5,500.00 | 736.60 | 16,205.20 | 205.00 | 4,510.00 | 213.00 | 4,686.00 | | 0089 | 719-01-02100 | Plants (Tree) (Container) (3-1/2 inch cal) ACER RUBRUM 'FLORIDA FLAME', FLORIDA FLAME RED MAPLE, 14'-16' HT, FULL, MATCHED, AND FEMALE | 101 | EACH | 300.00 | 30,300.00 | 498.11 | 50,308.61 | 280.00 | 28,280.00 | 292.00 | 29,492.00 | | 0090 | 719-01-02100 | Plants (Tree) (Container) (3-1/2 inch cal) TAXODIUM DISTICHUM 'AUTUMN GOLD', AUTUMN GOLD CYPRESS, 14'-16' HT, FULL AND MATCHED | 6 | EACH | 225.00 | 1,350.00 | 550.51 | 3,303.05 | 205.00 | 1,230.00 | 213.00 | 1,278.00 | | 0091 | 719-01-06000 | Plants (Plant) (Container) (4 inch) SEASONAL COLOR, CONT. 4" POTS, 6" O.C. MAX., FULL | 688 | EACH | 1.00 | 688.00 | 2.72 | 1,868.61 | 1.50 | 1,032.00 | 1.05 | 722.40 | | 0092 | 719-01-06000 | Plants (Plant) (Container) (4 inch) APTENIA CORDIFOLIA VARIEGATA 'CRYSTAL', VARIEGATED ICE PLANT, CONT. 4" POTS, 6" O.C. MAX ., FULL | 264 | EACH | 2.00 | 528.00 | 6.14 | 1,620.17 | 2.50 | 660.00 | 2.10 | 554.40 | | 0093 | 719-01-06000 | Plants (Plant) (Container) (4 inch) TRACHEOLOSPERMUM ASIATICUM, ASIAN JASMINE, CONT. 4" POTS, 6" O.C. MAX FULL | 4,380 | EACH | 1.00 | 4,380.00 | 2.19 | 9,605.34 | 1.25 | 5,475.00 | 1.05 | 4,599.00 | | 0094 | 719-01-06020 | Plants (Plant) (Container) (1 gallon) JUNCUS TENUIS, BLUE DART JUNCUS, 8" O.C. MAX., FULL | 2,660 | EACH | 3.00 | 7,980.00 | 11.76 | 31,289.58 | 2.75 | 7,315.00 | 2.70 | 7,182.00 | | 0095 | 719-01-06020 | Plants (Plant) (Container) (1 gallon) LIRIOPE SPICATA , CREEPING LIRIOPE, 8" O.C, FULL | 8,450 | EACH | 1.00 | 8,450.00 | 5.17 | 43,694.95 | 1.25 | 10,562.50 | 1.05 | 8,872.50 | | 0096 | 719-01-06020 | Plants (Plant) (Container) (1 gallon) BAPTISIA AUSTRALIS, INDIGO, SPACING- AS PER PLAN, FULL | 18 | EACH | 2.00 | 36.00 | 11.39 | 204.98 | 2.25 | 40.50 | 2.10 | 37.80 | | 0097 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) JUNCUS EFFUSUS , COMMON RUSH, 3'-0" O.C., FULL | 414 | EACH | 8.00 | 3,312.00 | 22.78 | 9,428.85 | 7.25 | 3,001.50 | 7.40 | 3,063.60 | | 0098 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Juniperus Squamata Expansa 'Parsonii', Parson Juniper, 3'-0" O.C., FULL | 168 | EACH | 8.00 | 1,344.00 | 18.09 | 3,039.62 | 7.25 | 1,218.00 | 7.40 | 1,243.20 | | 0099 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Loropetalum Chinense 'Shang-Hi', Loropetalum 'Purple Diamond', 3'-0" O.C., FULL | 174 | EACH | 8.00 | 1,392.00 | 31.97 | 5,562.78 | 7.25 | 1,261.50 | 7.40 | 1,287.60 | | 0100 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) NEOMARICA CAERULEA 'REGINA', BRAZILIAN IRIS REGINA, 1'-6" O.C. MAX., FULL | 152 | EACH | 8.00 | 1,216.00 | 24.72 | 3,757.29 | 7.25 | 1,102.00 | 7.40 | 1,124.80 | | 0101 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Pittosporum Tobira 'Mojo', Mojo Dwarf Pittosporum, 3'-0" O.C. FULL | 122 | EACH | 8.00 | 976.00 | 34.11 | 4,160.93 | 8.25 | 1,006.50 | 8.33 | 1,016.26 | | 0102 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) PITTOSPORUM TOBIRA 'NANA', DWARF PITTOSPORUM, 3'-0" O.C. MAX., FULL | 94 | EACH | 8.00 | 752.00 | 22.95 | 2,156.92 | 7.25 | 681.50 | 7.40 | 695.60 | | 0103 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) PODOCARPUS MACROPHYLLUS 'PRINGLES DWARF' , PRINGLES YEW, 2'-0" O.C., FULL | 180 | EACH | 10.00 | 1,800.00 | 22.95 | 4,130.28 | 8.50 | 1,530.00 | 8.33 | 1,499.40 | | 0104 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) RAPHEOLEPIS INDICA 'CLARA', INDIAN HAWTHORN, 2'-6" O.C., FULL | 329 | EACH | 8.00 | 2,632.00 | 18.22 | 5,993.72 | 7.50 | 2,467.50 | 7.40 | 2,434.60 | | 0105 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) 'ROSA MEIGALPIO' P.P.#17877, RED DRIFT ROSE, 1'-6" O.C., FULL | 309 | EACH | 12.00 | 3,708.00 | 33.29 | 10,285.99 | 10.50 | 3,244.50 | 11.00 | 3,399.00 | | 0106 | 719-01-06100 | Plants (Plant) (Container) (7 gallon) JUNIPERUS CHINENSIS 'BLUE POINT', BLUE POINT JUNIPER TOPIARY, SPACING- AS PER PLAN, FULL AND CONE SHAPED | 3 | EACH | 15.00 | 45.00 | 48.02 | 144.05 | 12.50 | 37.50 | 13.00 | 39.00 | | 0107 | 719-01-06160 | Plants (Plant) (Container) (30 gallon) PODOCARPUS MACROPHYLLUS, JAPENESE YEW, 4'-0" O.C., FULL | 11 | EACH | 200.00 | 2,200.00 | 269.16 | 2,960.73 | 155.00 | 1,705.00 | 160.00 | 1,760.00 | | 0108 | 719-02-00100 | Top Dressing Mulch (3" Depth) (Pinestraw) | 2,228 | SQYD | 5.00 | 11,140.00 | 8.41 | 18,737.48 | 3.50 | 7,798.00 | 3.20 | 7,129.60 | | 0109 | 719-03-00300 | Bed Preparation (10" Depth) | 2,010 | SQYD | 20.00 | 40,200.00 | 21.82 | 43,860.21 | 21.00 | 42,210.00 | 21.00 | 42,210.00 | | 0110 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 10,000.00 | 10,000.00 | 28,245.44 | 28,245.44 | 15,000.00 | 15,000.00 | 81,500.00 | 81,500.00 | | 0111 | 723-01-00100 | Granular Material (Net Section) (16" Thick Base Course) | 411 | CUYD | 35.00 | 14,385.00 | 63.89 | 26,258.38 | 30.00 | 12,330.00 | 45.00 | 18,495.00 | | 0112 | 723-01-00100 | Granular Material (Net Section) (4" Thick) | 792 | CUYD | 35.00 | 27,720.00 | 22.43 | 17,764.56 | 30.00 | 23,760.00 | 56.00 | 44,352.00 | | 0113 | 723-02-00100 | Granular Material (Vehicular Measurement) | 1,250 | CUYD | 75.00 | 93,750.00 | 11.66 | 14,580.00 | 28.00 | 35,000.00 | 26.00 | 32,500.00 | | 0114 | 726-01-00100 | Bedding Material | 4,306.1 | CUYD | 100.00 | 430,610.00 | 78.38 | 337,512.12 | 85.00 | 366,018.50 | 83.00 | 357,406.30 | | 0115 | 727-01-00100 | Mobilization | 1 | LUMP | 1,500,000.00 | 1,500,000.00 | 677,750.00 | 677,750.00 | 1,000,000.00 | 1,000,000.00 | 568,300.00 | 568,300.00 | | 0116 | 731-02-00100 | Reflectorized Raised Pavement Markers | 422 | EACH | 6.00 | 2,532.00 | 7.39 | 3,117.31 | 7.00 | 2,954.00 | 16.00 | 6,752.00 | | 0117 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 3,418 | LNFT | 2.00 | 6,836.00 | 2.84 | 9,710.54 | 3.00 | 10,254.00 | 4.17 | 14,253.06 | | 0118 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 650 | LNFT | 7.00 | 4,550.00 | 7.96 | 5,171.40 | 7.00 | 4,550.00 | 16.00 | 10,400.00 | | 0119 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 4.186 | MILE | 3,000.00 | 12,558.00 | 3,693.63 | 15,461.51 | 3,500.00 | 14,651.00 | 8,000.00 | 33,488.00 | | 0120 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.297 | MILE | 1,000.00 | 2,297.00 | 1,593.18 | 3,659.53 | 1,400.00 | 3,215.80 | 2,700.00 | 6,201.90 | | 0121 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.04 | MILE | 4,000.00 | 160.00 | 5,114.25 | 204.57 | 4,600.00 | 184.00 | 5,300.00 | 212.00 | | 0122 | 732-03-02012 | Plastic Pavement Striping (Dotted Line)(4" W)(3' L)(Thermo 90 mil) | 0.045 | MILE | 4,000.00 | 180.00 | 5,682.50 | 255.71 | 4,500.00 | 202.50 | 3,000.00 | 135.00 | | 0123 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.135 | MILE | 7,000.00 | 945.00 | 8,523.75 | 1,150.71 | 7,300.00 | 985.50 | 5,500.00 | 742.50 | | 0124 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.038 | MILE | 8,000.00 | 304.00 | 9,092.00 | 345.50 | 6,400.00 | 243.20 | 11,200.00 | 425.60 | | 0125 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 26 | EACH | 200.00 | 5,200.00 | 227.30 | 5,909.80 | 250.00 | 6,500.00 | 530.00 | 13,780.00 | | 0126 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 2 | EACH | 400.00 | 800.00 | 454.60 | 909.20 | 450.00 | 900.00 | 800.00 | 1,600.00 | | 0127 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 5 | EACH | 300.00 | 1,500.00 | 284.13 | 1,420.63 | 300.00 | 1,500.00 | 530.00 | 2,650.00 | | 0128 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 9 | EACH | 300.00 | 2,700.00 | 284.13 | 2,557.13 | 300.00 | 2,700.00 | 530.00 | 4,770.00 | | 0129 | 732-04-02000 | Plastic Pavement Legends and Symbols (Bicycle) | 24 | EACH | 200.00 | 4,800.00 | 284.13 | 6,819.00 | 300.00 | 7,200.00 | 530.00 | 12,720.00 | | 0130 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 9 | EACH | 300.00 | 2,700.00 | 340.95 | 3,068.55 | 350.00 | 3,150.00 | 530.00 | 4,770.00 | | 0131 | 732-05-00100 | Removal of Existing Markings | 1.6 | MILE | 7,000.00 | 11,200.00 | 8,523.75 | 13,638.00 | 7,600.00 | 12,160.00 | 10,600.00 | 16,960.00 | | 0132 | 740-01-00100 | Construction Layout | 1 | LUMP | 100,000.00 | 100,000.00 | 28,412.50 | 28,412.50 | 120,000.00 | 120,000.00 | 437,000.00 | 437,000.00 | | 0133 | 804-18-00100 | Vibration Monitoring | 100 | DAY | 1,000.00 | 100,000.00 | 340.95 | 34,095.00 | 850.00 | 85,000.00 | 530.00 | 53,000.00 | | 0134 | 806-01-00100 | Deformed Reinforcing Steel | 500 | LB | 2.00 | 1,000.00 | 0.80 | 398.00 | 1.00 | 500.00 | 3.00 | 1,500.00 | | 0135 | 822-03-00100 | Conductors (2C,#14 AWG) | 630 | LNFT | 6.00 | 3,780.00 | 7.30 | 4,596.48 | 6.50 | 4,095.00 | 7.00 | 4,410.00 | | 0136 | 822-04-00400 | Jacked or Bored Casing (2" DIA) (SCHEDULE 80 PVC) | 700 | LNFT | 30.00 | 21,000.00 | 22.91 | 16,038.40 | 21.00 | 14,700.00 | 21.40 | 14,980.00 | | 0137 | 822-16-00400 | Underground Junction Box (18" L x 12"W x 12"D) | 140 | EACH | 500.00 | 70,000.00 | 525.97 | 73,636.08 | 475.00 | 66,500.00 | 490.00 | 68,600.00 | | 0138 | 822-16-00400 | Underground Junction Box (24"L x 24"W x 12"D) | 30 | EACH | 1,200.00 | 36,000.00 | 1,334.32 | 40,029.57 | 1,200.00 | 36,000.00 | 1,250.00 | 37,500.00 | | 0139 | 822-22-00100 | Underground Marker Tape (3")(Detectable) | 12,700 | LNFT | 0.50 | 6,350.00 | 0.48 | 6,057.90 | 0.50 | 6,350.00 | 0.44 | 5,588.00 | | 0140 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 18 | EACH | 2,500.00 | 45,000.00 | 1,136.50 | 20,457.00 | 1,900.00 | 34,200.00 | 2,000.00 | 36,000.00 | | 0141 | NS-201-00005 | Arborist Services | 1 | LUMP | 1,000.00 | 1,000.00 | 1,136.50 | 1,136.50 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | | 0142 | NS-203-00006 | Exploratory Excavation | 50 | CUYD | 500.00 | 25,000.00 | 232.13 | 11,606.65 | 90.00 | 4,500.00 | 254.00 | 12,700.00 | | 0143 | NS-300-00060 | Geogrid | 7,609 | SQYD | 3.00 | 22,827.00 | 2.61 | 19,821.45 | 2.00 | 15,218.00 | 1.50 | 11,413.50 | | 0144 | NS-500-00300 | Traffic Maintenance Asphalt Concrete | 25 | TON | 400.00 | 10,000.00 | 268.48 | 6,712.05 | 225.00 | 5,625.00 | 290.00 | 7,250.00 | | 0145 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 1,300 | INLF | 1.00 | 1,300.00 | 0.57 | 739.70 | 1.00 | 1,300.00 | 0.57 | 741.00 | | 0146 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 77,225 | INLF | 0.01 | 772.25 | 1.10 | 84,638.60 | 1.00 | 77,225.00 | 0.73 | 56,374.25 | | 0147 | NS-719-00001 | Tree Protection Fencing | 1 | LUMP | 10,000.00 | 10,000.00 | 5,682.50 | 5,682.50 | 15,000.00 | 15,000.00 | 5,300.00 | 5,300.00 | | 0148 | PS-P26-02020 | Sewer Cleanouts | 10 | EACH | 250.00 | 2,500.00 | 2,879.75 | 28,797.50 | 3,000.00 | 30,000.00 | 1,200.00 | 12,000.00 | | 0149 | PS-P26-02040 | Pre-Construction and Post-Construction Pipe Cleaning and Video Inspection | 5,900 | LNFT | 6.00 | 35,400.00 | 17.05 | 100,583.20 | 15.00 | 88,500.00 | 6.00 | 35,400.00 | | 0150 | TS-700-00020 | Bench (Park)(Aluminum with Center Arm Rest) | 12 | EACH | 3,000.00 | 36,000.00 | 5,463.55 | 65,562.54 | 5,000.00 | 60,000.00 | 5,600.00 | 67,200.00 | | 0151 | TS-707-00300 | Concrete Curb (Mountable) (Doweled) (18" WIDE)(6" HIGH)(72 HOUR EARLY STRENGTH) | 864.9 | LNFT | 20.00 | 17,298.00 | 37.09 | 32,080.01 | 28.00 | 24,217.20 | 74.00 | 64,002.60 | | 0152 | TS-707-00300 | Concrete Curb (Mountable) (Doweled) (36" WIDE)(6" HIGH)(72 HOUR EARLY STRENGTH) | 1,412.4 | LNFT | 30.00 | 42,372.00 | 42.80 | 60,454.96 | 32.00 | 45,196.80 | 78.00 | 110,167.20 | | 0153 | TS-719-00010 | Landscape Edging | 890 | LNFT | 5.00 | 4,450.00 | 9.02 | 8,031.36 | 8.00 | 7,120.00 | 7.50 | 6,675.00 | | 0154 | TS-719-00020 | Pavers (Concrete)(Crosswalk)(7 13/16" x3 7/8"x80MM) | 10,236 | SQFT | 15.00 | 153,540.00 | 17.79 | 182,057.50 | 16.00 | 163,776.00 | 16.00 | 163,776.00 | | 0155 | TS-719-00020 | Pavers (Concrete)(Decorative Mosaic)(12"x12"x3") | 7,669 | SQFT | 25.00 | 191,725.00 | 17.79 | 136,400.83 | 22.00 | 168,718.00 | 21.25 | 162,966.25 | | 0156 | TS-719-00020 | Pavers (Concrete)(Driveway)(7 13/16" x 3 7/8" x80MM) | 9,277 | SQFT | 25.00 | 231,925.00 | 17.79 | 165,000.72 | 16.00 | 148,432.00 | 15.00 | 139,155.00 | | 0157 | TS-719-00020 | Pavers (Concrete)(Parklet)(12"x6"x2" Thick Min.) | 1,888 | SQFT | 12.00 | 22,656.00 | 17.79 | 33,579.97 | 12.00 | 22,656.00 | 10.70 | 20,201.60 | | 0158 | TS-719-00020 | Pavers (Concrete)(Sidewalk)(7 13/16" x3 7/8"x60MM) | 50,597 | SQFT | 10.00 | 505,970.00 | 17.79 | 899,918.24 | 11.00 | 556,567.00 | 9.90 | 500,910.30 | | 0159 | TS-719-00050 | Irrigation System (Furnished and Installed) | 1 | LUMP | 200,000.00 | 200,000.00 | 106,967.38 | 106,967.38 | 205,000.00 | 205,000.00 | 200,000.00 | 200,000.00 | | 0160 | TS-719-00060 | Landscape Protection Fence Sleeve | 681 | EACH | 100.00 | 68,100.00 | 129.84 | 88,423.08 | 45.00 | 30,645.00 | 186.00 | 126,666.00 | | 0161 | TS-719-00070 | Weed Control Fabric | 2,535 | SQYD | 3.00 | 7,605.00 | 7.83 | 19,849.05 | 8.00 | 20,280.00 | 6.40 | 16,224.00 | | 0162 | TS-727-00001 | Demobilization-Remobilization | 1 | LS | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 115,000.00 | 115,000.00 | 45,000.00 | 45,000.00 | | 0163 | TS-736-00010 | Countdown Pedestrian LED Lens (16 Inch x 18 Inch) | 6 | EACH | 250.00 | 1,500.00 | 290.76 | 1,744.57 | 275.00 | 1,650.00 | 272.00 | 1,632.00 | | 0164 | TS-MSC-00008 | Construction Photographs And Video | 1 | LUMP | 50,000.00 | 50,000.00 | 48,843.36 | 48,843.36 | 145,000.00 | 145,000.00 | 10,600.00 | 10,600.00 | | 0165 | TS-MSC-00010 | Trash Receptacle (Aluminum)(With Aggregate Sub-Base & Reinforced Concrete Base) | 5 | EACH | 3,000.00 | 15,000.00 | 3,847.45 | 19,237.25 | 3,100.00 | 15,500.00 | 3,600.00 | 18,000.00 | | 0166 | TS-MSC-00300 | Bike Racks | 4 | EACH | 7,500.00 | 30,000.00 | 8,665.46 | 34,661.82 | 7,500.00 | 30,000.00 | 6,800.00 | 27,200.00 | | 0167 | TS-MSC-00320 | Water Fountains | 2 | EACH | 5,000.00 | 10,000.00 | 6,584.52 | 13,169.05 | 5,000.00 | 10,000.00 | 6,800.00 | 13,600.00 | | 0168 | TS-MSC-20090 | Planter (Type A)(Reinforced Concrete)(22"/24"HT.) | 3 | EACH | 2,000.00 | 6,000.00 | 2,292.49 | 6,877.46 | 2,000.00 | 6,000.00 | 2,150.00 | 6,450.00 | | 0169 | TS-MSC-20090 | Planter (Type B)(Reinforced Concrete)(30"HT.) | 6 | EACH | 2,000.00 | 12,000.00 | 3,055.70 | 18,334.21 | 2,800.00 | 16,800.00 | 3,000.00 | 18,000.00 | | 0170 | TS-MSC-20090 | Planter (Type C)(Reinforced Concrete)(42"/48" HT.) | 3 | EACH | 3,000.00 | 9,000.00 | 2,876.93 | 8,630.79 | 2,700.00 | 8,100.00 | 2,800.00 | 8,400.00 | | 0171 | TS-P26-00000 | Pedestrian Push Button (Jefferson Parish) | 6 | EACH | 250.00 | 1,500.00 | 274.09 | 1,644.54 | 250.00 | 1,500.00 | 260.00 | 1,560.00 | | 0172 | TS-P26-00008 | 2 inch PVC Conduit (in earth) | 12,000 | LNFT | 8.00 | 96,000.00 | 9.47 | 113,604.00 | 9.00 | 108,000.00 | 9.00 | 108,000.00 | | 0173 | TS-P26-00011 | 3 inch PVC Conduit (in earth) | 50 | LNFT | 10.00 | 500.00 | 11.49 | 574.50 | 11.00 | 550.00 | 11.00 | 550.00 | | 0174 | TS-P26-00013 | 3 inch PVC Conduit (jack and bore) | 320 | LNFT | 30.00 | 9,600.00 | 31.92 | 10,215.68 | 29.00 | 9,280.00 | 30.00 | 9,600.00 | | 0175 | TS-P26-00023 | 12 inch Red Ball LED Lens | 2 | EACH | 100.00 | 200.00 | 84.23 | 168.45 | 76.00 | 152.00 | 80.00 | 160.00 | | 0176 | TS-P26-00024 | 12 inch Yellow Ball LED Lens | 2 | EACH | 100.00 | 200.00 | 84.23 | 168.45 | 76.00 | 152.00 | 80.00 | 160.00 | | 0177 | TS-P26-00025 | 12 inch Green Ball LED Lens | 2 | EACH | 100.00 | 200.00 | 84.23 | 168.45 | 76.00 | 152.00 | 80.00 | 160.00 | | 0178 | TS-P26-00029 | Loop Lead-in Cable | 300 | LNFT | 2.00 | 600.00 | 1.92 | 576.30 | 2.00 | 600.00 | 2.00 | 600.00 | | 0179 | TS-P26-00034 | Traffic Signal Cable, 5-conductor | 1,175 | LNFT | 2.00 | 2,350.00 | 2.41 | 2,830.58 | 2.50 | 2,937.50 | 2.30 | 2,702.50 | | 0180 | TS-P26-00054 | Traffic Signal Pedestal Pole | 3 | EACH | 2,800.00 | 8,400.00 | 3,187.91 | 9,563.72 | 3,000.00 | 9,000.00 | 3,000.00 | 9,000.00 | | 0181 | TS-P26-00056 | Underground Junction Box (32.25 in x 19.25 in x 18 in) | 4 | EACH | 1,200.00 | 4,800.00 | 1,276.52 | 5,106.07 | 1,200.00 | 4,800.00 | 1,200.00 | 4,800.00 | | 0182 | TS-P26-00057 | 3-Section Signal Head | 2 | EACH | 1,000.00 | 2,000.00 | 1,098.12 | 2,196.24 | 1,000.00 | 2,000.00 | 1,030.00 | 2,060.00 | | 0183 | TS-P26-00060 | Pedestrian Signal Head | 6 | EACH | 1,000.00 | 6,000.00 | 1,341.29 | 8,047.72 | 1,200.00 | 7,200.00 | 1,300.00 | 7,800.00 | | 0184 | TS-P26-00061 | Vehicle Loop Detector | 15 | EACH | 2,000.00 | 30,000.00 | 3,158.56 | 47,378.42 | 2,800.00 | 42,000.00 | 3,000.00 | 45,000.00 | | 0185 | TS-P26-00072 | Jeff Par Video Detection System - Furnish and Install | 1 | EACH | 20,000.00 | 20,000.00 | 27,323.68 | 27,323.68 | 25,000.00 | 25,000.00 | 25,600.00 | 25,600.00 | | 0186 | TS-P26-00082 | Traffic Signal Foundation (30 inch Diameter) | 1 | EACH | 8,000.00 | 8,000.00 | 8,754.66 | 8,754.66 | 7,800.00 | 7,800.00 | 8,200.00 | 8,200.00 | | 0187 | TS-P26-00090 | Pedestal Pole Foundation | 3 | EACH | 2,500.00 | 7,500.00 | 2,512.67 | 7,538.00 | 2,300.00 | 6,900.00 | 2,350.00 | 7,050.00 | | 0188 | TS-P26-00100 | Fire Hydrant Assembly | 7 | EACH | 4,500.00 | 31,500.00 | 7,315.34 | 51,207.37 | 7,300.00 | 51,100.00 | 6,450.00 | 45,150.00 | | 0189 | TS-P26-10208 | Gate Valve and Valve Box (8") | 4 | EACH | 1,500.00 | 6,000.00 | 3,210.08 | 12,840.34 | 2,600.00 | 10,400.00 | 1,800.00 | 7,200.00 | | 0190 | TS-P26-10306 | Butterfly Valve and Valve Box (24") | 1 | EACH | 7,500.00 | 7,500.00 | 9,601.74 | 9,601.74 | 11,000.00 | 11,000.00 | 15,500.00 | 15,500.00 | | 0191 | TS-P26-10350 | 35 Foot Single Mast Arm Assembly | 1 | EACH | 15,000.00 | 15,000.00 | 15,662.27 | 15,662.27 | 14,000.00 | 14,000.00 | 14,600.00 | 14,600.00 | | 0192 | TS-P26-13001 | Water Meter / Meter Box Adjustment (<1") | 12 | EACH | 1.00 | 12.00 | 356.62 | 4,279.49 | 350.00 | 4,200.00 | 700.00 | 8,400.00 | | 0193 | TS-P26-13002 | Water Meter / Meter Box Adjustment (1") | 9 | EACH | 1.00 | 9.00 | 369.03 | 3,321.31 | 385.00 | 3,465.00 | 700.00 | 6,300.00 | | 0194 | TS-P26-13004 | Water Meter / Meter Box Adjustment (2") | 16 | EACH | 1.00 | 16.00 | 515.59 | 8,249.42 | 490.00 | 7,840.00 | 800.00 | 12,800.00 | | 0195 | TS-P26-13006 | Water Meter / Meter Box Adjustment (3") | 3 | EACH | 1.00 | 3.00 | 625.40 | 1,876.20 | 630.00 | 1,890.00 | 800.00 | 2,400.00 | | 0196 | TS-P26-13012 | Water Valve / Valve-Box Adjustment (12 in. or less) | 20 | EACH | 1.00 | 20.00 | 1,126.25 | 22,525.02 | 420.00 | 8,400.00 | 2,070.00 | 41,400.00 | | 0197 | TS-P26-13018 | Water Valve / Valve Box Adjustment (greater than 12") | 4 | EACH | 1.00 | 4.00 | 1,993.85 | 7,975.39 | 490.00 | 1,960.00 | 2,070.00 | 8,280.00 | | 0198 | TS-P26-15040 | Waterline (8" Ductile Iron) (Restrained) (Jefferson Parish) | 100 | LNFT | 225.00 | 22,500.00 | 193.93 | 19,392.60 | 150.00 | 15,000.00 | 90.00 | 9,000.00 | | 0199 | TS-P26-15044 | Waterline (12" Ductile Iron) (Restrained) (Jefferson Parish) | 100 | LNFT | 250.00 | 25,000.00 | 275.49 | 27,549.10 | 195.00 | 19,500.00 | 137.00 | 13,700.00 | | 0200 | TS-P26-15048 | Waterline (24" PVC) (Restrained) (Jefferson Parish) | 1,035 | LNFT | 325.00 | 336,375.00 | 259.82 | 268,908.53 | 235.00 | 243,225.00 | 260.00 | 269,100.00 | | 0201 | TS-P26-15122 | Waterline (8" PVC) (Restrained) (Jefferson Parish) | 250 | LNFT | 175.00 | 43,750.00 | 153.64 | 38,409.00 | 115.00 | 28,750.00 | 56.00 | 14,000.00 | | 0202 | TS-P26-70100 | Fittings for Waterlines (DI) | 4,000 | LB | 3.00 | 12,000.00 | 3.64 | 14,576.00 | 3.50 | 14,000.00 | 4.30 | 17,200.00 | | 0203 | TS-P26-70102 | Transitional Coupling (12") | 2 | EACH | 1.00 | 2.00 | 4,775.23 | 9,550.45 | 1,500.00 | 3,000.00 | 426.00 | 852.00 | | 0204 | TS-P26-70103 | Removal and Disposal of Existing AC Waterline | 250 | LNFT | 1.00 | 250.00 | 9.88 | 2,470.75 | 45.00 | 11,250.00 | 38.00 | 9,500.00 | | 0205 | TS-P26-70104 | Transitional Coupling (8") | 17 | EACH | 1.00 | 17.00 | 2,464.76 | 41,900.87 | 1,300.00 | 22,100.00 | 300.00 | 5,100.00 | | 0206 | TS-P26-70110 | Transitional Coupling (24") | 3 | EACH | 1.00 | 3.00 | 5,665.07 | 16,995.20 | 10,100.00 | 30,300.00 | 2,300.00 | 6,900.00 | | 0207 | TS-P26-70120 | Jefferson Parish Standard Trench Drain | 4 | EACH | 7,500.00 | 30,000.00 | 22,869.68 | 91,478.70 | 13,000.00 | 52,000.00 | 20,100.00 | 80,400.00 | | 0208 | TS-P26-70221 | Manhole (Drainage) | 4 | EACH | 3,500.00 | 14,000.00 | 4,984.57 | 19,938.28 | 5,000.00 | 20,000.00 | 7,000.00 | 28,000.00 | | 0209 | TS-P26-70228 | Jefferson Parish Standard Catch Basin (CB-01) (Brick) | 2 | EACH | 4,000.00 | 8,000.00 | 5,258.16 | 10,516.32 | 4,600.00 | 9,200.00 | 7,400.00 | 14,800.00 | | 0210 | TS-P26-70230 | Jefferson Parish Standard Catch Basin (CB-01 Mod.) (Brick) | 1 | EACH | 4,000.00 | 4,000.00 | 6,244.69 | 6,244.69 | 4,600.00 | 4,600.00 | 7,400.00 | 7,400.00 | | 0211 | TS-P26-70231 | Jefferson Parish Standard Catch Basin (Double CB-01 Mod.) (Brick) | 1 | EACH | 5,000.00 | 5,000.00 | 8,594.06 | 8,594.06 | 9,300.00 | 9,300.00 | 12,200.00 | 12,200.00 | | 0212 | TS-P26-70232 | Catch Basin (Type 2) | 12 | EACH | 4,000.00 | 48,000.00 | 3,313.43 | 39,761.10 | 4,600.00 | 55,200.00 | 6,200.00 | 74,400.00 | | 0213 | TS-P26-70252 | Jefferson Parish Standard Catch Basin (CB-07) (Brick) | 8 | EACH | 4,500.00 | 36,000.00 | 5,838.55 | 46,708.41 | 9,900.00 | 79,200.00 | 12,600.00 | 100,800.00 | | 0214 | TS-P26-70253 | Jefferson Parish Standard Catch Basin (Double CB-07) (Brick) | 2 | EACH | 7,000.00 | 14,000.00 | 11,820.52 | 23,641.04 | 17,000.00 | 34,000.00 | 21,600.00 | 43,200.00 | | 0215 | TS-P26-70260 | Jefferson Parish Standard Catch Basin (CB-09) (Brick) | 18 | EACH | 5,000.00 | 90,000.00 | 11,967.57 | 215,416.19 | 6,800.00 | 122,400.00 | 14,500.00 | 261,000.00 | | 0216 | TS-P26-70262 | Jefferson Parish Standard Catch Basin (Double CB-09) (Brick) | 15 | EACH | 6,000.00 | 90,000.00 | 16,663.65 | 249,954.75 | 10,500.00 | 157,500.00 | 18,000.00 | 270,000.00 | | 0217 | TS-P26-70264 | Jefferson Parish Standard Catch Basin (Type A) (Brick) | 4 | EACH | 5,000.00 | 20,000.00 | 14,595.65 | 58,382.60 | 4,000.00 | 16,000.00 | 12,400.00 | 49,600.00 | | 0218 | TS-P26-70265 | Jefferson Parish Standard Catch Basin (Double Type A) (Brick) | 2 | EACH | 4,000.00 | 8,000.00 | 24,115.07 | 48,230.14 | 10,000.00 | 20,000.00 | 19,000.00 | 38,000.00 | | 0219 | TS-P26-70266 | Jefferson Parish Standard Catch Basin (Double CB-09/Type A) (Brick) | 4 | EACH | 5,000.00 | 20,000.00 | 24,668.58 | 98,674.33 | 12,550.00 | 50,200.00 | 19,000.00 | 76,000.00 | | 0220 | TS-P26-70280 | Jefferson Parish Standard Drain Inlet Mod. | 2 | EACH | 5,000.00 | 10,000.00 | 8,116.81 | 16,233.62 | 5,000.00 | 10,000.00 | 13,000.00 | 26,000.00 | | 0221 | TS-P26-74101 | Water Service Connections (<1") | 2 | EACH | 1,000.00 | 2,000.00 | 1,701.50 | 3,403.00 | 1,000.00 | 2,000.00 | 380.00 | 760.00 | | 0222 | TS-P26-74101 | Water Service Connections (1") | 2 | EACH | 1,000.00 | 2,000.00 | 1,701.50 | 3,403.00 | 1,000.00 | 2,000.00 | 850.00 | 1,700.00 | | 0223 | TS-P26-74101 | Water Service Connections (2") | 2 | EACH | 1,000.00 | 2,000.00 | 1,991.41 | 3,982.82 | 2,000.00 | 4,000.00 | 1,350.00 | 2,700.00 | | 0224 | TS-P26-74210 | Jefferson Parish Standard Conflict Box | 1 | EACH | 20,000.00 | 20,000.00 | 21,522.77 | 21,522.77 | 12,500.00 | 12,500.00 | 31,000.00 | 31,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 11,590,744.76 | | 13,206,674.16 | | 12,411,103.32 | | 14,786,054.98 |
|