Bid Tabulations for the Letting of 7/10/2019 LA DOTD Headquarters

Proposal:H.012934.6
Parish:Ascension
Routes:LA 936
Description:LA 936: W JCT LA 22 - E JCT LA 22
Type Construction:GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, LIME TREATMENT, IN-PLACE CEMENT TREATED BASE COURSE, IN-PLACE CEMENT TREATED SUBGRADE, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$2,185,404.18
Rank License BidderConstruction Bid
100046Barber Bros. Contracting Co., L.L.C$1,325,873.80
200481COASTAL BRIDGE CO., L.L.C.$1,413,835.88
306276Barriere Construction Co., LLC$1,423,571.10
412031R.J. Daigle & Sons Contractors, Inc$1,520,125.45


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barber Bros. Contracting Co., L.L.C
- 2 -
COASTAL BRIDGE CO., L.L.C.
- 3 -
Barriere Construction Co., LLC
- 4 -
R.J. Daigle & Sons Contractors, Inc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-14500Removal of Guard Rail 375     LNFT7.002,625.008.503,187.506.002,250.006.702,512.50
0002202-02-32100Removal of Pipe (Cross Drain) (24" RCP)4     LNFT30.00120.001.004.008.0032.001.004.00
0003203-07-00100Borrow (Vehicular Measurement) 254     CUYD22.005,588.005.001,270.0040.0010,160.0073.3618,633.44
0004203-07-00100Borrow (Vehicular Measurement) (Superelevation Correction)54     CUYD28.001,512.005.00270.0020.001,080.00184.629,969.48
0005203-10-00100Cleaning Existing Ditches 800     LNFT5.504,400.0010.008,000.0010.008,000.006.345,072.00
0006204-05-00100Temporary Sediment Check Dams (Hay) 40     EACH85.003,400.003.00120.0085.003,400.00135.965,438.40
0007204-06-00100Temporary Silt Fencing 511     LNFT1.25638.751.00511.002.251,149.753.181,624.98
0008303-03-00400In-Place Cement Treated Base Course (12" Thick) 14,197     SQYD7.50106,477.5010.00141,970.008.30117,835.109.36132,883.92
0009304-01-00100Lime 70.44  TON225.0015,849.001.0070.44275.0019,371.00211.0014,862.84
0010304-03-00400Lime Treatment (Type C) (12" Thick) 4,969     SQYD1.004,969.001.004,969.005.5027,329.502.1610,733.04
0011309-01-12000In-Place Cement Treated Subgrade (12" Thick) 2,130     SQYD10.2521,832.505.0010,650.0011.0023,430.0028.5560,811.50
0012401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 195     CUYD45.008,775.0075.0014,625.00100.0019,500.0029.655,781.75
0013402-01-00100Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 18     CUYD100.001,800.001.0018.00150.002,700.00173.333,119.94
0014502-01-00100Asphalt Concrete 7,434     TON84.00624,456.0091.50680,211.0083.75622,597.5086.19640,736.46
0015502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 352.4   TON122.0042,992.8091.5032,244.60190.0066,956.00135.3447,693.82
0016507-01-00100Asphalt Material (CRS-2P Emulsion) 9,268     GAL2.7525,487.002.7525,487.002.7525,487.003.3230,769.76
0017507-02-00200Aggregate (S2) 13,629     SQYD1.9025,895.102.0728,212.031.9025,895.102.2831,074.12
0018507-02-00300Aggregate (S3) 13,629     SQYD1.7023,169.301.7023,169.301.7023,169.302.0227,530.58
0019509-01-00100Milling Asphalt Pavement 53,021     SQYD1.95103,390.951.0053,021.001.8598,088.852.16114,525.36
0020509-02-00100Contractor Retained Reclaimed Asphalt Pavement -2,209     CUYD0.000.000.01-22.0930.00-66,270.000.01-22.09
0021510-01-00300Pavement Patching (18" Minimum Thickness) 597     SQYD110.0065,670.00100.0059,700.0095.0056,715.00159.6295,293.14
0022701-08-00100Relaying Pipe 24     LNFT170.004,080.00250.006,000.00150.003,600.00219.105,258.40
0023701-10-01060Reinforced Concrete Pipe (Extension) (24") 16     LNFT150.002,400.00500.008,000.00150.002,400.00338.395,414.24
0024701-15-00100Concrete Collar 5     EACH1,400.007,000.001,500.007,500.002,500.0012,500.001,087.205,436.00
0025701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 12     LNFT5.0060.00200.002,400.001.0012.0060.00720.00
0026704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 120     LNFT42.005,040.0030.003,600.0041.004,920.0044.885,385.60
0027704-03-00100Blocked Out Guard rail 31.3   LNFT32.001,001.6024.00751.2031.00970.3034.071,066.39
0028704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 37.5   LNFT23.00862.5024.00900.0022.00825.0024.53919.88
0029704-05-00100Guard Rail Anchor Sections (Trailing End) 6.3   LNFT160.001,008.00115.00724.50150.00945.00166.721,050.34
0030704-07-00200Guard Rail Transitions (Double Thrie Beam) 100     LNFT88.008,800.0080.008,000.0085.008,500.0091.639,163.00
0031704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 3     EACH3,000.009,000.003,200.009,600.003,000.009,000.003,237.409,712.20
0032711-03-00300Riprap (30 lb) 10     TON155.001,550.00145.001,450.00270.002,700.00301.803,018.00
0033711-04-00100Geotextile Fabric 8     SQYD3.0024.0016.00128.001.008.001.9815.84
0034713-01-00100Temporary Signs and Barricades 1     LUMP50,000.0050,000.0025,000.0025,000.0095,000.0095,000.0024,600.0024,600.00
0035713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 11.331 MILE200.002,266.20300.003,399.30100.001,133.10146.831,663.73
0036713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 3.444 MILE300.001,033.20325.001,119.30300.001,033.20303.031,043.64
0037713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 40.44  MILE100.004,044.00500.0020,220.00600.0024,264.00660.0026,690.40
0038713-06-00200Temporary Reflectorized Raised Pavement Markers (Tabs) 516     EACH3.001,548.003.501,806.002.001,032.003.301,702.80
0039722-02-00100Project Site Laboratory (Equipped) 1     EACH2,500.002,500.0010,000.0010,000.007,500.007,500.001,500.001,500.00
0040726-01-00100Bedding Material 14.2   CUYD65.00923.005.0071.0085.001,207.0060.30856.26
0041727-01-00100Mobilization 1     LUMP59,000.0059,000.00138,000.00138,000.0085,000.0085,000.0070,000.0070,000.00
0042729-16-00200Object Marker Assembly (Type 2) 18     EACH72.001,296.0045.00810.0080.001,440.0077.001,386.00
0043729-16-00300Object Marker Assembly (Type 3) 4     EACH84.00336.0075.00300.0085.00340.0088.00352.00
0044731-02-00100Reflectorized Raised Pavement Markers 571     EACH5.002,855.006.003,426.005.002,855.006.333,614.43
0045732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 36     LNFT12.50450.009.00324.0012.00432.0016.50594.00
0046732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 13.48  MILE3,000.0040,440.002,950.0039,766.002,900.0039,092.003,190.0043,001.20
0047732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.148 MILE800.00918.401,100.001,262.80800.00918.401,101.921,265.00
0048735-01-00100Mailboxes 106     EACH15.001,590.0020.002,120.001.00106.0018.151,923.90
0049735-02-00100Mailbox Supports (Single) 106     EACH125.0013,250.00120.0012,720.00127.0013,462.00145.2015,391.20
0050739-01-00100Hydro-Seeding 0.5   ACRE1,500.00750.003,500.001,750.003,000.001,500.004,264.112,132.06
0051740-01-00100Construction Layout 1     LUMP12,800.0012,800.0015,000.0015,000.0012,000.0012,000.0016,200.0016,200.00
             
  CONTRACTOR TOTAL   1,325,873.80 1,413,835.88 1,423,571.10 1,520,125.45