Proposal:H.011917.6
Parish:Caddo
Routes:I-49
Description:I-49 CB: MLK DR. TO ARKANSAS S/L
Type Construction:HIGH TENSION CABLE BARRIER, CONCRETE STRIP, DRILLED SHAFT FOUNDATIONS, AND RELATED WORK.
Estimated Construction Cost:$5,623,464.83
| Rank | License | Bidder | Construction Bid |
| 1 | 58815 | Simmons Erosion Control, Inc. | $7,024,714.68 |
| 2 | 39462 | JB JAMES CONSTRUCTION LLC | $7,216,154.00 |
| 3 | 43371 | Rmd Holdings Ltd. | $7,395,432.82 |
| 4 | 12312 | GILCHRIST CONSTRUCTION CO. LLC | $7,957,215.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Simmons Erosion Control, Inc. | - 2 - JB JAMES CONSTRUCTION LLC | - 3 - Rmd Holdings Ltd. | - 4 - GILCHRIST CONSTRUCTION CO. LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 130 | SQYD | 14.50 | 1,885.00 | 40.00 | 5,200.00 | 44.44 | 5,777.20 | 15.00 | 1,950.00 | | 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 5,000 | CUYD | 5.00 | 25,000.00 | 26.00 | 130,000.00 | 17.78 | 88,900.00 | 20.00 | 100,000.00 | | 0003 | 204-02-00100 | Temporary Hay Bales | 70 | EACH | 14.00 | 980.00 | 25.00 | 1,750.00 | 16.67 | 1,166.90 | 50.00 | 3,500.00 | | 0004 | 204-06-00100 | Temporary Silt Fencing | 6,000 | LNFT | 1.00 | 6,000.00 | 3.00 | 18,000.00 | 3.33 | 19,980.00 | 4.00 | 24,000.00 | | 0005 | 702-04-00200 | Adjusting Catch Basins | 10 | EACH | 1,000.00 | 10,000.00 | 2,000.00 | 20,000.00 | 1,161.11 | 11,611.10 | 3,500.00 | 35,000.00 | | 0006 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 130 | SQYD | 65.00 | 8,450.00 | 80.00 | 10,400.00 | 72.09 | 9,371.70 | 120.00 | 15,600.00 | | 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 35,000.00 | 35,000.00 | 265,000.00 | 265,000.00 | 369,722.22 | 369,722.22 | 300,000.00 | 300,000.00 | | 0008 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 7,500.00 | 15,000.00 | 12,000.00 | 24,000.00 | 6,805.56 | 13,611.12 | 10,000.00 | 20,000.00 | | 0009 | 716-01-00100 | Mulch (Vegetative) | 264 | TON | 295.00 | 77,880.00 | 500.00 | 132,000.00 | 611.11 | 161,333.04 | 175.00 | 46,200.00 | | 0010 | 717-01-00100 | Seeding | 7,941 | LB | 5.00 | 39,705.00 | 12.00 | 95,292.00 | 13.33 | 105,853.53 | 4.00 | 31,764.00 | | 0011 | 718-01-00100 | Fertilizer | 132,350 | LB | 0.30 | 39,705.00 | 0.40 | 52,940.00 | 0.72 | 95,292.00 | 0.15 | 19,852.50 | | 0012 | 727-01-00100 | Mobilization | 1 | LUMP | 700,000.00 | 700,000.00 | 700,000.00 | 700,000.00 | 721,396.67 | 721,396.67 | 750,000.00 | 750,000.00 | | 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 66,000.00 | 66,000.00 | 27,777.78 | 27,777.78 | 190,000.00 | 190,000.00 | | 0014 | NS-704-00001 | High Tension Cable Barrier | 164,794 | LNFT | 9.72 | 1,601,797.68 | 10.00 | 1,647,940.00 | 10.12 | 1,667,715.28 | 8.50 | 1,400,749.00 | | 0015 | NS-704-00002 | Cable Barrier Gated End Terminal | 98 | EACH | 4,600.00 | 450,800.00 | 3,000.00 | 294,000.00 | 2,950.94 | 289,192.12 | 4,500.00 | 441,000.00 | | 0016 | NS-704-00003 | Concrete Strip | 91,552 | SQYD | 43.50 | 3,982,512.00 | 41.00 | 3,753,632.00 | 41.58 | 3,806,732.16 | 50.00 | 4,577,600.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 7,024,714.68 | | 7,216,154.00 | | 7,395,432.82 | | 7,957,215.50 |
|