Proposal:H.009587.6
Parish:Concordia
Routes:US 84
Description:US 84: MISSISSIPPI RIVER BR. - LA 3180
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, WIRELESS MAGNETOMETER VEHICLE DETECTION SYSTEM, AND RELATED WORK.
Estimated Construction Cost:$2,284,196.12
Rank | License | Bidder | Construction Bid |
1 | 05789 | D & J CONSTRUCTION CO., LLC | $2,562,019.70 |
2 | 12312 | GILCHRIST CONSTRUCTION CO. LLC | $2,662,702.45 |
3 | 02214 | W. E. BLAIN & SONS, INC. | $2,826,141.49 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - D & J CONSTRUCTION CO., LLC | - 2 - GILCHRIST CONSTRUCTION CO. LLC | - 3 - W. E. BLAIN & SONS, INC. | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | 0001 | 202-02-02020 | Removal of Asphalt Pavement | 300 | SQYD | 7.50 | 2,250.00 | 13.00 | 3,900.00 | 22.30 | 6,690.00 | 0002 | 202-02-14500 | Removal of Guard Rail | 361 | LNFT | 20.00 | 7,220.00 | 13.00 | 4,693.00 | 9.00 | 3,249.00 | 0003 | 202-02-40120 | Removal of Traffic Detectors and Associated Equipment | 1 | LUMP | 3,500.00 | 3,500.00 | 25,000.00 | 25,000.00 | 3,360.00 | 3,360.00 | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 84 | CUYD | 60.00 | 5,040.00 | 50.00 | 4,200.00 | 58.00 | 4,872.00 | 0005 | 502-01-00100 | Asphalt Concrete Level 2F PG 76-22m | 11,426.8 | TON | 107.00 | 1,222,667.60 | 95.00 | 1,085,546.00 | 124.00 | 1,416,923.20 | 0006 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 647.8 | TON | 146.00 | 94,578.80 | 95.00 | 61,541.00 | 225.00 | 145,755.00 | 0007 | 509-01-00100 | Milling Asphalt Pavement | 106,521 | SQYD | 2.75 | 292,932.75 | 2.00 | 213,042.00 | 2.10 | 223,694.10 | 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -4,438 | CUYD | 1.00 | -4,438.00 | 1.00 | -4,438.00 | 1.00 | -4,438.00 | 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 850 | SQYD | 140.00 | 119,000.00 | 115.00 | 97,750.00 | 138.00 | 117,300.00 | 0010 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 400 | SQYD | 160.00 | 64,000.00 | 180.00 | 72,000.00 | 218.00 | 87,200.00 | 0011 | 602-03-00100 | Cleaning and Sealing Random cracks | 10,000 | LNFT | 2.70 | 27,000.00 | 3.25 | 32,500.00 | 2.70 | 27,000.00 | 0012 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 125 | SQYD | 300.00 | 37,500.00 | 210.00 | 26,250.00 | 293.00 | 36,625.00 | 0013 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 100 | SQYD | 275.00 | 27,500.00 | 210.00 | 21,000.00 | 266.00 | 26,600.00 | 0014 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 125 | LNFT | 25.00 | 3,125.00 | 27.50 | 3,437.50 | 26.00 | 3,250.00 | 0015 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 25 | LNFT | 55.00 | 1,375.00 | 85.00 | 2,125.00 | 68.00 | 1,700.00 | 0016 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 80.00 | 4,000.00 | 87.00 | 4,350.00 | 90.00 | 4,500.00 | 0017 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 2 | EACH | 2,600.00 | 5,200.00 | 3,000.00 | 6,000.00 | 3,000.00 | 6,000.00 | 0018 | 706-04-00100 | Handicapped Curb Ramps Type 4 | 1 | EACH | 2,600.00 | 2,600.00 | 5,000.00 | 5,000.00 | 2,665.00 | 2,665.00 | 0019 | 707-04-00100 | Asphalt Curb | 27 | LNFT | 60.00 | 1,620.00 | 200.00 | 5,400.00 | 215.00 | 5,805.00 | 0020 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 115,000.00 | 115,000.00 | 158,000.00 | 158,000.00 | 140,000.00 | 140,000.00 | 0021 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 5,166 | LNFT | 0.25 | 1,291.50 | 0.35 | 1,808.10 | 0.20 | 1,033.20 | 0022 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 980 | LNFT | 0.25 | 245.00 | 1.00 | 980.00 | 0.30 | 294.00 | 0023 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 20.854 | MILE | 200.00 | 4,170.80 | 200.00 | 4,170.80 | 370.00 | 7,715.98 | 0024 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 20.854 | MILE | 400.00 | 8,341.60 | 200.00 | 4,170.80 | 320.00 | 6,673.28 | 0025 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 22.111 | MILE | 650.00 | 14,372.15 | 600.00 | 13,266.60 | 530.00 | 11,718.83 | 0026 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 188 | EACH | 10.00 | 1,880.00 | 50.00 | 9,400.00 | 1.00 | 188.00 | 0027 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 2 | EACH | 10.00 | 20.00 | 50.00 | 100.00 | 1.00 | 2.00 | 0028 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 950 | SQYD | 2.25 | 2,137.50 | 2.75 | 2,612.50 | 5.00 | 4,750.00 | 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 115,000.00 | 115,000.00 | 260,000.00 | 260,000.00 | 170,000.00 | 170,000.00 | 0030 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 100.00 | 200.00 | 85.00 | 170.00 | 90.00 | 180.00 | 0031 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,024 | EACH | 5.00 | 10,120.00 | 6.00 | 12,144.00 | 4.80 | 9,715.20 | 0032 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 2,583 | LNFT | 2.00 | 5,166.00 | 1.25 | 3,228.75 | 1.30 | 3,357.90 | 0033 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 490 | LNFT | 8.50 | 4,165.00 | 6.50 | 3,185.00 | 6.60 | 3,234.00 | 0034 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 11.056 | MILE | 2,500.00 | 27,640.00 | 2,800.00 | 30,956.80 | 2,300.00 | 25,428.80 | 0035 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 9.536 | MILE | 850.00 | 8,105.60 | 850.00 | 8,105.60 | 850.00 | 8,105.60 | 0036 | 732-03-02102 | Plastic Pav't Striping (Broken) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black and White Contrast) | 0.891 | MILE | 2,000.00 | 1,782.00 | 4,500.00 | 4,009.50 | 5,000.00 | 4,455.00 | 0037 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 75 | EACH | 210.00 | 15,750.00 | 200.00 | 15,000.00 | 155.00 | 11,625.00 | 0038 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 19 | EACH | 210.00 | 3,990.00 | 200.00 | 3,800.00 | 155.00 | 2,945.00 | 0039 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 420.00 | 420.00 | 200.00 | 200.00 | 210.00 | 210.00 | 0040 | 732-05-00100 | Removal of Existing Markings PCC section only | 0.891 | MILE | 5,000.00 | 4,455.00 | 10,000.00 | 8,910.00 | 5,000.00 | 4,455.00 | 0041 | 735-01-00100 | Mailboxes | 3 | EACH | 50.00 | 150.00 | 50.00 | 150.00 | 25.00 | 75.00 | 0042 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 300.00 | 300.00 | 250.00 | 250.00 | 123.00 | 123.00 | 0043 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 400.00 | 400.00 | 350.00 | 350.00 | 160.00 | 160.00 | 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 25,000.00 | 25,000.00 | 3,400.00 | 3,400.00 | 0045 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 53,666 | LNFT | 1.15 | 61,715.90 | 2.00 | 107,332.00 | 1.05 | 56,349.30 | 0046 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 24,904 | LNFT | 1.25 | 31,130.00 | 2.00 | 49,808.00 | 1.15 | 28,639.60 | 0047 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 78,570 | LNFT | 1.15 | 90,355.50 | 1.75 | 137,497.50 | 1.05 | 82,498.50 | 0048 | NS-602-00001 | Milling Concrete Pavement | 149 | SQYD | 35.00 | 5,215.00 | 100.00 | 14,900.00 | 51.00 | 7,599.00 | 0049 | NS-736-00020 | Wireless Magnetometer Vehicle Detection System (Cabinet Components) | 6 | EACH | 4,700.00 | 28,200.00 | 5,000.00 | 30,000.00 | 4,900.00 | 29,400.00 | 0050 | NS-736-00021 | Wireless Magnetometer Vehicle Detection System (Antennas) | 6 | EACH | 4,250.00 | 25,500.00 | 5,000.00 | 30,000.00 | 4,475.00 | 26,850.00 | 0051 | NS-736-00022 | Wireless Magnetometer Vehicle Detection System (Magnetometers) | 77 | EACH | 690.00 | 53,130.00 | 700.00 | 53,900.00 | 730.00 | 56,210.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,562,019.70 | | 2,662,702.45 | | 2,826,141.49 |
|