Proposal:H.012451.6
Parish:Bienville, Caddo, Webster
Routes:I-20, I-49
Description:DISTRICT 04 - MISCELLANEOUS BRIDGE REPAIRS
Type Construction:BRIDGE REPAIRS AND RELATED WORK.
Estimated Construction Cost:$1,211,815.00
| Rank | License | Bidder | Construction Bid |
| 1 | 44133 | Gibson & Associates Inc. | $1,366,805.00 |
| 2 | 39462 | JB JAMES CONSTRUCTION LLC | $1,884,100.00 |
| 3 | 49239 | WL Bass Construction Inc. | $2,107,225.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Gibson & Associates Inc. | - 2 - JB JAMES CONSTRUCTION LLC | - 3 - WL Bass Construction Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-00050 | Removal of Debris (Bridge Substructure) | 1 | LUMP | 18,000.00 | 18,000.00 | 150,000.00 | 150,000.00 | 160,000.00 | 160,000.00 | | 0002 | 202-02-00050 | Removal of Debris (Bridge Superstructure) | 1 | LUMP | 18,000.00 | 18,000.00 | 40,000.00 | 40,000.00 | 80,000.00 | 80,000.00 | | 0003 | 202-02-04560 | Removal of Bridge Joint (Joint Armor and Concrete) | 1,555 | LNFT | 10.00 | 15,550.00 | 250.00 | 388,750.00 | 48.00 | 74,640.00 | | 0004 | 202-02-04560 | Removal of Bridge Joint (Joint Sealants) | 120 | LNFT | 10.00 | 1,200.00 | 60.00 | 7,200.00 | 20.00 | 2,400.00 | | 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 210,000.00 | 210,000.00 | 150,000.00 | 150,000.00 | 300,000.00 | 300,000.00 | | 0006 | 713-11-00100 | Portable Changeable Message Signs | 6 | EACH | 5,000.00 | 30,000.00 | 4,000.00 | 24,000.00 | 6,000.00 | 36,000.00 | | 0007 | 727-01-00100 | Mobilization | 1 | LUMP | 115,000.00 | 115,000.00 | 100,000.00 | 100,000.00 | 210,000.00 | 210,000.00 | | 0008 | 815-03-00200 | Joint Seal (Preformed Silicone) | 1,675 | LNFT | 85.00 | 142,375.00 | 40.00 | 67,000.00 | 55.00 | 92,125.00 | | 0009 | 830-02-00100 | Bridge Substructure Repair (End Bent Repair - Type 1) | 1 | EACH | 16,000.00 | 16,000.00 | 15,000.00 | 15,000.00 | 58,000.00 | 58,000.00 | | 0010 | 830-07-00100 | Structural Concrete Patching | 248 | SQFT | 285.00 | 70,680.00 | 550.00 | 136,400.00 | 150.00 | 37,200.00 | | 0011 | 830-09-00100 | Structure Jacking | 1 | LUMP | 25,000.00 | 25,000.00 | 85,000.00 | 85,000.00 | 135,000.00 | 135,000.00 | | 0012 | 830-10-00100 | Epoxy Injection | 21 | LNFT | 250.00 | 5,250.00 | 1,000.00 | 21,000.00 | 210.00 | 4,410.00 | | 0013 | NS-830-01100 | Bridge Deck Joint Repair (Both Sides of Joint) | 1,555 | LNFT | 450.00 | 699,750.00 | 450.00 | 699,750.00 | 590.00 | 917,450.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,366,805.00 | | 1,884,100.00 | | 2,107,225.00 |
|