Proposal:H.012082.6
Parish:West Baton Rouge
Routes:LA 1
Description:LA 1: PORT ALLEN BR. INT. REPAIRS (HBI)
Type Construction:REMOVAL OF BRIDGE DECK (HYDRODEMOLITION), STRUCTURAL METALWORK, BRIDGE REPAIRS, AND RELATED WORK.
Estimated Construction Cost:$4,536,433.50
Maximum Number of Days Allowed for Construction:180
Calculated Daily User Cost:$9,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 39462 | JB JAMES CONSTRUCTION LLC | $2,847,588.00 | 120.00 | $3,927,588.00 |
| 2 | 26435 | C.E.C., Inc. | $3,393,644.32 | 90.00 | $4,203,644.32 |
| 3 | 44133 | Gibson & Associates Inc. | $3,527,698.45 | 165.00 | $5,012,698.45 |
| 4 | 00481 | COASTAL BRIDGE CO., L.L.C. | $4,151,503.00 | 172.00 | $5,699,503.00 |
| 5 | 59114 | SOUTHERN ROAD & BRIDGE, LLC | $5,056,293.00 | 150.00 | $6,406,293.00 |
| 6 | 33131 | AMERICAN CONTRACTING & SERVICES,INC | $5,396,809.66 | 180.00 | $7,016,809.66 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - JB JAMES CONSTRUCTION LLC | - 2 - C.E.C., Inc. | - 3 - Gibson & Associates Inc. | - 4 - COASTAL BRIDGE CO., L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-00050 | Removal of REMOVAL OF RIVETS, ANCHOR BOLTS AND RELATED WORK | 1 | LUMP | 100,000.00 | 100,000.00 | 20,000.00 | 20,000.00 | 38,500.00 | 38,500.00 | 50,000.00 | 50,000.00 | | 0002 | 202-02-04510 | Removal of Bridge Deck (Hydro Demolition) (ADJACENT TO JOINT) | 48,713 | SFIN | 12.50 | 608,912.50 | 11.00 | 535,843.00 | 23.35 | 1,137,448.55 | 23.00 | 1,120,399.00 | | 0003 | 202-02-04560 | Removal of Bridge Joint (ARMOR) | 1,596 | LNFT | 40.00 | 63,840.00 | 15.00 | 23,940.00 | 2.00 | 3,192.00 | 160.00 | 255,360.00 | | 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 400,000.00 | 400,000.00 | 150,000.00 | 150,000.00 | 87,000.00 | 87,000.00 | 350,000.00 | 350,000.00 | | 0005 | 713-11-00100 | Portable Changeable Message Signs | 5 | EACH | 7,500.00 | 37,500.00 | 24,000.00 | 120,000.00 | 7,300.00 | 36,500.00 | 25,000.00 | 125,000.00 | | 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 280,000.00 | 280,000.00 | 300,000.00 | 300,000.00 | 310,000.00 | 310,000.00 | 287,000.00 | 287,000.00 | | 0007 | 731-02-00100 | Reflectorized Raised Pavement Markers | 289 | EACH | 6.50 | 1,878.50 | 9.60 | 2,774.40 | 6.60 | 1,907.40 | 8.00 | 2,312.00 | | 0008 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) (SOLID WHITE) | 1.87 | MILE | 3,000.00 | 5,610.00 | 4,200.00 | 7,854.00 | 3,298.90 | 6,168.94 | 3,600.00 | 6,732.00 | | 0009 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) (SOLID YELLOW) | 0.935 | MILE | 2,800.00 | 2,618.00 | 4,200.00 | 3,927.00 | 3,298.90 | 3,084.47 | 3,600.00 | 3,366.00 | | 0010 | 732-03-02001 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermo 90 mil)(Blk Cont) | 0.468 | MILE | 1,000.00 | 468.00 | 1,440.00 | 673.92 | 4,888.40 | 2,287.77 | 3,000.00 | 1,404.00 | | 0011 | 732-05-00100 | Removal of Existing Markings | 0.935 | MILE | 5,000.00 | 4,675.00 | 8,400.00 | 7,854.00 | 6,110.50 | 5,713.32 | 6,000.00 | 5,610.00 | | 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 7,920.00 | 7,920.00 | 1,000.00 | 1,000.00 | 25,000.00 | 25,000.00 | | 0013 | 807-01-00200 | Structural Metalwork (Grade 50) (COLUMN REPAIR SPLICE PLATE) | 1,660 | LUMP | 25,000.00 | 25,000.00 | 2,300.00 | 2,300.00 | 7,200.00 | 7,200.00 | 45,000.00 | 45,000.00 | | 0014 | 807-01-00200 | Structural Metalwork (Grade 50) (GUARD RAIL SUPPORT) | 2,500 | LUMP | 350,000.00 | 350,000.00 | 120,000.00 | 120,000.00 | 135,000.00 | 135,000.00 | 180,000.00 | 180,000.00 | | 0015 | 807-01-00800 | Structural Metalwork (GRADE 55)(INSTALLATION OF NEW ANCHOR BOLTS) | 950 | LUMP | 100,000.00 | 100,000.00 | 80,000.00 | 80,000.00 | 137,000.00 | 137,000.00 | 150,000.00 | 150,000.00 | | 0016 | 811-01-00100 | Cleaning and Painting (ANCHOR BOLT AND COLUMN REPAIR) | 1 | LUMP | 150,000.00 | 150,000.00 | 75,000.00 | 75,000.00 | 115,000.00 | 115,000.00 | 25,000.00 | 25,000.00 | | 0017 | 815-02-00200 | Sealed Expansion Joint (End Dams and Preformed Silicone Seal) | 756 | LNFT | 200.00 | 151,200.00 | 180.00 | 136,080.00 | 190.00 | 143,640.00 | 95.00 | 71,820.00 | | 0018 | 815-03-00300 | Joint Seal (Poured) | 840 | LNFT | 30.00 | 25,200.00 | 30.00 | 25,200.00 | 25.00 | 21,000.00 | 50.00 | 42,000.00 | | 0019 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 3,396 | INLF | 3.50 | 11,886.00 | 5.50 | 18,678.00 | 1.00 | 3,396.00 | 5.00 | 16,980.00 | | 0020 | NS-830-01100 | Bridge Deck Joint Repair (Both Sides of Joint) | 1,596 | LNFT | 300.00 | 478,800.00 | 1,100.00 | 1,755,600.00 | 835.00 | 1,332,660.00 | 870.00 | 1,388,520.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,847,588.00 | | 3,393,644.32 | | 3,527,698.45 | | 4,151,503.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - SOUTHERN ROAD & BRIDGE, LLC | - 6 - AMERICAN CONTRACTING & SERVICES,INC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-00050 | Removal of REMOVAL OF RIVETS, ANCHOR BOLTS AND RELATED WORK | 1 | LUMP | 90,000.00 | 90,000.00 | 14,000.00 | 14,000.00 | | 0002 | 202-02-04510 | Removal of Bridge Deck (Hydro Demolition) (ADJACENT TO JOINT) | 48,713 | SFIN | 30.00 | 1,461,390.00 | 50.50 | 2,460,006.50 | | 0003 | 202-02-04560 | Removal of Bridge Joint (ARMOR) | 1,596 | LNFT | 115.00 | 183,540.00 | 145.00 | 231,420.00 | | 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 250,000.00 | 250,000.00 | 435,000.00 | 435,000.00 | | 0005 | 713-11-00100 | Portable Changeable Message Signs | 5 | EACH | 5,000.00 | 25,000.00 | 18,125.00 | 90,625.00 | | 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 450,000.00 | 450,000.00 | 539,680.96 | 539,680.96 | | 0007 | 731-02-00100 | Reflectorized Raised Pavement Markers | 289 | EACH | 10.00 | 2,890.00 | 4.50 | 1,300.50 | | 0008 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) (SOLID WHITE) | 1.87 | MILE | 5,000.00 | 9,350.00 | 2,800.00 | 5,236.00 | | 0009 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) (SOLID YELLOW) | 0.935 | MILE | 5,000.00 | 4,675.00 | 984.71 | 920.70 | | 0010 | 732-03-02001 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermo 90 mil)(Blk Cont) | 0.468 | MILE | 1,500.00 | 702.00 | 7,863.25 | 3,680.00 | | 0011 | 732-05-00100 | Removal of Existing Markings | 0.935 | MILE | 10,000.00 | 9,350.00 | 3,978.61 | 3,720.00 | | 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 14,000.00 | 14,000.00 | | 0013 | 807-01-00200 | Structural Metalwork (Grade 50) (COLUMN REPAIR SPLICE PLATE) | 1,660 | LUMP | 25,000.00 | 25,000.00 | 8,000.00 | 8,000.00 | | 0014 | 807-01-00200 | Structural Metalwork (Grade 50) (GUARD RAIL SUPPORT) | 2,500 | LUMP | 200,000.00 | 200,000.00 | 160,000.00 | 160,000.00 | | 0015 | 807-01-00800 | Structural Metalwork (GRADE 55)(INSTALLATION OF NEW ANCHOR BOLTS) | 950 | LUMP | 450,000.00 | 450,000.00 | 55,000.00 | 55,000.00 | | 0016 | 811-01-00100 | Cleaning and Painting (ANCHOR BOLT AND COLUMN REPAIR) | 1 | LUMP | 350,000.00 | 350,000.00 | 109,000.00 | 109,000.00 | | 0017 | 815-02-00200 | Sealed Expansion Joint (End Dams and Preformed Silicone Seal) | 756 | LNFT | 425.00 | 321,300.00 | 250.00 | 189,000.00 | | 0018 | 815-03-00300 | Joint Seal (Poured) | 840 | LNFT | 78.00 | 65,520.00 | 45.00 | 37,800.00 | | 0019 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 3,396 | INLF | 6.00 | 20,376.00 | 5.00 | 16,980.00 | | 0020 | NS-830-01100 | Bridge Deck Joint Repair (Both Sides of Joint) | 1,596 | LNFT | 700.00 | 1,117,200.00 | 640.00 | 1,021,440.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 5,056,293.00 | | 5,396,809.66 |
|