Proposal:H.011789.6
Parish:Vermilion
Routes:LA 14
Description:LA 14 BYP: RIGHT TURN LANE AT US 167
Type Construction:GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING, CLASS II BASE COURSE, LIME TREATMENT, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$291,230.90
| Rank | License | Bidder | Construction Bid |
| 1 | 52306 | SIEMA CONSTRUCTION, LLC | $283,250.33 |
| 2 | 33663 | Glenn Lege Construction Inc | $373,462.85 |
| 3 | 51821 | Elliott Construction, LLC | $493,305.96 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - SIEMA CONSTRUCTION, LLC | - 2 - Glenn Lege Construction Inc | - 3 - Elliott Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-02020 | Removal of Asphalt Pavement | 36.6 | SQYD | 24.50 | 896.70 | 35.00 | 1,281.00 | 75.00 | 2,745.00 | | 0002 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 350.7 | LNFT | 4.50 | 1,578.15 | 7.60 | 2,665.32 | 50.00 | 17,535.00 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 219 | SQYD | 13.50 | 2,956.50 | 35.00 | 7,665.00 | 30.00 | 6,570.00 | | 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 15,000.00 | 15,000.00 | 22,250.00 | 22,250.00 | 40,000.00 | 40,000.00 | | 0005 | 204-06-00100 | Temporary Silt Fencing | 400 | LNFT | 2.85 | 1,140.00 | 7.52 | 3,008.00 | 3.00 | 1,200.00 | | 0006 | 302-02-08560 | Class II Base Course (8-1/2" Thick) (Crushed Stone, Recycled Portland Cement Concrete, Blended Calcium Sulfate) | 460.5 | SQYD | 41.50 | 19,110.75 | 46.50 | 21,413.25 | 55.00 | 25,327.50 | | 0007 | 304-01-00100 | Lime | 0.12 | TON | 13,200.00 | 1,584.00 | 10,000.00 | 1,200.00 | 10,000.00 | 1,200.00 | | 0008 | 304-05-00100 | Lime Treatment (Type E) | 236 | SQYD | 13.00 | 3,068.00 | 35.00 | 8,260.00 | 50.00 | 11,800.00 | | 0009 | 402-03-00100 | Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 50 | CUYD | 125.00 | 6,250.00 | 98.00 | 4,900.00 | 115.00 | 5,750.00 | | 0010 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 29 | TON | 272.00 | 7,888.00 | 400.00 | 11,600.00 | 300.00 | 8,700.00 | | 0011 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 415.6 | SQYD | 105.00 | 43,638.00 | 165.00 | 68,574.00 | 125.00 | 51,950.00 | | 0012 | 601-01-10000 | Portland Cement Concrete Pavement (Colored)(inch Thick) (4" Thick) | 27.9 | SQYD | 226.00 | 6,305.40 | 500.01 | 13,950.28 | 250.00 | 6,975.00 | | 0013 | 602-02-00100 | Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints | 6,200 | LNFT | 3.50 | 21,700.00 | 2.74 | 16,988.00 | 6.00 | 37,200.00 | | 0014 | 602-05-03160 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (9" Thick) | 51.1 | SQYD | 207.00 | 10,577.70 | 259.55 | 13,263.01 | 350.00 | 17,885.00 | | 0015 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 14 | LNFT | 246.00 | 3,444.00 | 205.00 | 2,870.00 | 200.00 | 2,800.00 | | 0016 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 14 | LNFT | 95.00 | 1,330.00 | 30.00 | 420.00 | 50.00 | 700.00 | | 0017 | 702-03-00500 | Catch Basins (CB-06) | 1 | EACH | 5,985.00 | 5,985.00 | 4,210.00 | 4,210.00 | 5,500.00 | 5,500.00 | | 0018 | 702-03-00600 | Catch Basins (CB-07) | 1 | EACH | 5,275.00 | 5,275.00 | 5,820.00 | 5,820.00 | 6,000.00 | 6,000.00 | | 0019 | 703-01-00100 | Shoulder Underdrain Systems | 395 | LNFT | 30.00 | 11,850.00 | 22.00 | 8,690.00 | 35.00 | 13,825.00 | | 0020 | 703-02-00100 | Shoulder Outlet Underdrains | 2 | EACH | 1,150.00 | 2,300.00 | 1,000.00 | 2,000.00 | 1,000.00 | 2,000.00 | | 0021 | 706-02-00200 | Concrete Drive (6" Thick) | 93.3 | SQYD | 85.50 | 7,977.15 | 85.00 | 7,930.50 | 95.00 | 8,863.50 | | 0022 | 707-01-00200 | Concrete Curb (Barrier) | 92.5 | LNFT | 21.00 | 1,942.50 | 12.47 | 1,153.48 | 45.00 | 4,162.50 | | 0023 | 707-01-00300 | Concrete Curb (Mountable) | 310.7 | LNFT | 9.00 | 2,796.30 | 13.00 | 4,039.10 | 45.00 | 13,981.50 | | 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 22,700.00 | 22,700.00 | 10,150.00 | 10,150.00 | 50,000.00 | 50,000.00 | | 0025 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 3.82 | MILE | 5,150.00 | 19,673.00 | 6,090.00 | 23,263.80 | 8,625.00 | 32,947.50 | | 0026 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 3 | EACH | 10.25 | 30.75 | 12.18 | 36.54 | 95.00 | 285.00 | | 0027 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 12,000.00 | 12,000.00 | 9,875.00 | 9,875.00 | 15,000.00 | 15,000.00 | | 0028 | 726-01-00100 | Bedding Material | 3.4 | CUYD | 165.00 | 561.00 | 200.00 | 680.00 | 125.00 | 425.00 | | 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 27,000.00 | 27,000.00 | 66,128.35 | 66,128.35 | 45,000.00 | 45,000.00 | | 0030 | 731-02-00100 | Reflectorized Raised Pavement Markers | 120 | EACH | 4.00 | 480.00 | 4.87 | 584.40 | 8.00 | 960.00 | | 0031 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 227 | LNFT | 1.50 | 340.50 | 1.83 | 415.41 | 4.00 | 908.00 | | 0032 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 52 | LNFT | 10.20 | 530.40 | 12.18 | 633.36 | 13.00 | 676.00 | | 0033 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.421 | MILE | 3,060.00 | 1,288.26 | 3,654.00 | 1,538.33 | 6,200.00 | 2,610.20 | | 0034 | 732-03-02001 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermo 90 mil)(Blk Cont) | 0.204 | MILE | 867.00 | 176.87 | 1,035.30 | 211.20 | 4,315.00 | 880.26 | | 0035 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.024 | MILE | 1,020.00 | 24.48 | 1,218.00 | 29.23 | 7,500.00 | 180.00 | | 0036 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.043 | MILE | 1,530.00 | 65.79 | 1,827.00 | 78.56 | 9,500.00 | 408.50 | | 0037 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 205.00 | 205.00 | 243.60 | 243.60 | 350.00 | 350.00 | | 0038 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 205.00 | 410.00 | 243.60 | 487.20 | 350.00 | 700.00 | | 0039 | 732-05-00100 | Removal of Existing Markings | 0.129 | MILE | 3,875.00 | 499.88 | 4,628.00 | 597.01 | 12,500.00 | 1,612.50 | | 0040 | 739-01-00100 | Hydro-Seeding | 0.209 | ACRE | 2,250.00 | 470.25 | 10,230.00 | 2,138.07 | 10,000.00 | 2,090.00 | | 0041 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,800.00 | 2,800.00 | 6,750.00 | 6,750.00 | 25,000.00 | 25,000.00 | | 0042 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 4,201 | INLF | 1.00 | 4,201.00 | 1.85 | 7,771.85 | 3.00 | 12,603.00 | | 0043 | NS-MSC-00120 | Drainage Structure Convert CB top to MH top | 2 | EACH | 2,600.00 | 5,200.00 | 3,850.00 | 7,700.00 | 4,000.00 | 8,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 283,250.33 | | 373,462.85 | | 493,305.96 |
|