Proposal:H.006546.6
Parish:Lafourche
Description: INTERSECTION UPGRADE N CANAL & 7TH ST
Type Construction:GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, MILLING ASPHALT PAVEMENT, ASPAHLT CONCRETE PAVEMENT, DRILLED SHAFT FOUNDATIONS, TRAFFIC SIGNALIZATION, AND RELATED WORK.
Estimated Construction Cost:$499,421.70
| Rank | License | Bidder | Construction Bid |
| 1 | 48896 | Command Construction Industries LLC | $598,512.50 |
| 2 | 06276 | Barriere Construction Co., LLC | $801,105.72 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Command Construction Industries LLC | - 2 - Barriere Construction Co., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 20,000.00 | 20,000.00 | 5,000.00 | 5,000.00 | | 0002 | 202-02-02020 | Removal of Asphalt Pavement | 135.6 | SQYD | 20.00 | 2,712.00 | 20.00 | 2,712.00 | | 0003 | 202-02-06060 | Removal of Concrete Catch Basin | 3 | EACH | 200.00 | 600.00 | 500.00 | 1,500.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 22 | SQYD | 20.00 | 440.00 | 20.00 | 440.00 | | 0005 | 202-02-06140 | Removal of Curbs (Concrete) | 1,347 | LNFT | 2.00 | 2,694.00 | 15.00 | 20,205.00 | | 0006 | 202-02-14000 | Removal of Gas Line | 10 | LNFT | 20.00 | 200.00 | 15.00 | 150.00 | | 0007 | 202-02-32140 | Removal of Pipe (Storm Drain) 15" RCP | 24 | LNFT | 20.00 | 480.00 | 15.00 | 360.00 | | 0008 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 11 | SQYD | 20.00 | 220.00 | 100.00 | 1,100.00 | | 0009 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 5,000.00 | 5,000.00 | 4,800.00 | 4,800.00 | | 0010 | 202-03-38000 | Relocation of Sign Co-Cathered and Speed Limit signs | 2 | EACH | 100.00 | 200.00 | 500.00 | 1,000.00 | | 0011 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 | | 0012 | 204-02-00100 | Temporary Hay or Straw Bales | 42 | EACH | 20.00 | 840.00 | 20.00 | 840.00 | | 0013 | 302-02-06000 | Class II Base Course (12" Thick) | 1,161.9 | SQYD | 30.00 | 34,857.00 | 55.00 | 63,904.50 | | 0014 | 701-10-01020 | Reinforced Concrete Pipe (Extension) (15") Existing Cross Drain Pipe; Type 3 Joints Required | 10 | LNFT | 750.00 | 7,500.00 | 465.00 | 4,650.00 | | 0015 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") Existing Cross Drain Pipe; Type 3 Joints Required | 9 | LNFT | 750.00 | 6,750.00 | 530.00 | 4,770.00 | | 0016 | 701-15-00100 | Concrete Collar | 2 | EACH | 1,500.00 | 3,000.00 | 1,400.00 | 2,800.00 | | 0017 | 702-03-00500 | Catch Basins (CB-06) | 3 | EACH | 4,000.00 | 12,000.00 | 6,900.00 | 20,700.00 | | 0018 | 706-04-00100 | Handicapped Curb Ramps | 6 | EACH | 1,500.00 | 9,000.00 | 1,210.00 | 7,260.00 | | 0019 | 707-03-00100 | Combination Concrete Curb and Gutter | 1,374.7 | LNFT | 30.00 | 41,241.00 | 26.00 | 35,742.20 | | 0020 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 70,000.00 | 70,000.00 | | 0021 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.25 | MILE | 300.00 | 75.00 | 10.00 | 2.50 | | 0022 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.5 | MILE | 750.00 | 375.00 | 10.00 | 5.00 | | 0023 | 716-01-00100 | Mulch (Vegetative) | 1 | TON | 750.00 | 750.00 | 2,085.00 | 2,085.00 | | 0024 | 717-01-00100 | Seeding Hulled Bermuda | 6 | LB | 20.00 | 120.00 | 33.00 | 198.00 | | 0025 | 718-01-00100 | Fertilizer | 200 | LB | 2.00 | 400.00 | 1.00 | 200.00 | | 0026 | 726-01-00100 | Bedding Material | 3 | CUYD | 100.00 | 300.00 | 175.00 | 525.00 | | 0027 | 727-01-00100 | Mobilization | 1 | LUMP | 60,000.00 | 60,000.00 | 78,000.00 | 78,000.00 | | 0028 | 729-01-00100 | Sign (Type A) | 78 | SQFT | 40.00 | 3,120.00 | 55.00 | 4,290.00 | | 0029 | 729-21-00100 | U-Channel Post | 4 | EACH | 150.00 | 600.00 | 275.00 | 1,100.00 | | 0030 | 730-01-00100 | Trenching and Backfilling | 543 | LNFT | 5.00 | 2,715.00 | 7.00 | 3,801.00 | | 0031 | 730-02-01140 | Conduit with Conductors (PVC/HDPE) (3") (HDPE)(3c,#2 AWG) | 543 | LNFT | 15.00 | 8,145.00 | 9.00 | 4,887.00 | | 0032 | 730-04-00100 | Jacked or Bored Casing (4" Diameter) (PVC/HDPE) (HDPE) | 228 | LNFT | 50.00 | 11,400.00 | 37.00 | 8,436.00 | | 0033 | 730-08-00200 | Electrical Service Point (Structure) | 1 | EACH | 15,000.00 | 15,000.00 | 11,500.00 | 11,500.00 | | 0034 | 730-13-00100 | Removal and Disposal of Light Pole Foundation | 3 | EACH | 750.00 | 2,250.00 | 489.00 | 1,467.00 | | 0035 | 730-15-01000 | Relocate Light Poles 25' Alum.Twin Arm | 3 | EACH | 2,500.00 | 7,500.00 | 3,428.00 | 10,284.00 | | 0036 | 730-16-00300 | Underground Junction Box (13" x 24") | 4 | EACH | 1,000.00 | 4,000.00 | 889.00 | 3,556.00 | | 0037 | 730-20-00020 | Disconnect (Service) denergized | 2 | EACH | 1,000.00 | 2,000.00 | 4,000.00 | 8,000.00 | | 0038 | 730-22-00220 | Underground Marker Tape (3")(Detectable) Conduit Location Markings | 543 | LNFT | 1.00 | 543.00 | 1.00 | 543.00 | | 0039 | 731-02-00100 | Reflectorized Raised Pavement Markers | 56 | EACH | 15.00 | 840.00 | 8.00 | 448.00 | | 0040 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 208 | LNFT | 10.00 | 2,080.00 | 10.00 | 2,080.00 | | 0041 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.6 | MILE | 5,000.00 | 3,000.00 | 4,000.00 | 2,400.00 | | 0042 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.118 | MILE | 12,000.00 | 1,416.00 | 10,000.00 | 1,180.00 | | 0043 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.252 | MILE | 3,000.00 | 756.00 | 1,500.00 | 378.00 | | 0044 | 732-03-02010 | Plastic Pvmt Strip (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.029 | MILE | 13,000.00 | 377.00 | 2,000.00 | 58.00 | | 0045 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 500.00 | 1,000.00 | 245.00 | 490.00 | | 0046 | 736-01-00100 | Trenching and Backfilling | 45 | LNFT | 7.00 | 315.00 | 7.00 | 315.00 | | 0047 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 228 | LNFT | 40.00 | 9,120.00 | 30.00 | 6,840.00 | | 0048 | 736-04-05006 | Signal Support (40'span, 25' span add-on arm) | 1 | EACH | 20,000.00 | 20,000.00 | 20,020.00 | 20,020.00 | | 0049 | 736-04-05009 | Signal Support (45'span, 25' span add-on arm) | 1 | EACH | 20,000.00 | 20,000.00 | 20,036.00 | 20,036.00 | | 0050 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 6 | EACH | 1,200.00 | 7,200.00 | 1,185.00 | 7,110.00 | | 0051 | 736-05-02070 | Signal Hds (3 Sec, 12" Led Lens, LT. R, LT. Y, LT. G) | 2 | EACH | 1,200.00 | 2,400.00 | 866.00 | 1,732.00 | | 0052 | 736-05-03000 | Signal Heads (4 Section, 12" Led Lens, R, Y, LT. G, G) | 2 | EACH | 1,500.00 | 3,000.00 | 1,618.00 | 3,236.00 | | 0053 | 736-06-00100 | Signal Service | 1 | EACH | 1,000.00 | 1,000.00 | 2,710.00 | 2,710.00 | | 0054 | 736-06-00200 | Signal Service (Pedestal Required) | 1 | EACH | 3,000.00 | 3,000.00 | 2,920.00 | 2,920.00 | | 0055 | 736-08-00102 | Signal Controller (980 ATC, Type 2)(Furnish & Install) | 1 | EACH | 7,000.00 | 7,000.00 | 6,960.00 | 6,960.00 | | 0056 | 736-10-00300 | Underground Junction Box (Type F) | 3 | EACH | 1,000.00 | 3,000.00 | 825.00 | 2,475.00 | | 0057 | 736-10-00400 | Underground Junction Box (Type G) | 1 | EACH | 1,500.00 | 1,500.00 | 1,158.00 | 1,158.00 | | 0058 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 10 | LNFT | 25.00 | 250.00 | 23.00 | 230.00 | | 0059 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 35 | LNFT | 15.00 | 525.00 | 14.00 | 490.00 | | 0060 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 90 | LNFT | 10.00 | 900.00 | 5.00 | 450.00 | | 0061 | 736-12-04000 | Conductor (6c, #14 awg) | 275 | LNFT | 5.00 | 1,375.00 | 4.00 | 1,100.00 | | 0062 | 736-12-06000 | Conductor (10c, #14 awg) | 590 | LNFT | 5.00 | 2,950.00 | 4.00 | 2,360.00 | | 0063 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 25,000.00 | 25,000.00 | | 0064 | 805-02-00100 | Class A(M) Concrete | 4 | CUYD | 2,000.00 | 8,000.00 | 2,500.00 | 10,000.00 | | 0065 | 806-01-00100 | Deformed Reinforcing Steel | 200 | LB | 2.00 | 400.00 | 12.00 | 2,400.00 | | 0066 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement 8" Thick | 5,608 | INLF | 1.00 | 5,608.00 | 0.55 | 3,084.40 | | 0067 | NS-502-01000 | Asphalt Concrete | 1,138.9 | TON | 115.00 | 130,973.50 | 127.00 | 144,640.30 | | 0068 | NS-509-01000 | Milling Asphalt Pavement | 5,501 | SQYD | 2.00 | 11,002.00 | 5.00 | 27,505.00 | | 0069 | NS-509-02000 | Contractor Retained Reclaimed Asphalt Pavement | -78 | CUYD | 1.00 | -78.00 | 0.01 | -0.78 | | 0070 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement 12" Thick | 288 | INLF | 2.00 | 576.00 | 0.70 | 201.60 | | 0071 | NS-736-00001 | GPS | 1 | EACH | 1,000.00 | 1,000.00 | 1,144.00 | 1,144.00 | | 0072 | NS-736-00005 | Video Detection Cabinet Components | 1 | EACH | 5,000.00 | 5,000.00 | 9,514.00 | 9,514.00 | | 0073 | NS-736-00006 | Video Detection Camera | 4 | EACH | 4,000.00 | 16,000.00 | 2,157.00 | 8,628.00 | | 0074 | NS-736-00131 | TS-2 Traffic Signal Cabinet (Pole Mounted) | 1 | EACH | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 598,512.50 | | 801,105.72 |
|