Bid Tabulations for the Letting of 7/11/2018 LA DOTD Headquarters

Proposal:H.972286.1
Parish:St. Tammany
Description:ABITA SPRINGS YARD RENOVATIONS
Type Construction:GRADING, DRAINAGE STRUCTURES, BUILDING RENOVATIONS, BUILDING ADDITIONS, MECHANICAL SYSTEM, ELECTRICAL SYSTEM
Estimated Construction Cost:$842,842.79
Rank License BidderConstruction Bid
103614W.H. WARD, LLC$868,191.89
232044Quality Design & Construction, LLC$902,801.01
330088Barbara Enterprises, Inc$915,722.43


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
W.H. WARD, LLC
- 2 -
Quality Design & Construction, LLC
- 3 -
Barbara Enterprises, Inc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001TS-821-00101Building Plumbing 1     LUMP62,900.0062,900.0074,700.0074,700.0079,483.0079,483.00
0002TS-821-00102HDPE Pipe (3")73.75  LNFT52.183,848.2840.002,950.0049.003,613.75
0003TS-821-00102HDPE Pipe (4" W/ Innerducts)524     LNFT37.5419,670.9612.006,288.0058.0030,392.00
0004TS-821-00102HDPE Pipe (6")409.83  LNFT62.3025,532.4147.9019,630.8653.0021,720.99
0005TS-821-00103PVC Pipe (4")101.17  LNFT34.883,528.8120.002,023.4032.003,237.44
0006TS-821-00103PVC Pipe (6")214.25  LNFT31.446,736.0229.006,213.2531.006,641.75
0007TS-821-00103PVC Pipe (8")461.75  LNFT50.2923,221.4154.0024,934.5060.0027,705.00
0008TS-821-00108Fire Hydrant 1     EACH7,434.007,434.004,191.004,191.005,312.505,312.50
0009TS-821-00109Precast Sanitary Sewer Manhole 2     EACH6,250.0012,500.003,910.007,820.004,775.009,550.00
0010TS-821-00201Building Heating, Ventilating, and Air Conditioning 1     LUMP60,500.0060,500.0063,700.0063,700.0076,066.4076,066.40
0011TS-821-02140Building (Renovation and Addition) .1     LUMP510,320.00510,320.00538,690.00538,690.00514,761.10514,761.10
0012TS-822-00002Building Electrical 1     LUMP132,000.00132,000.00151,660.00151,660.00137,238.50137,238.50
           
  CONTRACTOR TOTAL   868,191.89 902,801.01 915,722.43