Proposal:H.012196.6
Parish:Natchitoches
Routes:I-49
Description:I-49: CABLE BARRIERS NATCHITOCHES
Type Construction:GRADING, DRILLED SHAFT FOUNDATIONS, HIGH TENSION CABLE BARRIER, AND RELATED WORK.
Estimated Construction Cost:$5,608,584.10
| Rank | License | Bidder | Construction Bid |
| 1 | 30774 | Progressive Construction Co., LLC | $5,700,646.52 |
| 2 | 43371 | Rmd Holdings Ltd. | $5,969,420.89 |
| 3 | 39462 | JB JAMES CONSTRUCTION LLC | $6,209,697.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Progressive Construction Co., LLC | - 2 - Rmd Holdings Ltd. | - 3 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 230,000.00 | 230,000.00 | 354,163.88 | 354,163.88 | 500,000.00 | 500,000.00 | | 0002 | 204-02-00100 | Temporary Hay Bales | 798 | EACH | 14.00 | 11,172.00 | 12.92 | 10,310.16 | 10.00 | 7,980.00 | | 0003 | 204-06-00100 | Temporary Silt Fencing | 1,196 | LNFT | 2.25 | 2,691.00 | 4.16 | 4,975.36 | 2.50 | 2,990.00 | | 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 171.4 | CUYD | 90.00 | 15,426.00 | 280.90 | 48,146.26 | 100.00 | 17,140.00 | | 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 107,000.00 | 107,000.00 | 243,597.17 | 243,597.17 | 250,000.00 | 250,000.00 | | 0006 | 713-11-00100 | Portable Changeable Message Signs | 4 | EACH | 10,500.00 | 42,000.00 | 1,011.24 | 4,044.96 | 20,000.00 | 80,000.00 | | 0007 | 716-01-00100 | Mulch (Vegetative) | 69 | TON | 5.25 | 362.25 | 1,235.96 | 85,281.24 | 700.00 | 48,300.00 | | 0008 | 717-01-00100 | Seeding | 1,840 | LB | 16.00 | 29,440.00 | 21.35 | 39,284.00 | 12.00 | 22,080.00 | | 0009 | 718-01-00100 | Fertilizer | 4,600 | LB | 0.60 | 2,760.00 | 1.69 | 7,774.00 | 0.45 | 2,070.00 | | 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 570,000.00 | 570,000.00 | 463,138.00 | 463,138.00 | 550,000.00 | 550,000.00 | | 0011 | 740-01-00100 | Construction Layout | 1 | LUMP | 106,000.00 | 106,000.00 | 47,752.81 | 47,752.81 | 80,000.00 | 80,000.00 | | 0012 | NS-704-00001 | High Tension Cable Barrier | 178,547 | LNFT | 7.00 | 1,249,829.00 | 7.27 | 1,298,036.69 | 7.00 | 1,249,829.00 | | 0013 | NS-704-00002 | Cable Barrier Gated End Terminal | 64 | EACH | 2,355.00 | 150,720.00 | 2,509.66 | 160,618.24 | 3,500.00 | 224,000.00 | | 0014 | NS-704-00003 | Concrete Strip | 79,382.7 | SQYD | 40.10 | 3,183,246.27 | 40.34 | 3,202,298.12 | 40.00 | 3,175,308.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 5,700,646.52 | | 5,969,420.89 | | 6,209,697.00 |
|