Proposal:H.013244.6
Parish:Lafourche
Routes:LA 316
Description:BAYOU BLUE PONTOON BR ELEC WINCHES
Type Construction:REPLACEMENT OF PONTOON BRIDGE WINCH SYSTEM AND RELATED WORK.
Estimated Construction Cost:$456,425.00
| Rank | License | Bidder | Construction Bid |
| 1 | 33678 | Sealevel Construction Inc. | $374,800.00 |
| 2 | 32044 | Quality Design & Construction, LLC | $460,450.00 |
| 3 | 26435 | C.E.C., Inc. | $597,450.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Sealevel Construction Inc. | - 2 - Quality Design & Construction, LLC | - 3 - C.E.C., Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 44,250.00 | 44,250.00 | 34,500.00 | 34,500.00 | | 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 19,800.00 | 19,800.00 | 42,200.00 | 42,200.00 | 50,000.00 | 50,000.00 | | 0003 | 821-04-00900 | Pontoon Span Bridge Mechanical System (Removal/Disposal) | 1 | LUMP | 20,000.00 | 20,000.00 | 11,200.00 | 11,200.00 | 19,200.00 | 19,200.00 | | 0004 | 821-04-01100 | Pontoon Span Bridge Mechanical System (Backup Electric Capstan) | 1 | LUMP | 30,000.00 | 30,000.00 | 17,200.00 | 17,200.00 | 36,250.00 | 36,250.00 | | 0005 | 821-04-01100 | Pontoon Span Bridge Mechanical System (Vector Drive Electric Winch System) | 1 | LUMP | 213,000.00 | 213,000.00 | 172,600.00 | 172,600.00 | 321,500.00 | 321,500.00 | | 0006 | 822-09-00100 | Electrical System (Backup Electric Capstan) | 1 | LUMP | 1,000.00 | 1,000.00 | 6,800.00 | 6,800.00 | 6,000.00 | 6,000.00 | | 0007 | 822-09-00100 | Electrical System (Vector Drive Electric Winch System) | 1 | LUMP | 81,000.00 | 81,000.00 | 166,200.00 | 166,200.00 | 130,000.00 | 130,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 374,800.00 | | 460,450.00 | | 597,450.00 |
|