Proposal:H.011138.6
Parish:St. Tammany
Description:COVINGTON SIDEWALKS & OTHER SAFETY IMPR
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, CONCRETE WALK, AND RELATED WORK.
Estimated Construction Cost:$382,923.00
| Rank | License | Bidder | Construction Bid |
| 1 | 12198 | Byron E. Talbot Contractor, Inc. | $225,062.75 |
| 2 | 48896 | Command Construction Industries LLC | $277,024.76 |
| 3 | 49356 | KORT's CONSTRUCTION SERVICES, INC. | $277,263.60 |
| 4 | 16378 | Mcdonald Const. Inc. of Slidell | $299,901.90 |
| 5 | 38466 | Gulf States Contractors LLC | $312,103.10 |
| 6 | 50425 | K-Belle Consultants, LLC | $329,633.49 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Byron E. Talbot Contractor, Inc. | - 2 - Command Construction Industries LLC | - 3 - KORT's CONSTRUCTION SERVICES, INC. | - 4 - Mcdonald Const. Inc. of Slidell | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,500.00 | 10,500.00 | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 5,500.00 | 5,500.00 | | 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 190 | SQYD | 23.00 | 4,370.00 | 5.00 | 950.00 | 15.00 | 2,850.00 | 12.00 | 2,280.00 | | 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 18 | LNFT | 4.50 | 81.00 | 5.00 | 90.00 | 5.00 | 90.00 | 40.00 | 720.00 | | 0004 | 202-02-12020 | Removal of Fence (Chain Link) | 240 | LNFT | 6.00 | 1,440.00 | 5.00 | 1,200.00 | 6.00 | 1,440.00 | 5.00 | 1,200.00 | | 0005 | 202-02-32120 | Removal of Pipe (Side Drain) 12" RCP | 41 | LNFT | 13.50 | 553.50 | 15.00 | 615.00 | 5.00 | 205.00 | 12.00 | 492.00 | | 0006 | 202-02-38240 | Removal of Signs and Supports | 1 | EACH | 65.00 | 65.00 | 30.00 | 30.00 | 65.00 | 65.00 | 50.00 | 50.00 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 3,000.00 | 3,000.00 | 10,000.00 | 10,000.00 | 30,000.00 | 30,000.00 | 4,800.00 | 4,800.00 | | 0008 | 204-02-00100 | Temporary Hay Bales | 136 | EACH | 15.00 | 2,040.00 | 1.00 | 136.00 | 12.75 | 1,734.00 | 14.00 | 1,904.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 4,526 | LNFT | 2.00 | 9,052.00 | 0.01 | 45.26 | 1.75 | 7,920.50 | 2.00 | 9,052.00 | | 0010 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 473 | LNFT | 36.00 | 17,028.00 | 80.00 | 37,840.00 | 48.00 | 22,704.00 | 60.00 | 28,380.00 | | 0011 | 701-05-01020 | Side Drain Pipe (15" RCP/PP/CMP) | 41 | LNFT | 38.00 | 1,558.00 | 80.00 | 3,280.00 | 48.00 | 1,968.00 | 82.00 | 3,362.00 | | 0012 | 701-10-01020 | Reinforced Concrete Pipe (Extension) (15") | 64 | LNFT | 40.00 | 2,560.00 | 100.00 | 6,400.00 | 48.00 | 3,072.00 | 60.00 | 3,840.00 | | 0013 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 8 | LNFT | 44.00 | 352.00 | 105.00 | 840.00 | 50.00 | 400.00 | 98.00 | 784.00 | | 0014 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 32 | LNFT | 55.00 | 1,760.00 | 110.00 | 3,520.00 | 55.00 | 1,760.00 | 110.00 | 3,520.00 | | 0015 | 701-15-00100 | Concrete Collar | 2 | EACH | 750.00 | 1,500.00 | 1,000.00 | 2,000.00 | 1,500.00 | 3,000.00 | 800.00 | 1,600.00 | | 0016 | 702-02-00100 | Manholes (MH-06) | 3 | EACH | 2,400.00 | 7,200.00 | 3,500.00 | 10,500.00 | 3,000.00 | 9,000.00 | 4,200.00 | 12,600.00 | | 0017 | 702-03-00100 | Catch Basins (CB-01) | 11 | EACH | 2,250.00 | 24,750.00 | 2,500.00 | 27,500.00 | 2,200.00 | 24,200.00 | 2,000.00 | 22,000.00 | | 0019 | 702-04-00200 | Adjusting Catch Basins | 3 | EACH | 1,200.00 | 3,600.00 | 500.00 | 1,500.00 | 1,000.00 | 3,000.00 | 1,800.00 | 5,400.00 | | 0020 | 705-06-00200 | Chain Link Fence (5-Foot Height) | 225 | LNFT | 40.00 | 9,000.00 | 20.00 | 4,500.00 | 37.00 | 8,325.00 | 28.00 | 6,300.00 | | 0021 | 706-01-00100 | Concrete Walk (4" Thick) | 1,301.3 | SQYD | 41.00 | 53,353.30 | 55.00 | 71,571.50 | 49.00 | 63,763.70 | 62.00 | 80,680.60 | | 0022 | 706-02-00200 | Concrete Drive (6" Thick) | 151.1 | SQYD | 47.00 | 7,101.70 | 55.00 | 8,310.50 | 59.00 | 8,914.90 | 68.00 | 10,274.80 | | 0023 | 706-04-00100 | Handicapped Curb Ramps | 19 | EACH | 500.00 | 9,500.00 | 1,000.00 | 19,000.00 | 1,000.00 | 19,000.00 | 1,500.00 | 28,500.00 | | 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,500.00 | 6,500.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | | 0025 | 714-01-00600 | Slab Sodding (St. Augustine) | 1,033 | SQYD | 8.80 | 9,090.40 | 8.00 | 8,264.00 | 8.50 | 8,780.50 | 12.00 | 12,396.00 | | 0026 | 726-01-00100 | Bedding Material | 51.7 | CUYD | 148.00 | 7,651.60 | 50.00 | 2,585.00 | 30.00 | 1,551.00 | 70.00 | 3,619.00 | | 0027 | 727-01-00100 | Mobilization | 1 | LUMP | 7,500.00 | 7,500.00 | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | 10,500.00 | 10,500.00 | | 0028 | 729-01-00100 | Sign (Type A) | 1.5 | SQFT | 27.50 | 41.25 | 35.00 | 52.50 | 26.00 | 39.00 | 45.00 | 67.50 | | 0029 | 729-01-00103 | Sign (Type A)(Relocate) | 24 | SQFT | 33.00 | 792.00 | 25.00 | 600.00 | 31.00 | 744.00 | 20.00 | 480.00 | | 0030 | 729-21-00100 | U-Channel Post | 1 | EACH | 137.50 | 137.50 | 100.00 | 100.00 | 130.00 | 130.00 | 150.00 | 150.00 | | 0031 | 735-01-00100 | Mailboxes | 17 | EACH | 5.50 | 93.50 | 35.00 | 595.00 | 6.00 | 102.00 | 160.00 | 2,720.00 | | 0032 | 735-02-00100 | Mailbox Supports (Single) | 17 | EACH | 176.00 | 2,992.00 | 100.00 | 1,700.00 | 165.00 | 2,805.00 | 90.00 | 1,530.00 | | 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,000.00 | 4,000.00 | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 | 6,500.00 | 6,500.00 | | 0034 | 741-11-00100 | Adjusting Water Valve | 2 | EACH | 200.00 | 400.00 | 300.00 | 600.00 | 375.00 | 750.00 | 200.00 | 400.00 | | 0035 | 741-11-00200 | Adjusting Water Valve and Meter Box | 2 | EACH | 2,000.00 | 4,000.00 | 350.00 | 700.00 | 375.00 | 750.00 | 150.00 | 300.00 | | 0036 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 12 | EACH | 800.00 | 9,600.00 | 750.00 | 9,000.00 | 650.00 | 7,800.00 | 1,500.00 | 18,000.00 | | 0037 | NS-MSC-00120 | Drainage Structure Grate Replacement | 2 | EACH | 950.00 | 1,900.00 | 1,500.00 | 3,000.00 | 700.00 | 1,400.00 | 2,500.00 | 5,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 225,062.75 | | 277,024.76 | | 277,263.60 | | 299,901.90 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Gulf States Contractors LLC | - 6 - K-Belle Consultants, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 8,454.00 | 8,454.00 | | 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 190 | SQYD | 30.00 | 5,700.00 | 14.70 | 2,793.00 | | 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 18 | LNFT | 25.00 | 450.00 | 15.80 | 284.40 | | 0004 | 202-02-12020 | Removal of Fence (Chain Link) | 240 | LNFT | 3.00 | 720.00 | 5.54 | 1,329.60 | | 0005 | 202-02-32120 | Removal of Pipe (Side Drain) 12" RCP | 41 | LNFT | 18.00 | 738.00 | 20.31 | 832.71 | | 0006 | 202-02-38240 | Removal of Signs and Supports | 1 | EACH | 100.00 | 100.00 | 99.60 | 99.60 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 15,000.00 | 15,000.00 | 8,529.00 | 8,529.00 | | 0008 | 204-02-00100 | Temporary Hay Bales | 136 | EACH | 15.00 | 2,040.00 | 22.97 | 3,123.92 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 4,526 | LNFT | 0.10 | 452.60 | 3.32 | 15,026.32 | | 0010 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 473 | LNFT | 85.00 | 40,205.00 | 63.54 | 30,054.42 | | 0011 | 701-05-01020 | Side Drain Pipe (15" RCP/PP/CMP) | 41 | LNFT | 85.00 | 3,485.00 | 62.76 | 2,573.16 | | 0012 | 701-10-01020 | Reinforced Concrete Pipe (Extension) (15") | 64 | LNFT | 100.00 | 6,400.00 | 66.62 | 4,263.68 | | 0013 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 8 | LNFT | 110.00 | 880.00 | 73.98 | 591.84 | | 0014 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 32 | LNFT | 125.00 | 4,000.00 | 87.44 | 2,798.08 | | 0015 | 701-15-00100 | Concrete Collar | 2 | EACH | 1,350.00 | 2,700.00 | 979.99 | 1,959.98 | | 0016 | 702-02-00100 | Manholes (MH-06) | 3 | EACH | 3,300.00 | 9,900.00 | 2,785.79 | 8,357.37 | | 0017 | 702-03-00100 | Catch Basins (CB-01) | 11 | EACH | 3,300.00 | 36,300.00 | 2,569.86 | 28,268.46 | | 0019 | 702-04-00200 | Adjusting Catch Basins | 3 | EACH | 2,000.00 | 6,000.00 | 922.73 | 2,768.19 | | 0020 | 705-06-00200 | Chain Link Fence (5-Foot Height) | 225 | LNFT | 15.00 | 3,375.00 | 33.60 | 7,560.00 | | 0021 | 706-01-00100 | Concrete Walk (4" Thick) | 1,301.3 | SQYD | 57.00 | 74,174.10 | 65.01 | 84,597.51 | | 0022 | 706-02-00200 | Concrete Drive (6" Thick) | 151.1 | SQYD | 72.00 | 10,879.20 | 75.00 | 11,332.50 | | 0023 | 706-04-00100 | Handicapped Curb Ramps | 19 | EACH | 1,200.00 | 22,800.00 | 1,200.00 | 22,800.00 | | 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 10,665.75 | 10,665.75 | | 0025 | 714-01-00600 | Slab Sodding (St. Augustine) | 1,033 | SQYD | 5.00 | 5,165.00 | 19.62 | 20,267.46 | | 0026 | 726-01-00100 | Bedding Material | 51.7 | CUYD | 1.00 | 51.70 | 71.80 | 3,712.06 | | 0027 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 | 11,533.64 | 11,533.64 | | 0028 | 729-01-00100 | Sign (Type A) | 1.5 | SQFT | 25.00 | 37.50 | 30.00 | 45.00 | | 0029 | 729-01-00103 | Sign (Type A)(Relocate) | 24 | SQFT | 30.00 | 720.00 | 36.00 | 864.00 | | 0030 | 729-21-00100 | U-Channel Post | 1 | EACH | 125.00 | 125.00 | 150.00 | 150.00 | | 0031 | 735-01-00100 | Mailboxes | 17 | EACH | 5.00 | 85.00 | 11.72 | 199.24 | | 0032 | 735-02-00100 | Mailbox Supports (Single) | 17 | EACH | 160.00 | 2,720.00 | 192.00 | 3,264.00 | | 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 | 20,280.00 | 20,280.00 | | 0034 | 741-11-00100 | Adjusting Water Valve | 2 | EACH | 250.00 | 500.00 | 343.28 | 686.56 | | 0035 | 741-11-00200 | Adjusting Water Valve and Meter Box | 2 | EACH | 250.00 | 500.00 | 442.88 | 885.76 | | 0036 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 12 | EACH | 1,000.00 | 12,000.00 | 581.00 | 6,972.00 | | 0037 | NS-MSC-00120 | Drainage Structure Grate Replacement | 2 | EACH | 700.00 | 1,400.00 | 855.14 | 1,710.28 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 312,103.10 | | 329,633.49 |
|