Proposal:H.010916.6-R1
Parish:Calcasieu
Routes:I-210
Description:PRIEN LAKE RE-DECK & SAFETY IMPROVEMENTS
Type Construction:CLEARING AND GRUBBING, GRADING, REMOVAL OF BRIDGE DECK (FULL DEPTH), MILLING ASPHALT PAVEMENT, SUBGRADE TREATMENT, ASPHALT CONCRETE PAVEMENT, DRILLED SHAFT FOUNDATIONS, ROADWAY LIGHTING, METAL WORK, BRIDGE REPAIRS, INTELLIGENT TRANSPORTATION SYSTEM, TEMPORARY QUEUE DETECTION SYSTEM, AND RELATED WORK.
Estimated Construction Cost:$37,201,640.47
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$25,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 47347 | Kiewit Louisiana Co. | $35,374,000.00 | 365.00 | $44,499,000.00 |
| 2 | 26435 | C.E.C., Inc. | $35,785,983.15 | 450.00 | $47,035,983.15 |
| 3 | 39462 | JB JAMES CONSTRUCTION LLC | $36,309,519.80 | 660.00 | $52,809,519.80 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Kiewit Louisiana Co. | - 2 - C.E.C., Inc. | - 3 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 100,000.00 | 100,000.00 | 6,600.00 | 6,600.00 | 600,000.00 | 600,000.00 | | 0002 | 202-02-00010 | Removal of Impact Attenuator | 1 | EACH | 5,025.46 | 5,025.46 | 2,500.00 | 2,500.00 | 3,000.00 | 3,000.00 | | 0003 | 202-02-00010 | Removal of Temporary Precast Concrete Barrier | 67 | EACH | 225.01 | 15,075.67 | 600.00 | 40,200.00 | 90.00 | 6,030.00 | | 0004 | 202-02-00020 | Removal of Incidental Asphalt Concrete | 208.9 | SQYD | 30.92 | 6,459.19 | 3.00 | 626.70 | 16.00 | 3,342.40 | | 0005 | 202-02-04505 | Removal of Bridge Deck (Full Depth) Deck | 56,188 | SQFT | 18.98 | 1,066,448.24 | 17.00 | 955,196.00 | 7.00 | 393,316.00 | | 0006 | 202-02-04520 | Removal of Bridge Component (Aluminum Railing) | 15,146 | LNFT | 6.98 | 105,719.08 | 10.00 | 151,460.00 | 15.00 | 227,190.00 | | 0007 | 202-02-04520 | Removal of Bridge Component Barrier Rail | 2,790 | LNFT | 105.00 | 292,950.00 | 150.00 | 418,500.00 | 75.00 | 209,250.00 | | 0008 | 202-02-04520 | Removal of Bridge Component Bolster Block | 124 | LNFT | 19.95 | 2,473.80 | 500.00 | 62,000.00 | 100.00 | 12,400.00 | | 0009 | 202-02-04520 | Removal of Bridge Component End Bent Wingwalls & Backwalls | 208 | LNFT | 62.25 | 12,948.00 | 500.00 | 104,000.00 | 140.00 | 29,120.00 | | 0010 | 202-02-04540 | Removal of Bridge Component Hatch | 22 | EACH | 1,398.57 | 30,768.54 | 1,300.00 | 28,600.00 | 650.00 | 14,300.00 | | 0011 | 202-02-06000 | Removal of Concrete Approach Slabs | 275.6 | SQYD | 135.01 | 37,208.76 | 350.00 | 96,460.00 | 100.00 | 27,560.00 | | 0012 | 202-02-06101 | Removal of Concrete Median Barrier and Footing | 53 | SQYD | 88.57 | 4,694.21 | 645.00 | 34,185.00 | 290.00 | 15,370.00 | | 0013 | 202-02-14500 | Removal of Guard Rail | 359 | LNFT | 8.36 | 3,001.24 | 10.00 | 3,590.00 | 8.00 | 2,872.00 | | 0014 | 202-02-38240 | Removal of Signs and Supports | 16 | EACH | 874.10 | 13,985.60 | 90.00 | 1,440.00 | 75.00 | 1,200.00 | | 0015 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 1,639 | SQYD | 16.30 | 26,715.70 | 30.00 | 49,170.00 | 20.00 | 32,780.00 | | 0016 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 450,000.00 | 450,000.00 | 150,000.00 | 150,000.00 | 200,000.00 | 200,000.00 | | 0017 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 780.91 | 3,123.64 | 180.00 | 720.00 | 150.00 | 600.00 | | 0018 | 204-06-00100 | Temporary Silt Fencing | 1,098 | LNFT | 2.84 | 3,118.32 | 4.00 | 4,392.00 | 4.00 | 4,392.00 | | 0019 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 891 | SQYD | 118.75 | 105,806.25 | 110.00 | 98,010.00 | 70.00 | 62,370.00 | | 0020 | 502-01-00100 | Asphalt Concrete | 707.2 | TON | 162.00 | 114,566.40 | 145.00 | 102,544.00 | 120.00 | 84,864.00 | | 0021 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 66 | TON | 215.00 | 14,190.00 | 290.00 | 19,140.00 | 240.00 | 15,840.00 | | 0022 | 502-04-00100 | Asphalt Concrete (SMA) Wearing Course | 1,365.7 | TON | 215.00 | 293,625.50 | 188.00 | 256,751.60 | 156.00 | 213,049.20 | | 0023 | 509-01-00100 | Milling Asphalt Pavement | 12,337 | SQYD | 5.00 | 61,685.00 | 4.00 | 49,348.00 | 3.00 | 37,011.00 | | 0024 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -514 | CUYD | 0.01 | -5.14 | 1.00 | -514.00 | 0.20 | -102.80 | | 0025 | 702-04-00200 | Adjusting Catch Basins | 2 | EACH | 2,210.64 | 4,421.28 | 2,500.00 | 5,000.00 | 5,000.00 | 10,000.00 | | 0026 | 704-03-00200 | Blocked Out Guard Rail – 31”, (6’-3” Post Spacing) | 228.1 | LNFT | 32.68 | 7,454.31 | 36.00 | 8,211.60 | 30.00 | 6,843.00 | | 0027 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 25 | LNFT | 98.05 | 2,451.25 | 108.00 | 2,700.00 | 90.00 | 2,250.00 | | 0028 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 1 | EACH | 3,268.40 | 3,268.40 | 3,600.00 | 3,600.00 | 3,000.00 | 3,000.00 | | 0029 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 45.53 | SQYD | 148.20 | 6,747.55 | 375.00 | 17,073.75 | 150.00 | 6,829.50 | | 0030 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 750,000.00 | 750,000.00 | 460,000.00 | 460,000.00 | 1,000,000.00 | 1,000,000.00 | | 0031 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 1,515 | LNFT | 0.71 | 1,075.65 | 1.00 | 1,515.00 | 0.25 | 378.75 | | 0032 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 8,022 | LNFT | 1.09 | 8,743.98 | 1.20 | 9,626.40 | 0.35 | 2,807.70 | | 0033 | 713-03-01020 | Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) | 0.438 | MILE | 4,314.72 | 1,889.85 | 5,480.00 | 2,400.24 | 3,000.00 | 1,314.00 | | 0034 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 5.082 | MILE | 4,357.87 | 22,146.70 | 4,800.00 | 24,393.60 | 2,500.00 | 12,705.00 | | 0035 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 34.175 | MILE | 7,735.21 | 264,350.80 | 8,520.00 | 291,171.00 | 7,600.00 | 259,730.00 | | 0036 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 11,995 | EACH | 5.99 | 71,850.05 | 6.60 | 79,167.00 | 5.00 | 59,975.00 | | 0037 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) Length of each barrier equals 15 feet. | 1,232 | EACH | 300.00 | 369,600.00 | 1,000.00 | 1,232,000.00 | 1,000.00 | 1,232,000.00 | | 0038 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 434 | EACH | 200.00 | 86,800.00 | 890.00 | 386,260.00 | 80.00 | 34,720.00 | | 0039 | 721-01-00100 | Mowing | 27 | CYCL | 5,393.40 | 145,621.80 | 1,160.00 | 31,320.00 | 600.00 | 16,200.00 | | 0040 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 1.7 | MILE | 701.14 | 1,191.94 | 8,000.00 | 13,600.00 | 350.00 | 595.00 | | 0041 | 725-01-00100 | Temporary Detour Roads | 5,012.7 | SQYD | 194.69 | 975,922.56 | 185.00 | 927,349.50 | 130.00 | 651,651.00 | | 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 3,497,938.40 | 3,497,938.40 | 3,500,000.00 | 3,500,000.00 | 3,500,000.00 | 3,500,000.00 | | 0043 | 729-01-00100 | Sign (Type A) | 120 | SQFT | 26.97 | 3,236.40 | 40.00 | 4,800.00 | 25.00 | 3,000.00 | | 0044 | 729-16-00300 | Object Marker Assembly (Type 3) | 1 | EACH | 92.60 | 92.60 | 102.00 | 102.00 | 85.00 | 85.00 | | 0045 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 16 | EACH | 345.18 | 5,522.88 | 1,320.00 | 21,120.00 | 1,100.00 | 17,600.00 | | 0046 | 731-02-00100 | Reflectorized Raised Pavement Markers | 5,259 | EACH | 5.99 | 31,501.41 | 6.60 | 34,709.40 | 5.00 | 26,295.00 | | 0047 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 429 | LNFT | 9.26 | 3,972.54 | 10.20 | 4,375.80 | 8.00 | 3,432.00 | | 0048 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.68 | MILE | 4,248.92 | 53,876.31 | 4,680.00 | 59,342.40 | 2,800.00 | 35,504.00 | | 0049 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.307 | MILE | 16,342.00 | 5,016.99 | 18,000.00 | 5,526.00 | 5,600.00 | 1,719.20 | | 0050 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.104 | MILE | 1,797.62 | 5,579.81 | 1,980.00 | 6,145.92 | 900.00 | 2,793.60 | | 0051 | 732-03-02001 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermo 90 mil)(Blk Cont) | 3.236 | MILE | 4,139.97 | 13,396.94 | 4,560.00 | 14,756.16 | 2,700.00 | 8,737.20 | | 0052 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 1.498 | MILE | 11,984.13 | 17,952.23 | 13,200.00 | 19,773.60 | 2,800.00 | 4,194.40 | | 0053 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 1 | EACH | 653.68 | 653.68 | 720.00 | 720.00 | 1,000.00 | 1,000.00 | | 0054 | 732-05-00100 | Removal of Existing Markings | 5.007 | MILE | 9,805.20 | 49,094.64 | 10,800.00 | 54,075.60 | 7,600.00 | 38,053.20 | | 0055 | 740-01-00100 | Construction Layout | 1 | LUMP | 750,000.00 | 750,000.00 | 150,000.00 | 150,000.00 | 600,000.00 | 600,000.00 | | 0056 | 802-03-00100 | Temporary Sheeting (Steel) (PZ-22) | 600 | SQFT | 13.50 | 8,100.00 | 136.00 | 81,600.00 | 50.00 | 30,000.00 | | 0057 | 803-01-00700 | Drilled Shaft (54" Diameter) | 80 | LNFT | 1,621.45 | 129,716.00 | 1,500.00 | 120,000.00 | 1,500.00 | 120,000.00 | | 0058 | 803-08-00700 | Crosshole Sonic Log Test (54" Diameter) | 2 | EACH | 2,344.28 | 4,688.56 | 3,000.00 | 6,000.00 | 2,200.00 | 4,400.00 | | 0059 | 803-10-00700 | Permanent Casing (54" Diameter) | 80 | LNFT | 355.99 | 28,479.20 | 150.00 | 12,000.00 | 330.00 | 26,400.00 | | 0060 | 805-01-00200 | Class A1 Concrete (Deck) | 1,342.34 | CUYD | 2,700.00 | 3,624,318.00 | 2,800.00 | 3,758,552.00 | 2,000.00 | 2,684,680.00 | | 0061 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 16.41 | CUYD | 1,231.75 | 20,213.02 | 26,000.00 | 426,660.00 | 5,500.00 | 90,255.00 | | 0062 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 45,601.11 | SQFT | 4.62 | 210,677.13 | 2.90 | 132,243.22 | 3.00 | 136,803.33 | | 0063 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 320,888.64 | SQFT | 0.84 | 269,546.46 | 1.90 | 609,688.42 | 4.25 | 1,363,776.72 | | 0064 | 806-01-00100 | Deformed Reinforcing Steel | 581,704 | LB | 1.80 | 1,047,067.20 | 1.30 | 756,215.20 | 1.70 | 988,896.80 | | 0065 | 807-01-00200 | Structural Metalwork (Grade 50) | 27,156 | LUMP | 1,000,000.00 | 1,000,000.00 | 150,000.00 | 150,000.00 | 400,000.00 | 400,000.00 | | 0066 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 525 | LUMP | 300,000.00 | 300,000.00 | 200,000.00 | 200,000.00 | 10,000.00 | 10,000.00 | | 0067 | 807-03-00100 | Structural Metalwork (Access System) | 385,629 | LUMP | 4,671,000.00 | 4,671,000.00 | 2,500,000.00 | 2,500,000.00 | 3,900,000.00 | 3,900,000.00 | | 0068 | 807-04-00100 | Structural Metalwork (Shear Studs) | 2,480 | LUMP | 200,000.00 | 200,000.00 | 140,000.00 | 140,000.00 | 52,000.00 | 52,000.00 | | 0069 | 807-04-00100 | Structural Metalwork (Temporary Barrier Sliding Plates) | 7,606 | LUMP | 100,000.00 | 100,000.00 | 160,000.00 | 160,000.00 | 90,000.00 | 90,000.00 | | 0070 | 810-01-00100 | Concrete Bridge Railing (Standard) | 3,840 | LNFT | 97.31 | 373,670.40 | 130.00 | 499,200.00 | 120.00 | 460,800.00 | | 0071 | 810-01-00200 | Concrete Bridge Railing (Slotted) | 40 | LNFT | 130.79 | 5,231.60 | 500.00 | 20,000.00 | 320.00 | 12,800.00 | | 0072 | 810-02-00100 | Metal Bridge Railing | 30,292 | LNFT | 167.00 | 5,058,764.00 | 210.00 | 6,361,320.00 | 220.00 | 6,664,240.00 | | 0073 | 810-04-00100 | Hand Railing Safety Walkway | 9,300 | LNFT | 107.70 | 1,001,610.00 | 145.00 | 1,348,500.00 | 140.00 | 1,302,000.00 | | 0074 | 810-05-00300 | Concrete Roadway Barrier (Double Face ) | 744 | LNFT | 598.60 | 445,358.40 | 900.00 | 669,600.00 | 800.00 | 595,200.00 | | 0075 | 810-05-00400 | Concrete Roadway Barrier Standard | 410 | LNFT | 273.84 | 112,274.40 | 850.00 | 348,500.00 | 400.00 | 164,000.00 | | 0076 | 810-06-00100 | Concrete Pier Protection System (Vehicle) Sign Truss Protection | 60 | LNFT | 133.42 | 8,005.20 | 2,400.00 | 144,000.00 | 800.00 | 48,000.00 | | 0077 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 2,651 | SQFT | 71.88 | 190,553.88 | 125.00 | 331,375.00 | 80.00 | 212,080.00 | | 0078 | 815-02-00200 | Sealed Expansion Joint (End Dams and Preformed Silicone Seal) | 120 | LNFT | 181.21 | 21,745.20 | 390.00 | 46,800.00 | 460.00 | 55,200.00 | | 0079 | 816-01-00100 | Bridge Deck Drainage System (Collection) | 1 | LUMP | 150,000.00 | 150,000.00 | 350,000.00 | 350,000.00 | 300,000.00 | 300,000.00 | | 0080 | 822-01-00100 | Trenching and Backfilling | 6,751 | LNFT | 12.28 | 82,902.28 | 4.05 | 27,341.55 | 9.00 | 60,759.00 | | 0081 | 822-02-00200 | Conduit w Conductors (PVC/HDPE) (1") (2#6, 1#6 Bare Stranded Ground) (E) | 5,049 | LNFT | 11.53 | 58,214.97 | 5.50 | 27,769.50 | 11.00 | 55,539.00 | | 0082 | 822-02-00400 | Conduit w Conductors (PVC/HDPE) (1-1/2") (2#2, 1#2 Bare Stranded Ground) (AG) | 4,182 | LNFT | 11.93 | 49,891.26 | 9.35 | 39,101.70 | 11.00 | 46,002.00 | | 0083 | 822-02-00400 | Conduit w Conductors (PVC/HDPE) (1-1/2") (4#6, 1#6 Bare Stranded Ground) (AF) | 20 | LNFT | 10.67 | 213.40 | 11.00 | 220.00 | 10.00 | 200.00 | | 0084 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (2#2, 1#2 White Neutral, 1#2 Green Insulated Ground) (B) | 150 | LNFT | 14.17 | 2,125.50 | 12.10 | 1,815.00 | 13.00 | 1,950.00 | | 0085 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (2#6, 1#6 Bare Stranded Ground) (K) | 860 | LNFT | 9.20 | 7,912.00 | 6.99 | 6,011.40 | 9.00 | 7,740.00 | | 0086 | 822-02-01100 | Conduit w Conductors (Rigid Alum) (3/4") (1#12, 1#12 White Neutral, 1#12 Green Insulated Ground) (I) | 400 | LNFT | 22.34 | 8,936.00 | 37.40 | 14,960.00 | 21.00 | 8,400.00 | | 0087 | 822-02-01200 | Conduit w Conductors (Rigid Alum) (1") (2#6, 1#6 Green Insulated Ground) (J) | 1,860 | LNFT | 18.84 | 35,042.40 | 39.49 | 73,451.40 | 18.00 | 33,480.00 | | 0088 | 822-02-02400 | Conduit w Conductors (Rigid Galv Steel) (1-1/2") (2#2, 1#2 Green Insulated Ground) (H) | 8,340 | LNFT | 28.52 | 237,856.80 | 34.98 | 291,733.20 | 27.00 | 225,180.00 | | 0089 | 822-02-02400 | Conduit w Conductors (Rigid Galv Steel) (1-1/2") (4#6, 1#6 Green Insulated Ground) (M) | 3,610 | LNFT | 27.12 | 97,903.20 | 38.50 | 138,985.00 | 25.00 | 90,250.00 | | 0090 | 822-02-03200 | Conduit w Conductors (Liq Tight Flexible Metal) (1") (2#6, 1#6 Green Insulated Ground) (R) | 50 | LNFT | 50.44 | 2,522.00 | 27.50 | 1,375.00 | 47.00 | 2,350.00 | | 0091 | 822-02-03400 | Conduit w Conductors (Liq Tight Flexible Metal) (1-1/2") (2#2, 1#2 Green Insulated Ground) (AD) | 300 | LNFT | 79.33 | 23,799.00 | 30.80 | 9,240.00 | 74.00 | 22,200.00 | | 0092 | 822-02-03400 | Conduit w Conductors (Liq Tight Flexible Metal) (1-1/2") (4#6, 1#6 Green Insulated Ground) (AE) | 5 | LNFT | 54.65 | 273.25 | 88.00 | 440.00 | 51.00 | 255.00 | | 0093 | 822-02-04200 | Conduit w Conductors (Fiberglass) (1") (1#2 Bare Solid Ground) | 60 | LNFT | 51.84 | 3,110.40 | 46.20 | 2,772.00 | 48.00 | 2,880.00 | | 0094 | 822-02-04200 | Conduit w Conductors (Fiberglass) (1") (2#6, 1#6 Bare Stranded Ground) (F) | 60 | LNFT | 46.80 | 2,808.00 | 47.30 | 2,838.00 | 44.00 | 2,640.00 | | 0095 | 822-02-04400 | Conduit w Conductors (Fiberglass) (1-1/2") (2#2, 1#2 Bare Stranded Ground) (D) | 60 | LNFT | 55.22 | 3,313.20 | 60.50 | 3,630.00 | 52.00 | 3,120.00 | | 0096 | 822-02-04400 | Conduit w Conductors (Fiberglass) (1-1/2") (3#2) (A) | 30 | LNFT | 104.47 | 3,134.10 | 60.50 | 1,815.00 | 98.00 | 2,940.00 | | 0097 | 822-02-04400 | Conduit w Conductors (Fiberglass) (1-1/2") (4#6, 1#6 Bare Stranded Ground) (AB) | 30 | LNFT | 61.52 | 1,845.60 | 59.40 | 1,782.00 | 58.00 | 1,740.00 | | 0098 | 822-02-04500 | Conduit w Conductors (Fiberglass) (2") (2#2, 1#2 White Neutral, 1#2 Green Insulated Ground) (C) | 30 | LNFT | 119.85 | 3,595.50 | 70.40 | 2,112.00 | 112.00 | 3,360.00 | | 0099 | 822-04-00200 | Jacked or Bored Casing (6" Dia) (PVC/HDPE) | 2,500 | LNFT | 49.68 | 124,200.00 | 41.80 | 104,500.00 | 47.00 | 117,500.00 | | 0100 | 822-05-00700 | Light Pole (40') (Alum) (Single Arm) (Ground Mount) | 6 | EACH | 5,237.20 | 31,423.20 | 4,785.00 | 28,710.00 | 4,900.00 | 29,400.00 | | 0101 | 822-05-00900 | Light Pole (40') (Alum) (Twin Arm) (Ground Mount) | 9 | EACH | 5,624.59 | 50,621.31 | 5,247.00 | 47,223.00 | 5,300.00 | 47,700.00 | | 0102 | 822-05-01900 | Light Pole (50') (Alum) (Twin Arm) (Bridge Barrier Mount) | 4 | EACH | 4,754.13 | 19,016.52 | 4,543.00 | 18,172.00 | 9,700.00 | 38,800.00 | | 0103 | 822-05-01900 | Light Pole (50') (Alum) (Twin Arm) (Ground Mount) | 7 | EACH | 6,676.31 | 46,734.17 | 6,292.00 | 44,044.00 | 6,200.00 | 43,400.00 | | 0104 | 822-05-01900 | Light Pole (50') (Alum) (Twin Arm) (Median Barrier Mount) | 4 | EACH | 4,418.19 | 17,672.76 | 4,213.00 | 16,852.00 | 9,400.00 | 37,600.00 | | 0105 | 822-05-01900 | Light Pole (50') (Alum) (Twin Arm) (Median Barrier Mount) (Bridge) | 29 | EACH | 4,424.59 | 128,313.11 | 8,597.07 | 249,315.03 | 17,000.00 | 493,000.00 | | 0106 | 822-05-01900 | Light Pole (50') (Alum) (Twin Arm) (Median Barrier Mount) (Existing Foundation) | 4 | EACH | 4,417.58 | 17,670.32 | 3,740.00 | 14,960.00 | 4,100.00 | 16,400.00 | | 0107 | 822-06-00600 | High Mast Pole (120') (6 Luminaire) | 1 | EACH | 80,537.32 | 80,537.32 | 44,258.50 | 44,258.50 | 75,000.00 | 75,000.00 | | 0108 | 822-06-01000 | High Mast Pole (130') (6 Luminaire) | 1 | EACH | 85,361.18 | 85,361.18 | 44,550.00 | 44,550.00 | 80,000.00 | 80,000.00 | | 0109 | 822-07-00400 | Luminaire (70 Watt) (High Pressure Sodium) (Underpass) | 4 | EACH | 1,275.24 | 5,100.96 | 935.00 | 3,740.00 | 1,200.00 | 4,800.00 | | 0110 | 822-07-01600 | Luminaire (250 Watt) (High Pressure Sodium) (Low Mast) (Type II) | 94 | EACH | 433.48 | 40,747.12 | 544.50 | 51,183.00 | 400.00 | 37,600.00 | | 0111 | 822-07-01600 | Luminaire (250 Watt) (High Pressure Sodium) (Low Mast) (Type III) | 24 | EACH | 433.48 | 10,403.52 | 544.50 | 13,068.00 | 400.00 | 9,600.00 | | 0112 | 822-07-02500 | Luminaire (1000 Watt) (High Pressure Sodium) (Highmast) | 12 | EACH | 1,221.26 | 14,655.12 | 1,222.10 | 14,665.20 | 1,150.00 | 13,800.00 | | 0113 | 822-08-00200 | Electrical Service Point (Structure) | 3 | EACH | 20,578.23 | 61,734.69 | 16,648.50 | 49,945.50 | 20,000.00 | 60,000.00 | | 0114 | 822-09-00100 | Electrical System (Bridge Receptacles) | 1 | LUMP | 23,000.32 | 23,000.32 | 17,011.50 | 17,011.50 | 22,000.00 | 22,000.00 | | 0115 | 822-09-00100 | Electrical System (Navigation Lighting) | 1 | LUMP | 103,364.81 | 103,364.81 | 150,700.00 | 150,700.00 | 100,000.00 | 100,000.00 | | 0116 | 822-09-00100 | Electrical System (Temporary Navigation Lighting) | 1 | LUMP | 27,513.37 | 27,513.37 | 29,370.00 | 29,370.00 | 26,000.00 | 26,000.00 | | 0117 | 822-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 17,711.41 | 17,711.41 | 19,569.00 | 19,569.00 | 16,000.00 | 16,000.00 | | 0118 | 822-16-00200 | Underground Junction Box (11" x 18") (JB2) | 22 | EACH | 818.27 | 18,001.94 | 877.80 | 19,311.60 | 760.00 | 16,720.00 | | 0119 | 822-16-00200 | Underground Junction Box (11" x 18") (Median Barrier Junction Box with Bottom) (JBM) | 9 | EACH | 1,064.89 | 9,584.01 | 852.50 | 7,672.50 | 1,000.00 | 9,000.00 | | 0120 | 822-16-00300 | Underground Junction Box (13" x 24") (JB3) | 26 | EACH | 860.25 | 22,366.50 | 897.60 | 23,337.60 | 800.00 | 20,800.00 | | 0121 | 822-17-00400 | Structure Junction Box (Stainless Steel) (10" x 8" x 4") (JBS) | 32 | EACH | 697.83 | 22,330.56 | 954.80 | 30,553.60 | 650.00 | 20,800.00 | | 0122 | 822-17-00400 | Structure Junction Box (Stainless Steel) (12" x 12" x 24") (JBS3) | 87 | EACH | 2,506.78 | 218,089.86 | 1,501.50 | 130,630.50 | 2,300.00 | 200,100.00 | | 0123 | 822-17-00400 | Structure Junction Box (Stainless Steel) (30" x 30" x 12") (Divider Inside the Box at 8") (JBSI) | 8 | EACH | 4,575.15 | 36,601.20 | 5,384.50 | 43,076.00 | 4,300.00 | 34,400.00 | | 0124 | 822-18-00100 | Service Pole | 3 | EACH | 2,683.30 | 8,049.90 | 1,069.20 | 3,207.60 | 2,500.00 | 7,500.00 | | 0125 | 822-19-00100 | Modular Breakaway Cable System | 15 | EACH | 2,322.01 | 34,830.15 | 2,205.50 | 33,082.50 | 2,200.00 | 33,000.00 | | 0126 | 822-20-00100 | Disconnect (Service) (Fused) | 3 | EACH | 3,749.04 | 11,247.12 | 2,882.00 | 8,646.00 | 3,500.00 | 10,500.00 | | 0127 | 822-20-00100 | Disconnect (Service) (Non-Fused) | 6 | EACH | 3,258.24 | 19,549.44 | 2,640.00 | 15,840.00 | 3,000.00 | 18,000.00 | | 0128 | 822-20-00200 | Disconnect (Underpass) (2P, 20A, 600V) | 1 | EACH | 1,848.94 | 1,848.94 | 1,760.00 | 1,760.00 | 1,700.00 | 1,700.00 | | 0129 | 822-20-00300 | Disconnect (Other) (Structure) (2P, 30A, 600V) | 8 | EACH | 1,694.69 | 13,557.52 | 1,760.00 | 14,080.00 | 1,600.00 | 12,800.00 | | 0130 | 822-21-00100 | Duct Marker (Concrete) | 33 | EACH | 275.92 | 9,105.36 | 440.00 | 14,520.00 | 260.00 | 8,580.00 | | 0131 | 822-22-00300 | Underground Marker Tape (6")(Detectable) | 6,751 | LNFT | 0.65 | 4,388.15 | 0.66 | 4,455.66 | 0.60 | 4,050.60 | | 0132 | 830-01-00100 | Bridge Superstructure Repair (Cross Frames) | 16 | EACH | 16,223.80 | 259,580.80 | 8,000.00 | 128,000.00 | 5,000.00 | 80,000.00 | | 0133 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 106 | LNFT | 7.11 | 753.66 | 11.00 | 1,166.00 | 10.00 | 1,060.00 | | 0134 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 53,372 | INLF | 1.03 | 54,973.16 | 1.00 | 53,372.00 | 1.00 | 53,372.00 | | 0135 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 7,254 | INLF | 0.79 | 5,730.66 | 1.00 | 7,254.00 | 1.00 | 7,254.00 | | 0136 | NS-700-00260 | Temporary Queue Detection System | 1 | LUMP | 2,143,000.00 | 2,143,000.00 | 1,750,000.00 | 1,750,000.00 | 2,000,000.00 | 2,000,000.00 | | 0137 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 6 | EACH | 23,838.83 | 143,032.98 | 6,000.00 | 36,000.00 | 9,700.00 | 58,200.00 | | 0138 | NS-700-00820 | Impact Attenuator Relocation (Construction Zone) | 6 | EACH | 4,646.86 | 27,881.16 | 1,200.00 | 7,200.00 | 1,500.00 | 9,000.00 | | 0139 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 17 | EACH | 587.88 | 9,993.96 | 8,000.00 | 136,000.00 | 22,000.00 | 374,000.00 | | 0140 | NS-713-00010 | Portable Changeable Message Sign (with comm and camera) | 4 | EACH | 2,939.40 | 11,757.60 | 20,000.00 | 80,000.00 | 30,000.00 | 120,000.00 | | 0141 | NS-713-00012 | Movable Barriers Phase 2 | 1 | LUMP | 400,000.00 | 400,000.00 | 480,000.00 | 480,000.00 | 840,000.00 | 840,000.00 | | 0142 | NS-713-00012 | Movable Barriers Phase 3 | 1 | LUMP | 350,000.00 | 350,000.00 | 510,000.00 | 510,000.00 | 30,000.00 | 30,000.00 | | 0143 | NS-713-00013 | Movable Barrier Movement Contraflow | 8 | EACH | 14,224.37 | 113,794.96 | 8,000.00 | 64,000.00 | 4,000.00 | 32,000.00 | | 0144 | NS-713-00013 | Movable Barrier Movement Traffic Management | 24 | EACH | 676.00 | 16,224.00 | 6,000.00 | 144,000.00 | 5,000.00 | 120,000.00 | | 0145 | NS-744-00500 | Modular Glare Screen (Complete System) | 3,810 | LNFT | 22.34 | 85,115.40 | 33.00 | 125,730.00 | 20.00 | 76,200.00 | | 0146 | NS-ITS-04101 | Fiber Optic Cable, SM, Install 96 Strand | 10,000 | LNFT | 1.49 | 14,900.00 | 2.42 | 24,200.00 | 1.40 | 14,000.00 | | 0147 | NS-ITS-06020 | Pullbox, In-ground, Furnish & Install - New (JBI) | 2 | EACH | 3,878.94 | 7,757.88 | 3,850.00 | 7,700.00 | 3,600.00 | 7,200.00 | | 0148 | NS-ITS-15620 | 2" FRE Conduit (Z) | 8,500 | LNFT | 46.31 | 393,635.00 | 51.70 | 439,450.00 | 43.00 | 365,500.00 | | 0149 | NS-ITS-15640 | 4" FRE Conduit (4 Way Innerduct) (Y) | 8,500 | LNFT | 54.49 | 463,165.00 | 77.00 | 654,500.00 | 51.00 | 433,500.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 35,374,000.00 | | 35,785,983.15 | | 36,309,519.80 |
|