Proposal:H.009508.6
Parish:Bossier
Routes:LA 2
Description:LA 2: CANEY CREEK BRIDGE TO WEBSTER P/L
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, ASPHALTIC SURFACE TREATMENT, PAVEMENT PATCHING, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$2,682,216.53
| Rank | License | Bidder | Construction Bid |
| 1 | 17464 | Benton & Brown, LLC. | $2,629,168.85 |
| 2 | 36374 | Best-Yet Builders, Llc | $2,634,674.91 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Benton & Brown, LLC. | - 2 - Best-Yet Builders, Llc | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-14500 | Removal of Guard Rail | 462 | LNFT | 8.40 | 3,880.80 | 5.00 | 2,310.00 | | 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" RCP | 193 | LNFT | 19.00 | 3,667.00 | 10.00 | 1,930.00 | | 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 2,000 | CUYD | 26.50 | 53,000.00 | 15.00 | 30,000.00 | | 0004 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 24 | EACH | 121.00 | 2,904.00 | 50.00 | 1,200.00 | | 0005 | 204-06-00100 | Temporary Silt Fencing | 543 | LNFT | 3.15 | 1,710.45 | 2.50 | 1,357.50 | | 0006 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 14 | CUYD | 150.00 | 2,100.00 | 100.00 | 1,400.00 | | 0007 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 57.00 | 5,700.00 | 150.00 | 15,000.00 | | 0008 | 502-01-00100 | Asphalt Concrete | 9,063.1 | TON | 105.00 | 951,625.50 | 118.00 | 1,069,445.80 | | 0009 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 383.8 | TON | 170.00 | 65,246.00 | 107.00 | 41,066.60 | | 0010 | 507-01-00100 | Asphalt Material (CRS-2P Emulsion) | 27,651 | GAL | 2.42 | 66,915.42 | 2.30 | 63,597.30 | | 0011 | 507-02-00200 | Aggregate (S2) | 40,663 | SQYD | 1.34 | 54,488.42 | 1.28 | 52,048.64 | | 0012 | 507-02-00300 | Aggregate (S3) | 40,663 | SQYD | 1.14 | 46,355.82 | 1.09 | 44,322.67 | | 0013 | 509-01-00100 | Milling Asphalt Pavement | 82,592 | SQYD | 3.00 | 247,776.00 | 3.50 | 289,072.00 | | 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -3,442 | CUYD | 0.01 | -34.42 | 0.10 | -344.20 | | 0015 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 8,134 | SQYD | 80.00 | 650,720.00 | 88.00 | 715,792.00 | | 0016 | 701-01-02001 | Cross Drain Pipe (24" RCP/PP/CMP) | 217 | LNFT | 200.00 | 43,400.00 | 137.50 | 29,837.50 | | 0017 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 217 | LNFT | 22.00 | 4,774.00 | 40.00 | 8,680.00 | | 0018 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 196 | LNFT | 63.00 | 12,348.00 | 60.00 | 11,760.00 | | 0019 | 704-03-00200 | Blocked Out Guard Rail – 31”, (6’-3” Post Spacing) | 362.5 | LNFT | 31.50 | 11,418.75 | 30.00 | 10,875.00 | | 0020 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 79.00 | 7,900.00 | 75.00 | 7,500.00 | | 0021 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 4 | EACH | 3,150.00 | 12,600.00 | 3,000.00 | 12,000.00 | | 0022 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 110,000.00 | 110,000.00 | 25,000.00 | 25,000.00 | | 0023 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 525 | LNFT | 1.05 | 551.25 | 1.00 | 525.00 | | 0024 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13.26 | MILE | 350.00 | 4,641.00 | 500.00 | 6,630.00 | | 0025 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 11.092 | MILE | 525.00 | 5,823.30 | 500.00 | 5,546.00 | | 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 32.294 | MILE | 525.00 | 16,954.35 | 500.00 | 16,147.00 | | 0027 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 832 | EACH | 1.68 | 1,397.76 | 1.60 | 1,331.20 | | 0028 | 716-01-00100 | Mulch (Vegetative) | 1.5 | TON | 1,575.00 | 2,362.50 | 3,000.00 | 4,500.00 | | 0029 | 717-01-00100 | Seeding | 56 | LB | 21.00 | 1,176.00 | 25.00 | 1,400.00 | | 0030 | 718-01-00100 | Fertilizer | 1,871 | LB | 1.05 | 1,964.55 | 1.00 | 1,871.00 | | 0031 | 724-01-00100 | Rumble Strips (Centerline) | 6.301 | MILE | 2,100.00 | 13,232.10 | 2,000.00 | 12,602.00 | | 0032 | 726-01-00100 | Bedding Material | 16.1 | CUYD | 100.00 | 1,610.00 | 100.00 | 1,610.00 | | 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 110,000.00 | 110,000.00 | 50,000.00 | 50,000.00 | | 0034 | 729-16-00200 | Object Marker Assembly (Type 2) | 6 | EACH | 68.00 | 408.00 | 100.00 | 600.00 | | 0035 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 105.00 | 420.00 | 100.00 | 400.00 | | 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,148 | EACH | 5.75 | 6,601.00 | 5.50 | 6,314.00 | | 0037 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 263 | LNFT | 15.75 | 4,142.25 | 15.00 | 3,945.00 | | 0038 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 16.147 | MILE | 3,900.00 | 62,973.30 | 3,700.00 | 59,743.90 | | 0039 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.546 | MILE | 1,575.00 | 8,734.95 | 1,500.00 | 8,319.00 | | 0040 | 732-05-00100 | Removal of Existing Markings | 0.329 | MILE | 10,500.00 | 3,454.50 | 10,000.00 | 3,290.00 | | 0041 | 735-01-00100 | Mailboxes | 6 | EACH | 1.05 | 6.30 | 75.00 | 450.00 | | 0042 | 735-02-00100 | Mailbox Supports (Single) | 6 | EACH | 370.00 | 2,220.00 | 100.00 | 600.00 | | 0043 | 740-01-00100 | Construction Layout | 1 | LUMP | 22,000.00 | 22,000.00 | 15,000.00 | 15,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,629,168.85 | | 2,634,674.91 |
|