Search


Bid Tabulations for the Letting of 5/9/2018 LA DOTD Headquarters

Proposal:H.012135.6
Parish:Calcasieu, Jefferson Davis
Routes:LA 383
Description:LA 383: I-10 - LA 101
Type Construction:MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, PAVEMENT WIDENING, ASPHALT CONCRETE PAVEMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,262,196.23
Rank License BidderConstruction Bid
134356Prairie Contractors Inc.$932,555.18
200183R. E. Heidt Construction Co., LLC$936,673.76
300481COASTAL BRIDGE CO., L.L.C.$1,188,006.23
412312GILCHRIST CONSTRUCTION CO. LLC$1,254,978.87


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Prairie Contractors Inc.
- 2 -
R. E. Heidt Construction Co., LLC
- 3 -
COASTAL BRIDGE CO., L.L.C.
- 4 -
GILCHRIST CONSTRUCTION CO. LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-06100Removal of Concrete Walks and Drives 217     SQYD20.004,340.0015.153,287.5515.003,255.0015.003,255.00
0002203-07-00100Borrow (Vehicular Measurement) 50     CUYD30.001,500.0025.251,262.5050.002,500.0050.002,500.00
0003204-02-00100Temporary Hay Bales 30     EACH18.00540.0013.60408.0013.50405.0014.00420.00
0004204-06-00100Temporary Silt Fencing 770     LNFT3.502,695.003.302,541.003.502,695.003.502,695.00
0005401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 18     CUYD200.003,600.00150.002,700.00100.001,800.00200.003,600.00
0006402-03-00100Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 30     CUYD100.003,000.00140.004,200.0075.002,250.00100.003,000.00
0007502-01-00100Asphalt Concrete 6,975.1   TON76.00530,107.6085.00592,883.5090.00627,759.0098.00683,559.80
0008502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 273.8   TON45.0012,321.0087.0023,820.60150.0041,070.0098.0026,832.40
0009509-01-00100Milling Asphalt Pavement 38,319     SQYD1.9574,722.050.9536,403.052.69103,078.112.0076,638.00
0010509-02-00100Contractor Retained Reclaimed Asphalt Pavement -1,517     CUYD0.01-15.170.04-60.680.01-15.171.00-1,517.00
0011510-01-00300Pavement Patching (18" Minimum Thickness) 240     SQYD60.0014,400.0094.0022,560.00125.0030,000.00150.0036,000.00
0012510-02-00100Pavement Widening (Asphalt Widening)876     SQYD66.0057,816.0080.0070,080.0075.0065,700.00120.00105,120.00
0013602-05-01200Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) 40     SQYD200.008,000.00181.807,272.00300.0012,000.00425.0017,000.00
0014602-05-02200Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) 37     SQYD180.006,660.00171.706,352.90300.0011,100.00250.009,250.00
0015602-05-03200Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) 134     SQYD170.0022,780.00161.6021,654.40300.0040,200.00170.0022,780.00
0016706-02-00200Concrete Drive (6" Thick) 190     SQYD120.0022,800.00116.1522,068.5080.0015,200.0070.0013,300.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP15,000.0015,000.004,460.004,460.0032,000.0032,000.0021,600.0021,600.00
0018713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 7.686 MILE500.003,843.00365.002,805.39150.001,152.90225.001,729.35
0019713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 7.539 MILE0.010.08202.001,522.88210.001,583.191.007.54
0020713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 17.031 MILE0.010.17404.006,880.52410.006,982.711.0017.03
0021724-01-00100Rumble Strips (Centerline) 2.213 MILE1,000.002,213.00303.00670.54310.00686.03715.001,582.30
0022724-02-00100Rumble Strips (Shoulder/Edge) 4.426 MILE1,000.004,426.00303.001,341.08310.001,372.06525.002,323.65
0023727-01-00100Mobilization 1     LUMP84,000.0084,000.0031,000.0031,000.0075,000.0075,000.00120,000.00120,000.00
0024729-16-00200Object Marker Assembly (Type 2) 10     EACH65.00650.0065.65656.5080.00800.0068.00680.00
0025731-02-00100Reflectorized Raised Pavement Markers 370     EACH6.002,220.005.051,868.505.001,850.005.001,850.00
0026732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 5.677 MILE2,900.0016,463.302,828.0016,054.563,200.0018,166.402,800.0015,895.60
0027732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.513 MILE950.002,387.35909.002,284.321,000.002,513.00900.002,261.70
0028732-03-02010Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) 0.109 MILE7,000.00763.005,050.00550.455,000.00545.00500.0054.50
0029735-01-00100Mailboxes 7     EACH10.0070.0015.15106.053.0021.0016.00112.00
0030735-02-00100Mailbox Supports (Single) 7     EACH275.001,925.00116.15813.05245.001,715.00125.00875.00
0031739-01-00100Hydro-Seeding 0.038 ACRE50,000.001,900.0019,800.00752.4035,000.001,330.0031,000.001,178.00
0032740-01-00100Construction Layout 1     LUMP100.00100.006,100.006,100.004,500.004,500.009,000.009,000.00
0033NS-401-00100Hot-Mix Asphalt Aggregate Surface Course 518     TON57.0029,526.0076.5039,627.00150.0077,700.00132.0068,376.00
0034NS-600-00220Saw Cutting Portland Cement Concrete Pavement 1,092     INLF1.651,801.801.601,747.201.001,092.002.753,003.00
             
  CONTRACTOR TOTAL   932,555.18 936,673.76 1,188,006.23 1,254,978.87