Proposal:H.012831.6
Parish:Ouachita
Routes:I-20
Description:NUTLAND RD OVER I-20 GIRDER REPAIR
Type Construction:BRIDGE REPAIRS AND RELATED WORK.
Estimated Construction Cost:$176,643.84
| Rank | License | Bidder | Construction Bid |
| 1 | 44133 | Gibson & Associates Inc. | $170,656.05 |
| 2 | 55519 | Key, LLC Of Mississippi | $211,635.95 |
| 3 | 39462 | JB JAMES CONSTRUCTION LLC | $238,660.99 |
| 4 | 49239 | WL Bass Construction Inc. | $338,035.89 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Gibson & Associates Inc. | - 2 - Key, LLC Of Mississippi | - 3 - JB JAMES CONSTRUCTION LLC | - 4 - WL Bass Construction Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 500.00 | 500.00 | 2,500.00 | 2,500.00 | 100,000.00 | 100,000.00 | 2,000.00 | 2,000.00 | | 0002 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 23,000.00 | 23,000.00 | 49,500.00 | 49,500.00 | 22,000.00 | 22,000.00 | 57,700.00 | 57,700.00 | | 0003 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.5 | MILE | 4,500.00 | 2,250.00 | 5,000.00 | 2,500.00 | 3,850.00 | 1,925.00 | 3,850.00 | 1,925.00 | | 0004 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.5 | MILE | 10,500.00 | 5,250.00 | 10,000.00 | 5,000.00 | 9,500.00 | 4,750.00 | 9,500.00 | 4,750.00 | | 0005 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 1,650.00 | 3,300.00 | 1,250.00 | 2,500.00 | 3,000.00 | 6,000.00 | 2,500.00 | 5,000.00 | | 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 26,250.00 | 26,250.00 | 75,500.00 | 75,500.00 | 22,000.00 | 22,000.00 | 30,000.00 | 30,000.00 | | 0007 | 729-13-00100 | Mounting (Bridge Fascia Mounted) Remove and Replace | 2 | EACH | 2,000.00 | 4,000.00 | 3,750.00 | 7,500.00 | 15,155.07 | 30,310.14 | 20,000.00 | 40,000.00 | | 0008 | 740-01-00100 | Construction Layout | 1 | LUMP | 500.00 | 500.00 | 6,500.00 | 6,500.00 | 20,000.00 | 20,000.00 | 2,000.00 | 2,000.00 | | 0009 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 98.17 | SQFT | 65.00 | 6,381.05 | 35.00 | 3,435.95 | 5.00 | 490.85 | 667.00 | 65,479.39 | | 0010 | NS-830-01200 | Carbon Fiber Reinforced Polymer Repairs | 94.5 | SQFT | 1,050.00 | 99,225.00 | 600.00 | 56,700.00 | 330.00 | 31,185.00 | 1,367.00 | 129,181.50 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 170,656.05 | | 211,635.95 | | 238,660.99 | | 338,035.89 |
|