Proposal:H.011239.6
Parish:Lafourche
Routes:LA 1
Description:LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2E
Type Construction:DRILLED SHAFT FOUNDATIONS, INTELLIGENT TRANSPORTATION SYSTEM, PRECAST CONCRETE PILES, PRECAST-PRESTRESSED CONCRETE GIRDER SPANS BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$11,334,350.41
| Rank | License | Bidder | Construction Bid |
| 1 | 34567 | James Construction Group LLC | $13,248,581.59 |
| 2 | 00271 | Massman Construction Co. | $14,587,137.25 |
| 3 | 39462 | JB JAMES CONSTRUCTION LLC | $15,162,105.45 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $15,407,520.25 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - James Construction Group LLC | - 2 - Massman Construction Co. | - 3 - JB JAMES CONSTRUCTION LLC | - 4 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 400,000.00 | 400,000.00 | 9,800.00 | 9,800.00 | 30,000.00 | 30,000.00 | 300,000.00 | 300,000.00 | | 0002 | 202-02-04500 | Removal of Bridge (Partial Removal) (Deck and Barrier Rail) | 6,238 | SQFT | 30.00 | 187,140.00 | 70.00 | 436,660.00 | 65.00 | 405,470.00 | 75.00 | 467,850.00 | | 0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 67,000.00 | 67,000.00 | 46,500.00 | 46,500.00 | 300,000.00 | 300,000.00 | 475,000.00 | 475,000.00 | | 0004 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 9 | EACH | 2,500.00 | 22,500.00 | 1,900.00 | 17,100.00 | 1,800.00 | 16,200.00 | 775.00 | 6,975.00 | | 0005 | 713-08-00100 | Temporary Precast Concrete Barrier (Department Furnished) | 123 | EACH | 2,000.00 | 246,000.00 | 1,100.00 | 135,300.00 | 750.00 | 92,250.00 | 615.00 | 75,645.00 | | 0006 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 17 | EACH | 700.00 | 11,900.00 | 1,100.00 | 18,700.00 | 350.00 | 5,950.00 | 115.00 | 1,955.00 | | 0007 | 727-01-00100 | Mobilization | 1 | LUMP | 1,300,000.00 | 1,300,000.00 | 1,240,091.00 | 1,240,091.00 | 1,500,000.00 | 1,500,000.00 | 1,500,000.00 | 1,500,000.00 | | 0008 | 729-01-00103 | Sign (Type A)(Relocate) | 65 | SQFT | 15.00 | 975.00 | 15.00 | 975.00 | 15.00 | 975.00 | 17.00 | 1,105.00 | | 0009 | 729-08-00200 | Mounting (3 1/2" Size Post) | 2 | EACH | 1,500.00 | 3,000.00 | 1,500.00 | 3,000.00 | 1,500.00 | 3,000.00 | 1,700.00 | 3,400.00 | | 0010 | 731-02-00100 | Reflectorized Raised Pavement Markers | 157 | EACH | 7.50 | 1,177.50 | 7.50 | 1,177.50 | 7.50 | 1,177.50 | 8.00 | 1,256.00 | | 0011 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.915 | MILE | 3,500.00 | 6,702.50 | 3,500.00 | 6,702.50 | 3,500.00 | 6,702.50 | 4,000.00 | 7,660.00 | | 0012 | 732-05-00100 | Removal of Existing Markings | 0.389 | MILE | 5,000.00 | 1,945.00 | 5,000.00 | 1,945.00 | 5,000.00 | 1,945.00 | 5,500.00 | 2,139.50 | | 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 400,000.00 | 400,000.00 | 5,500.00 | 5,500.00 | 300,000.00 | 300,000.00 | 450,000.00 | 450,000.00 | | 0014 | 804-01-00600 | Precast Concrete Piles (24") | 14,419 | LNFT | 170.00 | 2,451,230.00 | 180.00 | 2,595,420.00 | 295.00 | 4,253,605.00 | 180.00 | 2,595,420.00 | | 0015 | 804-01-00700 | Precast Concrete Piles (30") | 4,251 | LNFT | 225.00 | 956,475.00 | 260.00 | 1,105,260.00 | 315.00 | 1,339,065.00 | 217.00 | 922,467.00 | | 0016 | 804-14-00100 | Dynamic Monitoring Assistance | 66 | EACH | 2,500.00 | 165,000.00 | 2,200.00 | 145,200.00 | 1,500.00 | 99,000.00 | 1,300.00 | 85,800.00 | | 0017 | 805-01-00200 | Class A1 Concrete (Deck) | 1,747 | CUYD | 1,500.00 | 2,620,500.00 | 2,005.00 | 3,502,735.00 | 1,500.00 | 2,620,500.00 | 1,800.00 | 3,144,600.00 | | 0018 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 256 | CUYD | 3,000.00 | 768,000.00 | 4,450.00 | 1,139,200.00 | 2,500.00 | 640,000.00 | 3,000.00 | 768,000.00 | | 0019 | 805-04-00100 | Class MASS(A1) Concrete (Bent Cap) | 190 | CUYD | 2,500.00 | 475,000.00 | 4,000.00 | 760,000.00 | 1,700.00 | 323,000.00 | 2,200.00 | 418,000.00 | | 0020 | 805-08-00400 | Precast-Prestressed Concrete Girders (Type III) | 5,323 | LNFT | 150.00 | 798,450.00 | 135.00 | 718,605.00 | 150.00 | 798,450.00 | 155.00 | 825,065.00 | | 0021 | 805-08-01200 | Precast-Prestressed Concrete Girder (Type LG-36) | 1,292 | LNFT | 300.00 | 387,600.00 | 235.00 | 303,620.00 | 230.00 | 297,160.00 | 225.00 | 290,700.00 | | 0022 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 18,517 | SQFT | 0.50 | 9,258.50 | 1.25 | 23,146.25 | 1.00 | 18,517.00 | 2.00 | 37,034.00 | | 0023 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 78,725 | SQFT | 0.60 | 47,235.00 | 1.25 | 98,406.25 | 1.25 | 98,406.25 | 1.75 | 137,768.75 | | 0024 | 806-01-00100 | Deformed Reinforcing Steel | 578,592 | LB | 1.50 | 867,888.00 | 1.90 | 1,099,324.80 | 1.35 | 781,099.20 | 2.00 | 1,157,184.00 | | 0025 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 1,156 | LUMP | 35,000.00 | 35,000.00 | 58,000.00 | 58,000.00 | 50,000.00 | 50,000.00 | 40,000.00 | 40,000.00 | | 0026 | 807-04-00100 | Structural Metalwork (Access Ladder) | 309 | LUMP | 1,500.00 | 1,500.00 | 3,100.00 | 3,100.00 | 10,000.00 | 10,000.00 | 6,000.00 | 6,000.00 | | 0027 | 807-04-00100 | Structural Metalwork (Armored Joints) | 1,852 | LUMP | 55,000.00 | 55,000.00 | 68,000.00 | 68,000.00 | 18,000.00 | 18,000.00 | 11,000.00 | 11,000.00 | | 0028 | 807-04-00100 | Structural Metalwork (Dowel (SS)) | 260 | LUMP | 20,000.00 | 20,000.00 | 8,500.00 | 8,500.00 | 15,000.00 | 15,000.00 | 2,000.00 | 2,000.00 | | 0029 | 807-04-00100 | Structural Metalwork (Sign Supports) | 284 | LUMP | 2,000.00 | 2,000.00 | 9,000.00 | 9,000.00 | 15,000.00 | 15,000.00 | 8,500.00 | 8,500.00 | | 0030 | 807-04-00100 | Structural Metalwork (Tie Rods) | 606 | LUMP | 22,000.00 | 22,000.00 | 41,000.00 | 41,000.00 | 10,000.00 | 10,000.00 | 22,500.00 | 22,500.00 | | 0031 | 810-01-00100 | Concrete Bridge Railing (Standard) | 2,257 | LNFT | 85.00 | 191,845.00 | 126.00 | 284,382.00 | 70.00 | 157,990.00 | 270.00 | 609,390.00 | | 0032 | 810-01-00200 | Concrete Bridge Railing (Slotted) | 357 | LNFT | 90.00 | 32,130.00 | 188.00 | 67,116.00 | 75.00 | 26,775.00 | 218.00 | 77,826.00 | | 0033 | 810-04-00100 | Hand Railing (Steel Pipe Handrail - CCTV Platform) | 39 | LNFT | 70.00 | 2,730.00 | 95.00 | 3,705.00 | 200.00 | 7,800.00 | 100.00 | 3,900.00 | | 0034 | 810-05-00400 | Concrete Roadway Barrier (Safe-T-Curve Barrier System) | 150 | LNFT | 650.00 | 97,500.00 | 650.00 | 97,500.00 | 550.00 | 82,500.00 | 745.00 | 111,750.00 | | 0035 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 58 | SFIN | 250.00 | 14,500.00 | 500.00 | 29,000.00 | 500.00 | 29,000.00 | 60.00 | 3,480.00 | | 0036 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 374 | SFIN | 110.00 | 41,140.00 | 154.00 | 57,596.00 | 550.00 | 205,700.00 | 280.00 | 104,720.00 | | 0037 | 815-02-00100 | Sealed Expansion Joint (End Dams and Preformed Neoprene Seal) | 99 | LNFT | 300.00 | 29,700.00 | 200.00 | 19,800.00 | 400.00 | 39,600.00 | 215.00 | 21,285.00 | | 0038 | 815-02-00200 | Sealed Expansion Joint (End Dams and Preformed Silicone Seal) | 176 | LNFT | 230.00 | 40,480.00 | 260.00 | 45,760.00 | 400.00 | 70,400.00 | 175.00 | 30,800.00 | | 0039 | 822-02-02200 | Conduit w Conductors (Rigid Galv Steel) (1") (PVC Coated) (2#10, 1#10 Green Insulated Ground) | 130 | LNFT | 9.00 | 1,170.00 | 60.16 | 7,820.80 | 62.00 | 8,060.00 | 70.00 | 9,100.00 | | 0040 | 822-02-02200 | Conduit w Conductors (Rigid Galv Steel) (1") (PVC Coated) (4#10, 1#10 Green Insulated Ground) | 140 | LNFT | 10.00 | 1,400.00 | 61.37 | 8,591.80 | 62.00 | 8,680.00 | 70.00 | 9,800.00 | | 0041 | 822-02-02200 | Conduit w Conductors (Rigid Galv Steel) (1") (PVC Coated) (8#10, 1#10 Green Insulated Ground) | 195 | LNFT | 10.00 | 1,950.00 | 62.15 | 12,119.25 | 64.00 | 12,480.00 | 70.00 | 13,650.00 | | 0042 | 822-02-02200 | Conduit w Conductors (Rigid Galv Steel) (1") (PVC Coated) (Empty) | 260 | LNFT | 60.16 | 15,641.60 | 63.71 | 16,564.60 | 60.00 | 15,600.00 | 73.00 | 18,980.00 | | 0043 | 822-02-02500 | Conduit w Conductors (Rigid Galv Steel) (2") (PVC Coated) (3#6, 1#6 Green Insulated Ground) | 575 | LNFT | 76.86 | 44,194.50 | 76.86 | 44,194.50 | 77.00 | 44,275.00 | 88.00 | 50,600.00 | | 0044 | 822-05-00700 | Light Pole (40') (Alum) (Single Arm) | 16 | EACH | 4,200.00 | 67,200.00 | 5,180.00 | 82,880.00 | 5,200.00 | 83,200.00 | 6,000.00 | 96,000.00 | | 0045 | 822-07-02800 | Luminaire (LED) | 16 | EACH | 838.66 | 13,418.56 | 840.00 | 13,440.00 | 840.00 | 13,440.00 | 960.00 | 15,360.00 | | 0046 | 822-09-00100 | Electrical System (Temporary Lighting) | 1 | LUMP | 16,389.36 | 16,389.36 | 16,400.00 | 16,400.00 | 16,400.00 | 16,400.00 | 18,750.00 | 18,750.00 | | 0047 | 822-11-00100 | Removal and Disposal of Electrical Equipment (ITS) | 1 | LUMP | 5,000.00 | 5,000.00 | 5,300.00 | 5,300.00 | 5,300.00 | 5,300.00 | 6,000.00 | 6,000.00 | | 0048 | 822-11-00100 | Removal and Disposal of Electrical Equipment (Lighting) | 1 | LUMP | 14,439.36 | 14,439.36 | 14,500.00 | 14,500.00 | 14,500.00 | 14,500.00 | 16,500.00 | 16,500.00 | | 0049 | 822-14-00100 | Removal and Disposal of Luminaire | 13 | EACH | 200.00 | 2,600.00 | 73.00 | 949.00 | 73.00 | 949.00 | 85.00 | 1,105.00 | | 0050 | 822-17-00100 | Structure Junction Box (Cast Aluminum) (8" x 8" x 4") | 6 | EACH | 1,000.00 | 6,000.00 | 1,000.00 | 6,000.00 | 1,000.00 | 6,000.00 | 1,200.00 | 7,200.00 | | 0051 | 822-17-00400 | Structure Junction Box (Stainless Steel) | 1 | EACH | 1,100.00 | 1,100.00 | 2,100.00 | 2,100.00 | 2,100.00 | 2,100.00 | 2,400.00 | 2,400.00 | | 0052 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 1 | EACH | 8,500.00 | 8,500.00 | 8,500.00 | 8,500.00 | 8,500.00 | 8,500.00 | 9,750.00 | 9,750.00 | | 0053 | NS-700-00820 | Impact Attenuator Relocation (Construction Zone) | 1 | EACH | 1,100.00 | 1,100.00 | 1,100.00 | 1,100.00 | 1,100.00 | 1,100.00 | 1,300.00 | 1,300.00 | | 0054 | NS-700-00840 | Impact Attenuator (Test Level 3) (Universal Tau-II System) | 1 | EACH | 33,000.00 | 33,000.00 | 33,000.00 | 33,000.00 | 33,000.00 | 33,000.00 | 38,000.00 | 38,000.00 | | 0055 | NS-722-00002 | Modular Office Building | 1 | LUMP | 93,000.00 | 93,000.00 | 25,000.00 | 25,000.00 | 75,000.00 | 75,000.00 | 200,000.00 | 200,000.00 | | 0056 | NS-ITS-01241 | CCTV C/Assembly, Install with PTZ, Digital | 2 | EACH | 982.12 | 1,964.24 | 1,000.00 | 2,000.00 | 982.00 | 1,964.00 | 1,125.00 | 2,250.00 | | 0057 | NS-ITS-07220 | ITS Controller Cabinet, Pad Mount, Furnish & Install | 1 | EACH | 32,789.12 | 32,789.12 | 32,800.00 | 32,800.00 | 32,800.00 | 32,800.00 | 37,500.00 | 37,500.00 | | 0058 | NS-ITS-08061 | Pole, Foundation & Lowering Device, >= 60', Furnish & Install (50') | 1 | EACH | 69,734.64 | 69,734.64 | 8,000.00 | 8,000.00 | 69,750.00 | 69,750.00 | 80,000.00 | 80,000.00 | | 0059 | NS-ITS-09400 | Point-to-Point Microwave Ethernet Data Radio, Furnish & Install | 1 | EACH | 14,791.40 | 14,791.40 | 14,800.00 | 14,800.00 | 14,800.00 | 14,800.00 | 17,000.00 | 17,000.00 | | 0060 | NS-ITS-09460 | Point-to-Point Microwave Ethernet Data Radio Antenna, Furnish & Install | 1 | EACH | 4,682.34 | 4,682.34 | 4,700.00 | 4,700.00 | 4,690.00 | 4,690.00 | 5,500.00 | 5,500.00 | | 0061 | NS-ITS-09520 | Point-to-Point Microwave Ethernet Data Radio Cable, Furnish & Install | 1 | EACH | 3,381.56 | 3,381.56 | 3,400.00 | 3,400.00 | 3,380.00 | 3,380.00 | 4,000.00 | 4,000.00 | | 0062 | NS-ITS-10220 | Power Surge Suppressor, Furnish & Install | 2 | EACH | 375.49 | 750.98 | 375.00 | 750.00 | 375.00 | 750.00 | 450.00 | 900.00 | | 0063 | NS-ITS-10340 | Data Surge Suppressor, Furnish & Install | 4 | EACH | 310.49 | 1,241.96 | 310.00 | 1,240.00 | 310.00 | 1,240.00 | 350.00 | 1,400.00 | | 0064 | NS-ITS-10362 | Power Surge Suppressor (ITS Cabinet), Furnish & Install | 1 | EACH | 1,057.99 | 1,057.99 | 1,060.00 | 1,060.00 | 1,060.00 | 1,060.00 | 1,300.00 | 1,300.00 | | 0065 | NS-ITS-12020 | TMC Integration | 1 | LUMP | 8,589.36 | 8,589.36 | 8,600.00 | 8,600.00 | 8,590.00 | 8,590.00 | 10,000.00 | 10,000.00 | | 0066 | NS-ITS-13200 | As-Builts | 1 | LUMP | 2,993.12 | 2,993.12 | 4,500.00 | 4,500.00 | 4,260.00 | 4,260.00 | 5,000.00 | 5,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 13,248,581.59 | | 14,587,137.25 | | 15,162,105.45 | | 15,407,520.25 |
|