Proposal:H.010661.6
Parish:East Baton Rouge
Description:N. FLANNERY/ FIREWOOD/ CLOVERLAND BRIDGES
Type Construction:CLEARING AND GRUBBING, REMOVAL OF BRIDGES, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGES, AND RELATED WORK.
Estimated Construction Cost:$1,860,607.00
| Rank | License | Bidder | Construction Bid |
| 1 | 55505 | MERRICK, LLC | $1,875,442.10 |
| 2 | 63897 | TL Hawk, LLC | $1,883,881.20 |
| 3 | 39462 | JB JAMES CONSTRUCTION LLC | $2,397,219.10 |
| 4 | 00044 | Guinn Construction, LLC | $2,409,542.50 |
| 5 | 36827 | Shavers-Whittle Construction LLC | $2,443,425.45 |
| 6 | 12312 | GILCHRIST CONSTRUCTION CO. LLC | $2,499,577.90 |
| 7 | 49239 | WL Bass Construction Inc. | $2,531,208.90 |
| 8 | 00481 | COASTAL BRIDGE CO., L.L.C. | $2,618,373.54 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - MERRICK, LLC | - 2 - TL Hawk, LLC | - 3 - JB JAMES CONSTRUCTION LLC | - 4 - Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 3 | LUMP | 20,000.00 | 20,000.00 | 40,000.00 | 40,000.00 | 200,000.00 | 200,000.00 | 40,000.00 | 40,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 25,000.00 | 25,000.00 | 40,000.00 | 40,000.00 | 15,000.00 | 15,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 60 | SQYD | 20.00 | 1,200.00 | 8.00 | 480.00 | 30.00 | 1,800.00 | 5.00 | 300.00 | | 0004 | 202-02-04000 | Removal of Bridge (STA 100+00, 23.7' X 76.5' CONCRETE SLAB BRIDGE W/ TIMBER PILES) | 1 | EACH | 22,000.00 | 22,000.00 | 30,000.00 | 30,000.00 | 58,000.00 | 58,000.00 | 30,000.00 | 30,000.00 | | 0005 | 202-02-04000 | Removal of Bridge (STA 200+00, 28.5' X 56.9' CONCRETE SLAB BRIDGE W/ TIMBER PILES) | 1 | EACH | 22,000.00 | 22,000.00 | 35,000.00 | 35,000.00 | 55,000.00 | 55,000.00 | 25,000.00 | 25,000.00 | | 0006 | 202-02-04000 | Removal of Bridge (STA 300+00, 28.5 'X 57.1' CONCRETE SLAB BRIDGE W/ TIMBER PILES) | 1 | EACH | 22,000.00 | 22,000.00 | 35,000.00 | 35,000.00 | 55,000.00 | 55,000.00 | 35,000.00 | 35,000.00 | | 0007 | 202-02-06000 | Removal of Concrete Approach Slabs | 268 | SQYD | 40.00 | 10,720.00 | 40.00 | 10,720.00 | 45.00 | 12,060.00 | 50.00 | 13,400.00 | | 0008 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 90.5 | LNFT | 10.00 | 905.00 | 6.00 | 543.00 | 15.00 | 1,357.50 | 10.00 | 905.00 | | 0009 | 202-02-06090 | Removal of Concrete Revetment | 1 | LUMP | 8,000.00 | 8,000.00 | 6,045.00 | 6,045.00 | 30,000.00 | 30,000.00 | 40,000.00 | 40,000.00 | | 0010 | 202-02-06100 | Removal of Concrete Walks and Drives | 292 | SQYD | 10.00 | 2,920.00 | 6.00 | 1,752.00 | 15.00 | 4,380.00 | 10.00 | 2,920.00 | | 0011 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 1,390.8 | SQYD | 11.00 | 15,298.80 | 8.00 | 11,126.40 | 12.00 | 16,689.60 | 10.00 | 13,908.00 | | 0012 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 85,000.00 | 85,000.00 | 50,000.00 | 50,000.00 | 60,000.00 | 60,000.00 | 55,000.00 | 55,000.00 | | 0013 | 204-02-00100 | Temporary Hay or Straw Bales | 48 | EACH | 20.00 | 960.00 | 30.00 | 1,440.00 | 50.00 | 2,400.00 | 25.00 | 1,200.00 | | 0014 | 204-03-00100 | Temporary Slope Drains | 40 | LNFT | 15.00 | 600.00 | 1.00 | 40.00 | 8.00 | 320.00 | 1.00 | 40.00 | | 0015 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 2 | EACH | 200.00 | 400.00 | 175.00 | 350.00 | 500.00 | 1,000.00 | 500.00 | 1,000.00 | | 0016 | 204-06-00100 | Temporary Silt Fencing | 1,682 | LNFT | 2.00 | 3,364.00 | 2.75 | 4,625.50 | 3.50 | 5,887.00 | 4.00 | 6,728.00 | | 0017 | 302-01-00700 | Class II Base Course (Stone) (CRUSHED) | 416.5 | CUYD | 135.00 | 56,227.50 | 100.00 | 41,650.00 | 110.00 | 45,815.00 | 140.00 | 58,310.00 | | 0018 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 4 | CUYD | 250.00 | 1,000.00 | 120.00 | 480.00 | 360.00 | 1,440.00 | 250.00 | 1,000.00 | | 0019 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 90.00 | 4,500.00 | 80.00 | 4,000.00 | 110.00 | 5,500.00 | 100.00 | 5,000.00 | | 0020 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) (RCP/PP only) | 67 | LNFT | 70.00 | 4,690.00 | 60.00 | 4,020.00 | 95.00 | 6,365.00 | 68.00 | 4,556.00 | | 0021 | 701-05-01080 | Side Drain Pipe (30" RCP/PP/CMP) (RCP/PP only) | 74 | LNFT | 95.00 | 7,030.00 | 90.00 | 6,660.00 | 110.00 | 8,140.00 | 175.00 | 12,950.00 | | 0022 | 702-03-00100 | Catch Basins (CB-01) | 2 | EACH | 4,000.00 | 8,000.00 | 4,000.00 | 8,000.00 | 4,000.00 | 8,000.00 | 5,000.00 | 10,000.00 | | 0023 | 704-03-00100 | Blocked Out Guard Rail | 50 | LNFT | 22.00 | 1,100.00 | 18.00 | 900.00 | 20.00 | 1,000.00 | 30.00 | 1,500.00 | | 0024 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 70.00 | 7,000.00 | 80.00 | 8,000.00 | 65.00 | 6,500.00 | 75.00 | 7,500.00 | | 0025 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,500.00 | 10,000.00 | 2,200.00 | 8,800.00 | 2,500.00 | 10,000.00 | 2,500.00 | 10,000.00 | | 0026 | 705-01-00100 | Barbed Wire Fence | 112 | LNFT | 30.00 | 3,360.00 | 19.50 | 2,184.00 | 19.50 | 2,184.00 | 25.00 | 2,800.00 | | 0027 | 706-01-00100 | Concrete Walk (4" Thick) | 87.6 | SQYD | 80.00 | 7,008.00 | 60.00 | 5,256.00 | 55.00 | 4,818.00 | 100.00 | 8,760.00 | | 0028 | 706-02-00200 | Concrete Drive (6" Thick) | 242.4 | SQYD | 90.00 | 21,816.00 | 85.00 | 20,604.00 | 60.00 | 14,544.00 | 100.00 | 24,240.00 | | 0029 | 707-03-00100 | Combination Concrete Curb and Gutter | 74 | LNFT | 38.00 | 2,812.00 | 35.00 | 2,590.00 | 50.00 | 3,700.00 | 100.00 | 7,400.00 | | 0030 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 222 | SQYD | 75.00 | 16,650.00 | 90.00 | 19,980.00 | 80.00 | 17,760.00 | 100.00 | 22,200.00 | | 0031 | 711-04-00100 | Geotextile Fabric | 222 | SQYD | 2.00 | 444.00 | 7.00 | 1,554.00 | 4.00 | 888.00 | 10.00 | 2,220.00 | | 0032 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 273 | SQYD | 95.00 | 25,935.00 | 80.00 | 21,840.00 | 85.00 | 23,205.00 | 100.00 | 27,300.00 | | 0033 | 712-01-00300 | Concrete Cast-in-Place Revetment (6" Thick) | 326 | SQYD | 102.00 | 33,252.00 | 105.00 | 34,230.00 | 92.00 | 29,992.00 | 125.00 | 40,750.00 | | 0034 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 20,000.00 | 20,000.00 | 27,000.00 | 27,000.00 | 25,000.00 | 25,000.00 | | 0035 | 716-01-00100 | Mulch (Vegetative) | 0.8 | TON | 2,200.00 | 1,760.00 | 1,500.00 | 1,200.00 | 1,500.00 | 1,200.00 | 10,000.00 | 8,000.00 | | 0036 | 717-01-00100 | Seeding | 15 | LB | 80.00 | 1,200.00 | 10.00 | 150.00 | 55.00 | 825.00 | 100.00 | 1,500.00 | | 0037 | 718-01-00100 | Fertilizer | 356 | LB | 5.00 | 1,780.00 | 2.10 | 747.60 | 4.00 | 1,424.00 | 5.00 | 1,780.00 | | 0038 | 726-01-00100 | Bedding Material | 3.2 | CUYD | 300.00 | 960.00 | 100.00 | 320.00 | 180.00 | 576.00 | 250.00 | 800.00 | | 0039 | 727-01-00100 | Mobilization | 1 | LUMP | 187,000.00 | 187,000.00 | 188,000.00 | 188,000.00 | 236,000.00 | 236,000.00 | 275,000.00 | 275,000.00 | | 0040 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 90.00 | 1,080.00 | 80.00 | 960.00 | 75.00 | 900.00 | 100.00 | 1,200.00 | | 0041 | 735-01-00100 | Mailboxes | 2 | EACH | 30.00 | 60.00 | 5.00 | 10.00 | 1.00 | 2.00 | 100.00 | 200.00 | | 0042 | 735-02-00100 | Mailbox Supports (Single) | 2 | EACH | 200.00 | 400.00 | 350.00 | 700.00 | 150.00 | 300.00 | 200.00 | 400.00 | | 0043 | 740-01-00100 | Construction Layout | 1 | LUMP | 35,000.00 | 35,000.00 | 40,000.00 | 40,000.00 | 25,000.00 | 25,000.00 | 40,000.00 | 40,000.00 | | 0044 | 804-01-00300 | Precast Concrete Piles (16") | 2,970 | LNFT | 90.00 | 267,300.00 | 72.00 | 213,840.00 | 100.00 | 297,000.00 | 75.00 | 222,750.00 | | 0045 | 804-01-00600 | Precast Concrete Piles (24") | 440 | LNFT | 135.00 | 59,400.00 | 145.00 | 63,800.00 | 195.00 | 85,800.00 | 300.00 | 132,000.00 | | 0046 | 804-12-00100 | Loading Permanent Piles | 3 | EACH | 1,000.00 | 3,000.00 | 15,000.00 | 45,000.00 | 2,500.00 | 7,500.00 | 1.00 | 3.00 | | 0047 | 805-01-00700 | Class A Concrete (Bents) | 28.51 | CUYD | 800.00 | 22,808.00 | 800.00 | 22,808.00 | 1,500.00 | 42,765.00 | 1,800.00 | 51,318.00 | | 0048 | 805-04-00100 | Class AA(M) Concrete | 34.04 | CUYD | 1,600.00 | 54,464.00 | 700.00 | 23,828.00 | 2,000.00 | 68,080.00 | 1,600.00 | 54,464.00 | | 0049 | 805-10-02120 | Bridge Superstructure and Substructure (28' Clear Roadway; 60 Degree Crossing) (Cast-in-Place) | 2 | SPAN | 38,000.00 | 76,000.00 | 45,000.00 | 90,000.00 | 50,000.00 | 100,000.00 | 62,500.00 | 125,000.00 | | 0050 | 805-10-02320 | Bridge Superstructure and Substructure (28' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) (20' Span with Sidewalks) | 5 | SPAN | 60,000.00 | 300,000.00 | 65,000.00 | 325,000.00 | 70,000.00 | 350,000.00 | 68,500.00 | 342,500.00 | | 0051 | 805-10-02320 | Bridge Superstructure and Substructure (28' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) (25' Span with Sidewalks) | 1 | SPAN | 62,000.00 | 62,000.00 | 80,000.00 | 80,000.00 | 70,000.00 | 70,000.00 | 72,500.00 | 72,500.00 | | 0052 | 806-01-00100 | Deformed Reinforcing Steel | 14,017 | LB | 1.40 | 19,623.80 | 1.10 | 15,418.70 | 1.50 | 21,025.50 | 1.50 | 21,025.50 | | 0053 | 807-08-00100 | Structural Metalwork | 1,850 | LUMP | 14,000.00 | 14,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 15,000.00 | 15,000.00 | | 0054 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 80 | LNFT | 110.00 | 8,800.00 | 120.00 | 9,600.00 | 140.00 | 11,200.00 | 200.00 | 16,000.00 | | 0055 | 810-04-00100 | Steel and Concrete Railing | 250 | LNFT | 265.00 | 66,250.00 | 250.00 | 62,500.00 | 210.00 | 52,500.00 | 300.00 | 75,000.00 | | 0056 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,386 | INLF | 3.00 | 4,158.00 | 1.00 | 1,386.00 | 1.00 | 1,386.00 | 5.00 | 6,930.00 | | 0057 | NS-502-01000 | Asphalt Concrete | 498.7 | TON | 170.00 | 84,779.00 | 160.00 | 79,792.00 | 165.00 | 82,285.50 | 250.00 | 124,675.00 | | 0058 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 761 | INLF | 3.00 | 2,283.00 | 1.00 | 761.00 | 1.00 | 761.00 | 10.00 | 7,610.00 | | 0059 | NS-705-00004 | Chain Link Fence With Barbed Wire Extension (4-FOOT HEIGHT) | 48 | LF | 48.00 | 2,304.00 | 35.00 | 1,680.00 | 3.00 | 144.00 | 75.00 | 3,600.00 | | 0060 | NS-705-00004 | Chain Link Fence With Barbed Wire Extension (6-FOOT HEIGHT) | 50 | LF | 68.00 | 3,400.00 | 40.00 | 2,000.00 | 5.00 | 250.00 | 100.00 | 5,000.00 | | 0061 | NS-800-00040 | Concrete Approach Slabs (28' CLR RDWY 60 DEG CROSSING) (W/O ASPHALT) (20' LONG) | 2 | EACH | 16,000.00 | 32,000.00 | 20,000.00 | 40,000.00 | 15,000.00 | 30,000.00 | 22,500.00 | 45,000.00 | | 0062 | NS-800-00040 | Concrete Approach Slabs (28' CLR RDWY 90 DEG CROSSING) (W/O ASPHALT) (10' LONG) | 4 | EACH | 8,000.00 | 32,000.00 | 10,000.00 | 40,000.00 | 10,000.00 | 40,000.00 | 14,000.00 | 56,000.00 | | 0063 | NS-800-00182 | Precast Prestressed Concrete Girder (Type Quad Beam) Class P (HPC) | 237 | LNFT | 120.00 | 28,440.00 | 110.00 | 26,070.00 | 150.00 | 35,550.00 | 200.00 | 47,400.00 | | 0064 | NS-804-00001 | Vibration Monitoring | 50 | EACH | 320.00 | 16,000.00 | 375.00 | 18,750.00 | 450.00 | 22,500.00 | 1,000.00 | 50,000.00 | | 0065 | NS-804-00002 | Construction Site Survey | 1 | LUMP | 6,000.00 | 6,000.00 | 11,690.00 | 11,690.00 | 26,500.00 | 26,500.00 | 55,000.00 | 55,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,875,442.10 | | 1,883,881.20 | | 2,397,219.10 | | 2,409,542.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Shavers-Whittle Construction LLC | - 6 - GILCHRIST CONSTRUCTION CO. LLC | - 7 - WL Bass Construction Inc. | - 8 - COASTAL BRIDGE CO., L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 3 | LUMP | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 65,000.00 | 65,000.00 | 45,000.00 | 45,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 50,000.00 | 50,000.00 | 4,000.00 | 4,000.00 | 45,000.00 | 45,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 60 | SQYD | 15.00 | 900.00 | 63.00 | 3,780.00 | 16.00 | 960.00 | 30.00 | 1,800.00 | | 0004 | 202-02-04000 | Removal of Bridge (STA 100+00, 23.7' X 76.5' CONCRETE SLAB BRIDGE W/ TIMBER PILES) | 1 | EACH | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 60,000.00 | 60,000.00 | 125,000.00 | 125,000.00 | | 0005 | 202-02-04000 | Removal of Bridge (STA 200+00, 28.5' X 56.9' CONCRETE SLAB BRIDGE W/ TIMBER PILES) | 1 | EACH | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 52,500.00 | 52,500.00 | 100,000.00 | 100,000.00 | | 0006 | 202-02-04000 | Removal of Bridge (STA 300+00, 28.5 'X 57.1' CONCRETE SLAB BRIDGE W/ TIMBER PILES) | 1 | EACH | 35,000.00 | 35,000.00 | 25,000.00 | 25,000.00 | 52,500.00 | 52,500.00 | 100,000.00 | 100,000.00 | | 0007 | 202-02-06000 | Removal of Concrete Approach Slabs | 268 | SQYD | 55.00 | 14,740.00 | 54.00 | 14,472.00 | 120.00 | 32,160.00 | 135.00 | 36,180.00 | | 0008 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 90.5 | LNFT | 12.00 | 1,086.00 | 53.00 | 4,796.50 | 12.00 | 1,086.00 | 25.00 | 2,262.50 | | 0009 | 202-02-06090 | Removal of Concrete Revetment | 1 | LUMP | 25,000.00 | 25,000.00 | 31,000.00 | 31,000.00 | 14,000.00 | 14,000.00 | 30,000.00 | 30,000.00 | | 0010 | 202-02-06100 | Removal of Concrete Walks and Drives | 292 | SQYD | 15.00 | 4,380.00 | 32.00 | 9,344.00 | 24.00 | 7,008.00 | 25.00 | 7,300.00 | | 0011 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 1,390.8 | SQYD | 15.00 | 20,862.00 | 10.00 | 13,908.00 | 12.00 | 16,689.60 | 10.00 | 13,908.00 | | 0012 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 62,000.00 | 62,000.00 | 100,000.00 | 100,000.00 | 35,000.00 | 35,000.00 | 35,000.00 | 35,000.00 | | 0013 | 204-02-00100 | Temporary Hay or Straw Bales | 48 | EACH | 11.00 | 528.00 | 50.00 | 2,400.00 | 50.00 | 2,400.00 | 10.00 | 480.00 | | 0014 | 204-03-00100 | Temporary Slope Drains | 40 | LNFT | 26.00 | 1,040.00 | 40.00 | 1,600.00 | 100.00 | 4,000.00 | 25.00 | 1,000.00 | | 0015 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 2 | EACH | 160.00 | 320.00 | 550.00 | 1,100.00 | 500.00 | 1,000.00 | 150.00 | 300.00 | | 0016 | 204-06-00100 | Temporary Silt Fencing | 1,682 | LNFT | 3.50 | 5,887.00 | 3.00 | 5,046.00 | 2.50 | 4,205.00 | 1.69 | 2,842.58 | | 0017 | 302-01-00700 | Class II Base Course (Stone) (CRUSHED) | 416.5 | CUYD | 135.00 | 56,227.50 | 200.00 | 83,300.00 | 135.00 | 56,227.50 | 125.00 | 52,062.50 | | 0018 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 4 | CUYD | 110.00 | 440.00 | 200.00 | 800.00 | 100.00 | 400.00 | 150.00 | 600.00 | | 0019 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 100.00 | 5,000.00 | 90.00 | 4,500.00 | 90.00 | 4,500.00 | 50.00 | 2,500.00 | | 0020 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) (RCP/PP only) | 67 | LNFT | 85.00 | 5,695.00 | 97.00 | 6,499.00 | 125.00 | 8,375.00 | 96.00 | 6,432.00 | | 0021 | 701-05-01080 | Side Drain Pipe (30" RCP/PP/CMP) (RCP/PP only) | 74 | LNFT | 100.00 | 7,400.00 | 115.00 | 8,510.00 | 70.00 | 5,180.00 | 115.00 | 8,510.00 | | 0022 | 702-03-00100 | Catch Basins (CB-01) | 2 | EACH | 3,500.00 | 7,000.00 | 4,200.00 | 8,400.00 | 7,500.00 | 15,000.00 | 4,800.00 | 9,600.00 | | 0023 | 704-03-00100 | Blocked Out Guard Rail | 50 | LNFT | 21.00 | 1,050.00 | 23.00 | 1,150.00 | 40.00 | 2,000.00 | 20.00 | 1,000.00 | | 0024 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 90.00 | 9,000.00 | 68.00 | 6,800.00 | 100.00 | 10,000.00 | 88.00 | 8,800.00 | | 0025 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,600.00 | 10,400.00 | 2,500.00 | 10,000.00 | 3,000.00 | 12,000.00 | 2,400.00 | 9,600.00 | | 0026 | 705-01-00100 | Barbed Wire Fence | 112 | LNFT | 20.00 | 2,240.00 | 28.00 | 3,136.00 | 25.00 | 2,800.00 | 19.50 | 2,184.00 | | 0027 | 706-01-00100 | Concrete Walk (4" Thick) | 87.6 | SQYD | 62.00 | 5,431.20 | 115.00 | 10,074.00 | 189.49 | 16,599.32 | 77.00 | 6,745.20 | | 0028 | 706-02-00200 | Concrete Drive (6" Thick) | 242.4 | SQYD | 75.00 | 18,180.00 | 84.00 | 20,361.60 | 220.41 | 53,427.38 | 81.00 | 19,634.40 | | 0029 | 707-03-00100 | Combination Concrete Curb and Gutter | 74 | LNFT | 50.00 | 3,700.00 | 120.00 | 8,880.00 | 39.00 | 2,886.00 | 50.00 | 3,700.00 | | 0030 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 222 | SQYD | 95.00 | 21,090.00 | 100.00 | 22,200.00 | 80.00 | 17,760.00 | 72.00 | 15,984.00 | | 0031 | 711-04-00100 | Geotextile Fabric | 222 | SQYD | 5.00 | 1,110.00 | 2.00 | 444.00 | 3.00 | 666.00 | 6.00 | 1,332.00 | | 0032 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 273 | SQYD | 125.00 | 34,125.00 | 200.00 | 54,600.00 | 120.00 | 32,760.00 | 85.00 | 23,205.00 | | 0033 | 712-01-00300 | Concrete Cast-in-Place Revetment (6" Thick) | 326 | SQYD | 135.00 | 44,010.00 | 200.00 | 65,200.00 | 130.00 | 42,380.00 | 92.00 | 29,992.00 | | 0034 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 40,000.00 | 40,000.00 | 50,000.00 | 50,000.00 | 15,000.00 | 15,000.00 | 55,000.00 | 55,000.00 | | 0035 | 716-01-00100 | Mulch (Vegetative) | 0.8 | TON | 1,600.00 | 1,280.00 | 1,600.00 | 1,280.00 | 1,500.00 | 1,200.00 | 1,500.00 | 1,200.00 | | 0036 | 717-01-00100 | Seeding | 15 | LB | 11.00 | 165.00 | 58.00 | 870.00 | 50.00 | 750.00 | 10.00 | 150.00 | | 0037 | 718-01-00100 | Fertilizer | 356 | LB | 2.25 | 801.00 | 5.00 | 1,780.00 | 4.00 | 1,424.00 | 2.10 | 747.60 | | 0038 | 726-01-00100 | Bedding Material | 3.2 | CUYD | 65.00 | 208.00 | 400.00 | 1,280.00 | 100.00 | 320.00 | 200.00 | 640.00 | | 0039 | 727-01-00100 | Mobilization | 1 | LUMP | 240,000.00 | 240,000.00 | 240,000.00 | 240,000.00 | 252,000.00 | 252,000.00 | 250,000.00 | 250,000.00 | | 0040 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 90.00 | 1,080.00 | 85.00 | 1,020.00 | 100.00 | 1,200.00 | 88.00 | 1,056.00 | | 0041 | 735-01-00100 | Mailboxes | 2 | EACH | 6.00 | 12.00 | 16.00 | 32.00 | 10.00 | 20.00 | 6.00 | 12.00 | | 0042 | 735-02-00100 | Mailbox Supports (Single) | 2 | EACH | 350.00 | 700.00 | 135.00 | 270.00 | 155.00 | 310.00 | 380.00 | 760.00 | | 0043 | 740-01-00100 | Construction Layout | 1 | LUMP | 80,000.00 | 80,000.00 | 15,000.00 | 15,000.00 | 60,000.00 | 60,000.00 | 45,000.00 | 45,000.00 | | 0044 | 804-01-00300 | Precast Concrete Piles (16") | 2,970 | LNFT | 80.00 | 237,600.00 | 70.00 | 207,900.00 | 85.00 | 252,450.00 | 70.00 | 207,900.00 | | 0045 | 804-01-00600 | Precast Concrete Piles (24") | 440 | LNFT | 163.00 | 71,720.00 | 160.00 | 70,400.00 | 212.75 | 93,610.00 | 128.00 | 56,320.00 | | 0046 | 804-12-00100 | Loading Permanent Piles | 3 | EACH | 500.00 | 1,500.00 | 3,000.00 | 9,000.00 | 10,000.00 | 30,000.00 | 150.00 | 450.00 | | 0047 | 805-01-00700 | Class A Concrete (Bents) | 28.51 | CUYD | 2,000.00 | 57,020.00 | 1,200.00 | 34,212.00 | 1,900.00 | 54,169.00 | 2,000.00 | 57,020.00 | | 0048 | 805-04-00100 | Class AA(M) Concrete | 34.04 | CUYD | 1,900.00 | 64,676.00 | 2,000.00 | 68,080.00 | 2,000.00 | 68,080.00 | 1,900.00 | 64,676.00 | | 0049 | 805-10-02120 | Bridge Superstructure and Substructure (28' Clear Roadway; 60 Degree Crossing) (Cast-in-Place) | 2 | SPAN | 72,500.00 | 145,000.00 | 65,000.00 | 130,000.00 | 50,000.00 | 100,000.00 | 60,000.00 | 120,000.00 | | 0050 | 805-10-02320 | Bridge Superstructure and Substructure (28' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) (20' Span with Sidewalks) | 5 | SPAN | 81,000.00 | 405,000.00 | 75,000.00 | 375,000.00 | 72,000.00 | 360,000.00 | 100,000.00 | 500,000.00 | | 0051 | 805-10-02320 | Bridge Superstructure and Substructure (28' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) (25' Span with Sidewalks) | 1 | SPAN | 100,000.00 | 100,000.00 | 105,000.00 | 105,000.00 | 132,000.00 | 132,000.00 | 125,000.00 | 125,000.00 | | 0052 | 806-01-00100 | Deformed Reinforcing Steel | 14,017 | LB | 1.25 | 17,521.25 | 1.40 | 19,623.80 | 1.20 | 16,820.40 | 0.78 | 10,933.26 | | 0053 | 807-08-00100 | Structural Metalwork | 1,850 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 53,000.00 | 53,000.00 | 10,000.00 | 10,000.00 | | 0054 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 80 | LNFT | 200.00 | 16,000.00 | 180.00 | 14,400.00 | 155.00 | 12,400.00 | 90.00 | 7,200.00 | | 0055 | 810-04-00100 | Steel and Concrete Railing | 250 | LNFT | 250.00 | 62,500.00 | 350.00 | 87,500.00 | 310.00 | 77,500.00 | 240.00 | 60,000.00 | | 0056 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,386 | INLF | 2.00 | 2,772.00 | 4.00 | 5,544.00 | 2.30 | 3,187.80 | 2.00 | 2,772.00 | | 0057 | NS-502-01000 | Asphalt Concrete | 498.7 | TON | 180.00 | 89,766.00 | 230.00 | 114,701.00 | 167.00 | 83,282.90 | 125.00 | 62,337.50 | | 0058 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 761 | INLF | 2.50 | 1,902.50 | 4.00 | 3,044.00 | 5.00 | 3,805.00 | 5.00 | 3,805.00 | | 0059 | NS-705-00004 | Chain Link Fence With Barbed Wire Extension (4-FOOT HEIGHT) | 48 | LF | 20.00 | 960.00 | 50.00 | 2,400.00 | 45.00 | 2,160.00 | 55.00 | 2,640.00 | | 0060 | NS-705-00004 | Chain Link Fence With Barbed Wire Extension (6-FOOT HEIGHT) | 50 | LF | 30.00 | 1,500.00 | 70.00 | 3,500.00 | 65.00 | 3,250.00 | 75.00 | 3,750.00 | | 0061 | NS-800-00040 | Concrete Approach Slabs (28' CLR RDWY 60 DEG CROSSING) (W/O ASPHALT) (20' LONG) | 2 | EACH | 30,000.00 | 60,000.00 | 27,500.00 | 55,000.00 | 25,000.00 | 50,000.00 | 30,000.00 | 60,000.00 | | 0062 | NS-800-00040 | Concrete Approach Slabs (28' CLR RDWY 90 DEG CROSSING) (W/O ASPHALT) (10' LONG) | 4 | EACH | 20,000.00 | 80,000.00 | 17,500.00 | 70,000.00 | 19,000.00 | 76,000.00 | 12,000.00 | 48,000.00 | | 0063 | NS-800-00182 | Precast Prestressed Concrete Girder (Type Quad Beam) Class P (HPC) | 237 | LNFT | 200.00 | 47,400.00 | 120.00 | 28,440.00 | 150.00 | 35,550.00 | 150.00 | 35,550.00 | | 0064 | NS-804-00001 | Vibration Monitoring | 50 | EACH | 850.00 | 42,500.00 | 600.00 | 30,000.00 | 25.00 | 1,250.00 | 550.00 | 27,500.00 | | 0065 | NS-804-00002 | Construction Site Survey | 1 | LUMP | 50,000.00 | 50,000.00 | 57,000.00 | 57,000.00 | 55,000.00 | 55,000.00 | 50,000.00 | 50,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,443,425.45 | | 2,499,577.90 | | 2,531,208.90 | | 2,618,373.54 |
|