Proposal:H.009461.6
Parish:Iberville, St. Martin
Routes:I-10
Description:I-10 CLEAN, PAINT AND MISCELLANEOUS REPAIRS
Type Construction:CLEANING AND PAINTING, BRIDGE REPAIRS, AND RELATED WORK.
Estimated Construction Cost:$29,724,730.00
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$5,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 59114 | SOUTHERN ROAD & BRIDGE, LLC | $18,464,550.00 | 400.00 | $20,464,550.00 |
| 2 | 47645 | Olympus Painting Contractors, Inc. | $21,106,047.13 | 375.00 | $22,981,047.13 |
| 3 | BLA01 | Blastech Enterprises Inc. | $21,168,546.00 | 400.00 | $23,168,546.00 |
| 4 | 55663 | Intech Contracting, LLC | $23,655,087.00 | 275.00 | $25,030,087.00 |
| 5 | 37457 | ROYAL BRIDGE, INC. | $26,623,896.90 | 740.00 | $30,323,896.90 |
| 6 | 39452 | M&J CONST COMPANY OF PINELLAS COUNTY INC | $27,006,565.60 | 880.00 | $31,406,565.60 |
| 7 | 28182 | Liberty Maintenance, Inc. | $30,649,465.25 | 420.00 | $32,749,465.25 |
| 8 | 24429 | Abhe & Svoboda, Inc. | $40,577,770.00 | 725.00 | $44,202,770.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - SOUTHERN ROAD & BRIDGE, LLC | - 2 - Olympus Painting Contractors, Inc. | - 3 - Blastech Enterprises Inc. | - 4 - Intech Contracting, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-00050 | Removal of Bridge Components (Steel Cross Frames) (GR 3) | 1 | LUMP | 5,000.00 | 5,000.00 | 6,125.00 | 6,125.00 | 5,000.00 | 5,000.00 | 1,575.00 | 1,575.00 | | 0002 | 202-02-00050 | Removal of Bridge Components (Steel Grid Deck) (DR 3) | 1 | LUMP | 5,000.00 | 5,000.00 | 1,715.00 | 1,715.00 | 1,400.00 | 1,400.00 | 1,575.00 | 1,575.00 | | 0003 | 202-02-00050 | Removal of Debris (Bridge Substructure) | 1 | LUMP | 500,000.00 | 500,000.00 | 52,675.00 | 52,675.00 | 43,000.00 | 43,000.00 | 300,000.00 | 300,000.00 | | 0004 | 202-02-04510 | Removal of Bridge Deck (Hydro Demolition) (DR 1) | 5,854 | SFIN | 40.00 | 234,160.00 | 116.37 | 681,229.98 | 115.00 | 673,210.00 | 55.00 | 321,970.00 | | 0005 | 202-02-04560 | Removal of Bridge Joint (Joint Sealants) | 4,147 | LNFT | 10.00 | 41,470.00 | 24.50 | 101,601.50 | 20.00 | 82,940.00 | 28.00 | 116,116.00 | | 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 500,000.00 | 500,000.00 | 650,000.00 | 650,000.00 | 300,000.00 | 300,000.00 | 750,000.00 | 750,000.00 | | 0007 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 | 60,000.00 | 60,000.00 | 15,000.00 | 15,000.00 | | 0008 | 727-01-00100 | Mobilization | 1 | LUMP | 1,485,000.00 | 1,485,000.00 | 957,500.00 | 957,500.00 | 1,800,000.00 | 1,800,000.00 | 2,125,000.00 | 2,125,000.00 | | 0009 | 808-01-00100 | Steel Grid Flooring (Heavy Duty) (DR 3) | 45 | SQFT | 500.00 | 22,500.00 | 483.87 | 21,774.15 | 395.00 | 17,775.00 | 750.00 | 33,750.00 | | 0010 | 808-01-00300 | Steel Grid Flooring (MR 3) | 45 | SQFT | 500.00 | 22,500.00 | 116.37 | 5,236.65 | 95.00 | 4,275.00 | 480.00 | 21,600.00 | | 0011 | 811-01-00100 | Cleaning and Painting (Bridge "A" - Span 13) | 1 | LUMP | 448,000.00 | 448,000.00 | 613,845.54 | 613,845.54 | 600,000.00 | 600,000.00 | 450,000.00 | 450,000.00 | | 0012 | 811-01-00100 | Cleaning and Painting (Bridge "A" - Spans 272-274) | 1 | LUMP | 1,080,000.00 | 1,080,000.00 | 921,945.96 | 921,945.96 | 800,000.00 | 800,000.00 | 750,000.00 | 750,000.00 | | 0013 | 811-01-00100 | Cleaning and Painting (Bridge "B" - Span 13) | 1 | LUMP | 448,000.00 | 448,000.00 | 613,845.54 | 613,845.54 | 600,000.00 | 600,000.00 | 450,000.00 | 450,000.00 | | 0014 | 811-01-00100 | Cleaning and Painting (Bridge "B" - Spans 273-275) | 1 | LUMP | 1,080,000.00 | 1,080,000.00 | 921,945.96 | 921,945.96 | 800,000.00 | 800,000.00 | 750,000.00 | 750,000.00 | | 0015 | 811-01-00100 | Cleaning and Painting (Bridge "C" - Spans 3-8) | 1 | LUMP | 3,122,000.00 | 3,122,000.00 | 3,503,103.70 | 3,503,103.70 | 4,000,000.00 | 4,000,000.00 | 3,750,000.00 | 3,750,000.00 | | 0016 | 811-01-00100 | Cleaning and Painting (Bridge "H" - Spans 1-9) | 1 | LUMP | 4,500,000.00 | 4,500,000.00 | 7,031,645.50 | 7,031,645.50 | 7,000,000.00 | 7,000,000.00 | 8,750,000.00 | 8,750,000.00 | | 0017 | 811-01-00100 | Cleaning and Painting (Bridge "I" - Span 578) | 1 | LUMP | 228,000.00 | 228,000.00 | 361,230.28 | 361,230.28 | 450,000.00 | 450,000.00 | 280,000.00 | 280,000.00 | | 0018 | 811-01-00100 | Cleaning and Painting (Bridge "J" - Span 578) | 1 | LUMP | 228,000.00 | 228,000.00 | 361,230.28 | 361,230.28 | 450,000.00 | 450,000.00 | 280,000.00 | 280,000.00 | | 0019 | 811-01-00100 | Cleaning and Painting (Bridge "K") | 1 | LUMP | 100,000.00 | 100,000.00 | 240,000.00 | 240,000.00 | 75,000.00 | 75,000.00 | 100,000.00 | 100,000.00 | | 0020 | 811-01-00100 | Cleaning and Painting (Bridge "P" - Spans 7 & 12) | 1 | LUMP | 150,000.00 | 150,000.00 | 288,175.00 | 288,175.00 | 200,000.00 | 200,000.00 | 150,000.00 | 150,000.00 | | 0021 | 811-01-00100 | Cleaning and Painting (Bridge "Q" - Spans 7 & 12) | 1 | LUMP | 150,000.00 | 150,000.00 | 288,175.00 | 288,175.00 | 200,000.00 | 200,000.00 | 150,000.00 | 150,000.00 | | 0022 | 811-01-00100 | Cleaning and Painting (Bridge "R") | 1 | LUMP | 78,000.00 | 78,000.00 | 149,891.70 | 149,891.70 | 300,000.00 | 300,000.00 | 100,000.00 | 100,000.00 | | 0023 | 811-01-00100 | Cleaning and Painting (Bridge "S") | 1 | LUMP | 78,000.00 | 78,000.00 | 149,597.70 | 149,597.70 | 300,000.00 | 300,000.00 | 100,000.00 | 100,000.00 | | 0024 | 815-03-00200 | Joint Seal (Preformed Silicone) (JR 2) | 3,556 | LNFT | 75.00 | 266,700.00 | 44.10 | 156,819.60 | 36.00 | 128,016.00 | 31.00 | 110,236.00 | | 0025 | 815-03-00300 | Joint Seal (Poured) (JR 3 & JR 4) | 591 | LNFT | 50.00 | 29,550.00 | 46.55 | 27,511.05 | 38.00 | 22,458.00 | 32.50 | 19,207.50 | | 0026 | 816-01-00300 | Bridge Deck Drainage System (JR 5) | 1 | LUMP | 355,000.00 | 355,000.00 | 269,500.00 | 269,500.00 | 220,000.00 | 220,000.00 | 325,000.00 | 325,000.00 | | 0027 | 822-09-00100 | Electrical System (MR 2) | 1 | LUMP | 150,000.00 | 150,000.00 | 8,575.00 | 8,575.00 | 7,000.00 | 7,000.00 | 5,000.00 | 5,000.00 | | 0028 | 822-09-00100 | Electrical System (MR 4) | 1 | LUMP | 50,000.00 | 50,000.00 | 11,637.50 | 11,637.50 | 9,500.00 | 9,500.00 | 2,500.00 | 2,500.00 | | 0029 | 830-01-00100 | Bridge Superstructure Repair (BR 1) | 29 | EACH | 1,250.00 | 36,250.00 | 4,287.50 | 124,337.50 | 3,500.00 | 101,500.00 | 2,250.00 | 65,250.00 | | 0030 | 830-01-00100 | Bridge Superstructure Repair (BR 2) | 89 | EACH | 650.00 | 57,850.00 | 514.50 | 45,790.50 | 420.00 | 37,380.00 | 400.00 | 35,600.00 | | 0031 | 830-01-00100 | Bridge Superstructure Repair (BR 3) | 6 | EACH | 3,000.00 | 18,000.00 | 7,962.50 | 47,775.00 | 6,500.00 | 39,000.00 | 4,250.00 | 25,500.00 | | 0032 | 830-01-00100 | Bridge Superstructure Repair (DR 2) | 4,221 | EACH | 20.00 | 84,420.00 | 17.15 | 72,390.15 | 17.00 | 71,757.00 | 12.50 | 52,762.50 | | 0033 | 830-01-00100 | Bridge Superstructure Repair (Girder Heat Straightening) (GR 2) | 2 | EACH | 20,000.00 | 40,000.00 | 30,625.00 | 61,250.00 | 2,500.00 | 5,000.00 | 16,000.00 | 32,000.00 | | 0034 | 830-01-00100 | Bridge Superstructure Repair (GR 4) | 4 | EACH | 2,500.00 | 10,000.00 | 5,267.50 | 21,070.00 | 4,300.00 | 17,200.00 | 2,250.00 | 9,000.00 | | 0035 | 830-01-00100 | Bridge Superstructure Repair (MR 5) | 5 | EACH | 10,000.00 | 50,000.00 | 9,065.00 | 45,325.00 | 7,400.00 | 37,000.00 | 6,700.00 | 33,500.00 | | 0036 | 830-01-00100 | Bridge Superstructure Repair (Replacement Cross Frame) (GR 3) | 5 | EACH | 8,000.00 | 40,000.00 | 8,330.00 | 41,650.00 | 6,800.00 | 34,000.00 | 5,000.00 | 25,000.00 | | 0037 | 830-02-00100 | Bridge Substructure Repair (MR 6) | 44 | EACH | 28,500.00 | 1,254,000.00 | 17,150.00 | 754,600.00 | 16,000.00 | 704,000.00 | 42,500.00 | 1,870,000.00 | | 0038 | 830-07-00100 | Structural Concrete Patching (CR 1) | 6 | SQFT | 1,000.00 | 6,000.00 | 1,225.00 | 7,350.00 | 1,000.00 | 6,000.00 | 370.00 | 2,220.00 | | 0039 | 830-07-00100 | Structural Concrete Patching (DR 1) | 4,683 | SQFT | 100.00 | 468,300.00 | 159.25 | 745,767.75 | 90.00 | 421,470.00 | 80.00 | 374,640.00 | | 0040 | 830-07-00100 | Structural Concrete Patching (GR 1) | 607 | SQFT | 500.00 | 303,500.00 | 153.12 | 92,943.84 | 125.00 | 75,875.00 | 370.00 | 224,590.00 | | 0041 | 830-07-00100 | Structural Concrete Patching (MR 1) | 286 | SQFT | 500.00 | 143,000.00 | 153.12 | 43,792.32 | 125.00 | 35,750.00 | 370.00 | 105,820.00 | | 0042 | 830-09-00100 | Structure Jacking (BR 3) | 1 | LUMP | 75,000.00 | 75,000.00 | 36,750.00 | 36,750.00 | 30,000.00 | 30,000.00 | 25,000.00 | 25,000.00 | | 0043 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation (RR 1) | 238 | LNFT | 600.00 | 142,800.00 | 251.12 | 59,766.56 | 205.00 | 48,790.00 | 675.00 | 160,650.00 | | 0044 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation (RR 2) | 213 | LNFT | 1,000.00 | 213,000.00 | 1,568.00 | 333,984.00 | 1,280.00 | 272,640.00 | 1,250.00 | 266,250.00 | | 0045 | NS-830-01000 | Bridge Deck Joint Repair (One Side of Joint) (JR 6) | 43 | LNFT | 500.00 | 21,500.00 | 563.50 | 24,230.50 | 460.00 | 19,780.00 | 385.00 | 16,555.00 | | 0046 | NS-830-01100 | Bridge Deck Joint Repair (Both Sides of Joint) (JR 1) | 120 | LNFT | 800.00 | 96,000.00 | 526.75 | 63,210.00 | 430.00 | 51,600.00 | 760.00 | 91,200.00 | | 0047 | NS-830-01200 | Carbon Fiber Reinforced Polymer Repairs (CR 2) | 66 | SQFT | 425.00 | 28,050.00 | 189.87 | 12,531.42 | 155.00 | 10,230.00 | 470.00 | 31,020.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 18,464,550.00 | | 21,106,047.13 | | 21,168,546.00 | | 23,655,087.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - ROYAL BRIDGE, INC. | - 6 - M&J CONST COMPANY OF PINELLAS COUNTY INC | - 7 - Liberty Maintenance, Inc. | - 8 - Abhe & Svoboda, Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-00050 | Removal of Bridge Components (Steel Cross Frames) (GR 3) | 1 | LUMP | 1,732.50 | 1,732.50 | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 10,290.00 | 10,290.00 | | 0002 | 202-02-00050 | Removal of Bridge Components (Steel Grid Deck) (DR 3) | 1 | LUMP | 1,732.50 | 1,732.50 | 1,680.00 | 1,680.00 | 1,680.00 | 1,680.00 | 2,880.00 | 2,880.00 | | 0003 | 202-02-00050 | Removal of Debris (Bridge Substructure) | 1 | LUMP | 427,350.00 | 427,350.00 | 51,600.00 | 51,600.00 | 51,600.00 | 51,600.00 | 88,500.00 | 88,500.00 | | 0004 | 202-02-04510 | Removal of Bridge Deck (Hydro Demolition) (DR 1) | 5,854 | SFIN | 60.50 | 354,167.00 | 114.00 | 667,356.00 | 110.00 | 643,940.00 | 175.00 | 1,024,450.00 | | 0005 | 202-02-04560 | Removal of Bridge Joint (Joint Sealants) | 4,147 | LNFT | 1.10 | 4,561.70 | 24.00 | 99,528.00 | 23.00 | 95,381.00 | 30.00 | 124,410.00 | | 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 156,000.00 | 156,000.00 | 527,186.00 | 527,186.00 | 215,000.00 | 215,000.00 | 205,250.00 | 205,250.00 | | 0007 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 20,000.00 | 20,000.00 | 30,000.00 | 30,000.00 | 100,000.00 | 100,000.00 | 160,000.00 | 160,000.00 | | 0008 | 727-01-00100 | Mobilization | 1 | LUMP | 2,297,000.00 | 2,297,000.00 | 2,361,900.00 | 2,361,900.00 | 3,000,000.00 | 3,000,000.00 | 4,000,000.00 | 4,000,000.00 | | 0009 | 808-01-00100 | Steel Grid Flooring (Heavy Duty) (DR 3) | 45 | SQFT | 753.50 | 33,907.50 | 474.00 | 21,330.00 | 474.00 | 21,330.00 | 650.00 | 29,250.00 | | 0010 | 808-01-00300 | Steel Grid Flooring (MR 3) | 45 | SQFT | 522.50 | 23,512.50 | 114.00 | 5,130.00 | 114.00 | 5,130.00 | 150.00 | 6,750.00 | | 0011 | 811-01-00100 | Cleaning and Painting (Bridge "A" - Span 13) | 1 | LUMP | 525,000.00 | 525,000.00 | 834,820.00 | 834,820.00 | 1,069,000.00 | 1,069,000.00 | 900,000.00 | 900,000.00 | | 0012 | 811-01-00100 | Cleaning and Painting (Bridge "A" - Spans 272-274) | 1 | LUMP | 935,000.00 | 935,000.00 | 1,122,800.00 | 1,122,800.00 | 1,384,000.00 | 1,384,000.00 | 1,325,000.00 | 1,325,000.00 | | 0013 | 811-01-00100 | Cleaning and Painting (Bridge "B" - Span 13) | 1 | LUMP | 525,000.00 | 525,000.00 | 834,820.00 | 834,820.00 | 1,069,000.00 | 1,069,000.00 | 900,000.00 | 900,000.00 | | 0014 | 811-01-00100 | Cleaning and Painting (Bridge "B" - Spans 273-275) | 1 | LUMP | 935,000.00 | 935,000.00 | 1,122,800.00 | 1,122,800.00 | 1,384,000.00 | 1,384,000.00 | 1,328,000.00 | 1,328,000.00 | | 0015 | 811-01-00100 | Cleaning and Painting (Bridge "C" - Spans 3-8) | 1 | LUMP | 4,450,000.00 | 4,450,000.00 | 5,090,000.00 | 5,090,000.00 | 6,060,000.00 | 6,060,000.00 | 7,250,000.00 | 7,250,000.00 | | 0016 | 811-01-00100 | Cleaning and Painting (Bridge "H" - Spans 1-9) | 1 | LUMP | 10,000,000.00 | 10,000,000.00 | 9,719,570.00 | 9,719,570.00 | 11,300,000.00 | 11,300,000.00 | 16,250,000.00 | 16,250,000.00 | | 0017 | 811-01-00100 | Cleaning and Painting (Bridge "I" - Span 578) | 1 | LUMP | 315,000.00 | 315,000.00 | 415,000.00 | 415,000.00 | 455,000.00 | 455,000.00 | 525,000.00 | 525,000.00 | | 0018 | 811-01-00100 | Cleaning and Painting (Bridge "J" - Span 578) | 1 | LUMP | 315,000.00 | 315,000.00 | 415,000.00 | 415,000.00 | 455,000.00 | 455,000.00 | 525,000.00 | 525,000.00 | | 0019 | 811-01-00100 | Cleaning and Painting (Bridge "K") | 1 | LUMP | 20,000.00 | 20,000.00 | 200,000.00 | 200,000.00 | 130,000.00 | 130,000.00 | 400,497.00 | 400,497.00 | | 0020 | 811-01-00100 | Cleaning and Painting (Bridge "P" - Spans 7 & 12) | 1 | LUMP | 185,000.00 | 185,000.00 | 182,000.00 | 182,000.00 | 140,000.00 | 140,000.00 | 480,000.00 | 480,000.00 | | 0021 | 811-01-00100 | Cleaning and Painting (Bridge "Q" - Spans 7 & 12) | 1 | LUMP | 185,000.00 | 185,000.00 | 182,000.00 | 182,000.00 | 140,000.00 | 140,000.00 | 480,000.00 | 480,000.00 | | 0022 | 811-01-00100 | Cleaning and Painting (Bridge "R") | 1 | LUMP | 123,000.00 | 123,000.00 | 190,000.00 | 190,000.00 | 118,000.00 | 118,000.00 | 167,000.00 | 167,000.00 | | 0023 | 811-01-00100 | Cleaning and Painting (Bridge "S") | 1 | LUMP | 123,000.00 | 123,000.00 | 190,000.00 | 190,000.00 | 118,000.00 | 118,000.00 | 167,000.00 | 167,000.00 | | 0024 | 815-03-00200 | Joint Seal (Preformed Silicone) (JR 2) | 3,556 | LNFT | 73.70 | 262,077.20 | 43.20 | 153,619.20 | 44.00 | 156,464.00 | 50.00 | 177,800.00 | | 0025 | 815-03-00300 | Joint Seal (Poured) (JR 3 & JR 4) | 591 | LNFT | 48.40 | 28,604.40 | 45.60 | 26,949.60 | 46.00 | 27,186.00 | 50.00 | 29,550.00 | | 0026 | 816-01-00300 | Bridge Deck Drainage System (JR 5) | 1 | LUMP | 364,100.00 | 364,100.00 | 264,000.00 | 264,000.00 | 253,000.00 | 253,000.00 | 400,000.00 | 400,000.00 | | 0027 | 822-09-00100 | Electrical System (MR 2) | 1 | LUMP | 130,000.00 | 130,000.00 | 8,400.00 | 8,400.00 | 8,050.00 | 8,050.00 | 10,000.00 | 10,000.00 | | 0028 | 822-09-00100 | Electrical System (MR 4) | 1 | LUMP | 130,000.00 | 130,000.00 | 11,400.00 | 11,400.00 | 10,925.00 | 10,925.00 | 15,000.00 | 15,000.00 | | 0029 | 830-01-00100 | Bridge Superstructure Repair (BR 1) | 29 | EACH | 2,035.00 | 59,015.00 | 4,200.00 | 121,800.00 | 4,200.00 | 121,800.00 | 5,000.00 | 145,000.00 | | 0030 | 830-01-00100 | Bridge Superstructure Repair (BR 2) | 89 | EACH | 561.00 | 49,929.00 | 504.00 | 44,856.00 | 504.00 | 44,856.00 | 600.00 | 53,400.00 | | 0031 | 830-01-00100 | Bridge Superstructure Repair (BR 3) | 6 | EACH | 4,620.00 | 27,720.00 | 7,800.00 | 46,800.00 | 7,800.00 | 46,800.00 | 8,000.00 | 48,000.00 | | 0032 | 830-01-00100 | Bridge Superstructure Repair (DR 2) | 4,221 | EACH | 17.60 | 74,289.60 | 16.80 | 70,912.80 | 17.00 | 71,757.00 | 18.00 | 75,978.00 | | 0033 | 830-01-00100 | Bridge Superstructure Repair (Girder Heat Straightening) (GR 2) | 2 | EACH | 17,325.00 | 34,650.00 | 30,000.00 | 60,000.00 | 30,000.00 | 60,000.00 | 40,000.00 | 80,000.00 | | 0034 | 830-01-00100 | Bridge Superstructure Repair (GR 4) | 4 | EACH | 2,310.00 | 9,240.00 | 5,160.00 | 20,640.00 | 5,160.00 | 20,640.00 | 7,250.00 | 29,000.00 | | 0035 | 830-01-00100 | Bridge Superstructure Repair (MR 5) | 5 | EACH | 7,287.50 | 36,437.50 | 8,880.00 | 44,400.00 | 8,880.00 | 44,400.00 | 10,000.00 | 50,000.00 | | 0036 | 830-01-00100 | Bridge Superstructure Repair (Replacement Cross Frame) (GR 3) | 5 | EACH | 5,445.00 | 27,225.00 | 8,160.00 | 40,800.00 | 8,160.00 | 40,800.00 | 14,000.00 | 70,000.00 | | 0037 | 830-02-00100 | Bridge Substructure Repair (MR 6) | 44 | EACH | 46,750.00 | 2,057,000.00 | 16,800.00 | 739,200.00 | 16,800.00 | 739,200.00 | 25,000.00 | 1,100,000.00 | | 0038 | 830-07-00100 | Structural Concrete Patching (CR 1) | 6 | SQFT | 401.50 | 2,409.00 | 1,200.00 | 7,200.00 | 1,150.00 | 6,900.00 | 1,500.00 | 9,000.00 | | 0039 | 830-07-00100 | Structural Concrete Patching (DR 1) | 4,683 | SQFT | 82.50 | 386,347.50 | 90.00 | 421,470.00 | 86.25 | 403,908.75 | 230.00 | 1,077,090.00 | | 0040 | 830-07-00100 | Structural Concrete Patching (GR 1) | 607 | SQFT | 401.50 | 243,710.50 | 150.00 | 91,050.00 | 144.00 | 87,408.00 | 200.00 | 121,400.00 | | 0041 | 830-07-00100 | Structural Concrete Patching (MR 1) | 286 | SQFT | 401.50 | 114,829.00 | 150.00 | 42,900.00 | 144.00 | 41,184.00 | 200.00 | 57,200.00 | | 0042 | 830-09-00100 | Structure Jacking (BR 3) | 1 | LUMP | 28,050.00 | 28,050.00 | 36,000.00 | 36,000.00 | 36,000.00 | 36,000.00 | 60,000.00 | 60,000.00 | | 0043 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation (RR 1) | 238 | LNFT | 715.00 | 170,170.00 | 246.00 | 58,548.00 | 235.75 | 56,108.50 | 300.00 | 71,400.00 | | 0044 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation (RR 2) | 213 | LNFT | 1,320.00 | 281,160.00 | 1,536.00 | 327,168.00 | 1,472.00 | 313,536.00 | 2,000.00 | 426,000.00 | | 0045 | NS-830-01000 | Bridge Deck Joint Repair (One Side of Joint) (JR 6) | 43 | LNFT | 423.50 | 18,210.50 | 552.00 | 23,736.00 | 529.00 | 22,747.00 | 725.00 | 31,175.00 | | 0046 | NS-830-01100 | Bridge Deck Joint Repair (Both Sides of Joint) (JR 1) | 120 | LNFT | 825.00 | 99,000.00 | 516.00 | 61,920.00 | 516.00 | 61,920.00 | 625.00 | 75,000.00 | | 0047 | NS-830-01200 | Carbon Fiber Reinforced Polymer Repairs (CR 2) | 66 | SQFT | 511.50 | 33,759.00 | 186.00 | 12,276.00 | 179.00 | 11,814.00 | 250.00 | 16,500.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 26,623,896.90 | | 27,006,565.60 | | 30,649,465.25 | | 40,577,770.00 |
|