Search


Bid Tabulations for the Letting of 6/14/2017 LA DOTD Headquarters

Proposal:H.009143.6
Parish:St. Martin
Routes:LA 31 & LA 92-1
Description:LA 31 & LA 92-1: ROUNDABOUT
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE (SOIL CEMENT, STONE), LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, ASPHALTIC SURFACE TREATMENT, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$2,468,014.34
Rank License BidderConstruction Bid
133663Glenn Lege Construction Inc$3,067,349.49
255950Brown Industrial Construction, LLC$3,248,818.84
352306Cecil Perry Improvements Llc$3,252,491.87
439462JB JAMES CONSTRUCTION LLC$4,793,116.11


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Glenn Lege Construction Inc
- 2 -
Brown Industrial Construction, LLC
- 3 -
Cecil Perry Improvements Llc
- 4 -
JB JAMES CONSTRUCTION LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 7     LUMP15,600.0015,600.00110,000.00110,000.0036,000.0036,000.00575,000.00575,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP5,200.005,200.004,000.004,000.001,500.001,500.001,000.001,000.00
0003202-02-02000Removal of Asphalt Drives 217     SQYD12.352,679.9514.003,038.005.251,139.2535.007,595.00
0004202-02-06020Removal of Concrete Box Culverts 2' x 2' RCB1     EACH11,352.9011,352.902,400.002,400.002,400.002,400.007,100.007,100.00
0005202-02-06040Removal of Concrete Box Headwall 12" Headwall2     EACH1,300.002,600.00600.001,200.00984.001,968.005,200.0010,400.00
0006202-02-06100Removal of Concrete Walks and Drives 130     SQYD17.552,281.5020.002,600.008.001,040.0069.008,970.00
0007202-02-32100Removal of Pipe (Cross Drain) 26" CPEPDW & 42" CMP171     LNFT131.3022,452.3025.004,275.0035.005,985.0041.007,011.00
0008202-02-32120Removal of Pipe (Side Drain) 18" rcp & 22" steel67     LNFT19.501,306.5025.001,675.0022.301,494.10104.006,968.00
0009202-02-32120Removal of Pipe (Side Drain) 36" cmp91     LNFT19.501,774.5030.002,730.0022.002,002.0075.006,825.00
0010202-02-32180Removal of Pipe Headwalls 2     EACH650.001,300.00800.001,600.001,190.002,380.004,000.008,000.00
0011202-02-32500Removal of Portland Cement Concrete Pavement Removes Composite Pavement1,653.3   SQYD18.8531,164.7116.0026,452.809.0014,879.7023.0038,025.90
0012202-02-38500Removal of Surfacing and Stabilized Base 9,780.6   SQYD11.00107,586.607.0068,464.207.0068,464.209.0088,025.40
0013202-02-40100Removal of Traffic Signal Equipment Includes signals, wires, poles, and pole foundations1     LUMP17,729.4017,729.4014,000.0014,000.005,100.005,100.007,200.007,200.00
0014203-05-00100Excavation and Embankment Measured by Lump Sum1     LUMP234,000.00234,000.00320,000.00320,000.00289,000.00289,000.00361,500.00361,500.00
0015203-07-00100Borrow (Vehicular Measurement) To be used to dress insufficient ditch slopes50     CUYD22.751,137.5064.003,200.0041.002,050.00123.006,150.00
0016204-02-00100Temporary Hay or Straw Bales 50     EACH18.85942.5012.00600.0046.002,300.0025.001,250.00
0017204-05-00100Temporary Sediment Check Dams (Hay) 14     EACH55.25773.50150.002,100.00255.003,570.00150.002,100.00
0018204-05-00200Temporary Sediment Check Dams (Stone) 8     EACH100.00800.00800.006,400.00500.004,000.00850.006,800.00
0019204-06-00100Temporary Silt Fencing 2,316.76  LNFT2.505,791.902.004,633.523.658,456.1714.0032,434.64
0020302-02-05020Class II Base Course (10" Thick) (Soil Cement) 583.6   SQYD20.8012,138.8828.0016,340.8027.5016,049.0039.0022,760.40
0021302-02-05100Class II Base Course (10" Thick) (Stone) 8,504.2   SQYD37.05315,080.6135.00297,647.0032.50276,386.5044.00374,184.80
0022303-01-00300In-Place Cement Stabilized Base Course (10" Thick) 3,653     SQYD10.4037,991.2011.0040,183.0014.2552,055.2521.0076,713.00
0023304-04-00400Lime Treatment (Type D) (12" Thick) 9,127     SQYD7.0163,980.270.504,563.506.6560,694.5517.00155,159.00
0024305-01-04020Subgrade Layer (12" Thick) (Treated) 10,313     SQYD19.01196,050.1316.50170,164.5023.00237,199.0034.00350,642.00
0025401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 58.8   CUYD91.005,350.80119.006,997.20165.009,702.00282.0016,581.60
0026402-01-00100Traffic Maintenance Aggregate (Vehicular Measurement) 80     CUYD91.007,280.00100.008,000.0099.507,960.00153.0012,240.00
0027502-01-00100Superpave Asphaltic Concrete 1,421.8   TON94.90134,928.82135.00191,943.0096.50137,203.7095.00135,071.00
0028502-01-00200Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 19.5   TON120.002,340.00250.004,875.00122.352,385.83120.002,340.00
0029507-01-00100Asphaltic Material (CRS-2P Emulsion) 2,880     GAL3.139,014.404.0011,520.002.507,200.002.507,200.00
0030507-02-00200Aggregate (S2) 4,235     SQYD4.5419,226.901.908,046.503.6015,246.003.5014,822.50
0031507-02-00300Aggregate (S3) 4,235     SQYD4.2618,041.101.656,987.753.4014,399.003.3013,975.50
0032509-01-00100Cold Planing Asphaltic Pavement 6,528     SQYD11.7076,377.606.0039,168.003.8024,806.4012.0078,336.00
0033509-02-00100Contractor Retained Reclaimed Asphaltic Pavement -849     CUYD0.01-8.490.01-8.490.01-8.490.01-8.49
0034510-01-00260Pavement Patching (16 inch Minimum Thickness) 131.8   SQYD115.7715,258.49110.0014,498.00216.6028,547.88115.0015,157.00
0035601-01-00100Portland Cement Concrete Pavement (8" Thick) 6,143.9   SQYD96.85595,061.2974.00454,648.6082.50506,871.7585.00522,231.50
0036601-01-10000Portland Cement Concrete Pavement (Colored)(inch Thick) Color - Solomon Color #413 - Terra Cotta or Similar 11" Thick768.5   SQYD143.00109,895.50142.00109,127.00148.00113,738.00127.0097,599.50
0037601-01-10000Portland Cement Concrete Pavement (Colored)(inch Thick) Terra Cota 11" Thick472.6   SQYD143.0067,581.80142.0067,109.20135.0063,801.00160.0075,616.00
0038601-04-00100Portland Cement Concrete Pavement Coring 10     EACH650.006,500.00145.001,450.0084.50845.00100.001,000.00
0039701-02-01000Cross Drain Pipe Arch (24" Equiv. RCPA) 112     LNFT170.3019,073.60122.0013,664.00137.5015,400.00257.0028,784.00
0040701-02-01020Cross Drain Pipe Arch (30" Equiv. RCPA) 220     LNFT187.0141,142.20145.0031,900.00150.5033,110.00141.0031,020.00
0041701-02-01040Cross Drain Pipe Arch (36" Equiv. RCPA) 320     LNFT194.3562,192.00148.0047,360.00169.3054,176.00153.0048,960.00
0042701-02-01080Cross Drain Pipe Arch (48" Equiv. RCPA) 104     LNFT234.9824,437.92241.0025,064.00250.5026,052.00247.0025,688.00
0043701-06-01040Side Drain Pipe Arch (24" Equiv. RCPA/CMPA) 68     LNFT134.559,149.4090.006,120.0099.006,732.00173.0011,764.00
0044701-06-01060Side Drain Pipe Arch (30" Equiv. RCPA/CMPA) 44     LNFT141.516,226.4497.004,268.00105.504,642.00297.0013,068.00
0045701-06-01080Side Drain Pipe Arch (36" Equiv. RCPA/CMPA) 44     LNFT173.557,636.20116.005,104.00122.505,390.00241.0010,604.00
0046702-03-00500Catch Basins (CB-06) 3     EACH5,569.0016,707.005,500.0016,500.006,815.0020,445.008,400.0025,200.00
0047703-01-00100Shoulder Underdrain Systems 3,190     LNFT29.2593,307.5015.5049,445.0028.0089,320.0022.0070,180.00
0048703-02-00100Shoulder Outlet Underdrains 8     EACH286.002,288.00900.007,200.00515.004,120.001,900.0015,200.00
0049706-02-00200Concrete Drive (6" Thick) 402.3   SQYD83.0033,390.9065.0026,149.5068.0027,356.40160.0064,368.00
0050707-03-00100Combination Concrete Curb and Gutter 4,051.2   LNFT30.00121,536.0032.00129,638.4025.00101,280.0045.00182,304.00
0051708-01-00100Right-of-Way Monument 9     EACH325.002,925.00240.002,160.00476.004,284.0037.00333.00
0052708-02-00100Right-of-Way Monument Witness Post 9     EACH325.002,925.00240.002,160.0082.50742.509.0081.00
0053712-02-00100Sacked Concrete Revetment 36     SQYD145.005,220.00400.0014,400.00248.008,928.00190.006,840.00
0054712-04-00100Flexible Revetment 68     SQYD75.005,100.00450.0030,600.00110.007,480.0088.005,984.00
0055713-01-00100Temporary Signs and Barricades 1     LUMP35,000.0035,000.0020,000.0020,000.0055,000.0055,000.0060,000.0060,000.00
0056713-02-00300Temporary Pavement Markings (8" Width) 20,176     LNFT0.5210,491.520.459,079.200.408,070.400.163,228.16
0057713-02-00400Temporary Pavement Markings (12" Width) 318     LNFT2.60826.803.00954.002.05651.900.2579.50
0058713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 0.5   MILE1,300.00650.006.003.001,030.00515.001,500.00750.00
0059713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 0.969 MILE1,300.001,259.706.005.811,030.00998.071,300.001,259.70
0060722-02-00100Project Site Laboratory (Equipped) 1     EACH2,500.002,500.0030,000.0030,000.0010,000.0010,000.0072,000.0072,000.00
0061725-01-00100Temporary Detour Roads 2,711.7   SQYD63.00170,837.1058.00157,278.6070.55191,310.4470.00189,819.00
0062726-01-00100Bedding Material 124.5   CUYD58.507,283.25144.0017,928.0099.5012,387.75127.0015,811.50
0063727-01-00100Mobilization 1     LUMP49,335.0049,335.00320,000.00320,000.00300,000.00300,000.00400,000.00400,000.00
0064729-01-00100Sign (Type A) 87.2   SQFT27.302,380.5624.002,092.8020.401,778.8820.001,744.00
0065729-02-00100Sign (Type B) 149.6   SQFT29.904,473.0422.003,291.2020.403,051.8420.002,992.00
0066729-16-00200Object Marker Assembly (Type 2) 12     EACH97.501,170.00180.002,160.0056.00672.0045.00540.00
0067729-22-00100Square Tubing Post with 2-1/4" Anchor 20     EACH1,432.0028,640.00114.002,280.0076.501,530.0085.001,700.00
0068729-22-00200Square Tubing Post with 2-1/4" Omni-Directional Anchor 16     EACH260.004,160.00150.002,400.00117.251,876.00100.001,600.00
0069730-01-00100Trenching and Backfilling 120     LNFT10.001,200.0012.001,440.007.00840.0045.005,400.00
0070731-02-00100Reflectorized Raised Pavement Markers 470     EACH8.453,971.508.003,760.006.653,125.508.003,760.00
0071732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 2.093 MILE3,500.007,325.504,200.008,790.603,560.007,451.083,900.008,162.70
0072732-02-02040Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) 0.098 MILE8,000.00784.008,800.00862.408,155.00799.198,000.00784.00
0073732-03-02050Plastic Pvmt Strip (Dotted Line)(12" W)(2' L)(Thermo 90 mil) 0.029 MILE22,000.00638.0018,250.00529.2522,425.00650.3311,700.00339.30
0074735-01-00100Mailboxes 4     EACH13.0052.0050.00200.004.0016.005.0020.00
0075735-02-00100Mailbox Supports (Single) 4     EACH325.001,300.00230.00920.00122.30489.20120.00480.00
0076736-11-00500Conduit (4" HDPE, Schedule 80) 120     LNFT40.004,800.0012.001,440.0013.901,668.0025.003,000.00
0077739-01-00100Hydro-Seeding 3.79  ACRE3,730.0014,136.701,500.005,685.002,040.007,731.602,000.007,580.00
0078740-01-00100Construction Layout 1     LUMP16,250.0016,250.0036,000.0036,000.0037,605.0037,605.0060,000.0060,000.00
0079NS-500-00340Saw Cutting Asphaltic Concrete Pavement 288     INLF1.65475.202.00576.001.00288.000.50144.00
0080NS-500-00360Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement 12,920     INLF1.3016,796.001.5019,380.001.0012,920.000.506,460.00
0081NS-701-00002Trench Excavation Safety Protection (Depth > 5 feet) 518     LNFT7.804,040.407.003,626.0016.508,547.006.003,108.00
0082NS-713-00008Portable Changeable Message Sign 4     EACH1,092.004,368.005,560.0022,240.009,000.0036,000.0010,000.0040,000.00
0083NS-MSC-00120Drainage Structure Double Paved Gutter Drain9     EACH3,315.0029,835.007,615.0068,535.006,750.0060,750.0012,000.00108,000.00
0084NS-MSC-00120Drainage Structure Paved Gutter Drain10     EACH3,055.0030,550.006,300.0063,000.004,750.0047,500.0010,000.00100,000.00
             
  CONTRACTOR TOTAL   3,067,349.49 3,248,818.84 3,252,491.87 4,793,116.11