Proposal:H.011276.6
Parish:Jefferson
Routes:AIRPORT ACCESS RD., I-10 WB OFF RAMP, LOYOLA DR., VETERANS BLVD.
Description:N.O. AIRPORT CONNECTOR ROAD
Type Construction:CLEARING & GRUBBING, GRADING, NONPLASTIC EMBANKMENT (SAND) (SURCHARGE), CLASS II BASE COURSE, PORTLAND CEMENT CONCRETE PAVEMENT, ASPHALT CONCRETE PAVEMENT, MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, DRAINAGE STRUCTURES, LIGHTING, TRAFFIC SIGNALIZATION, DRILLED SHAFT FOUNDATIONS, NOISE REDUCTION SYSTEMS, WATERLINES AND RELATED WORK.
Estimated Construction Cost:$6,506,103.05
Maximum Number of Days Allowed for Construction:365
Calculated Daily User Cost:$3,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 24901 | Hard Rock Construction LLC | $6,461,568.52 | 180.00 | $7,001,568.52 |
| 2 | 06276 | Barriere Construction Co., LLC | $6,136,052.85 | 300.00 | $7,036,052.85 |
| 3 | 44187 | Palmisano Construction LLC | $6,195,042.80 | 305.00 | $7,110,042.80 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $6,499,464.50 | 334.00 | $7,501,464.50 |
| 5 | 36961 | Cycle Construction Co. L.L.C. | $7,125,650.20 | 365.00 | $8,220,650.20 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Hard Rock Construction LLC | - 2 - Barriere Construction Co., LLC | - 3 - Palmisano Construction LLC | - 4 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 5.6 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | 35,000.00 | 35,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 7,500.00 | 7,500.00 | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 194 | SQYD | 12.00 | 2,328.00 | 15.00 | 2,910.00 | 11.00 | 2,134.00 | 20.00 | 3,880.00 | | 0004 | 202-02-02020 | Removal of Asphalt Pavement | 90 | SQYD | 11.00 | 990.00 | 15.00 | 1,350.00 | 22.00 | 1,980.00 | 20.00 | 1,800.00 | | 0005 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 2,534.9 | LNFT | 7.00 | 17,744.30 | 5.00 | 12,674.50 | 8.50 | 21,546.65 | 7.00 | 17,744.30 | | 0006 | 202-02-06100 | Removal of Concrete Walks and Drives | 820 | SQYD | 16.00 | 13,120.00 | 15.00 | 12,300.00 | 13.25 | 10,865.00 | 7.00 | 5,740.00 | | 0007 | 202-02-06140 | Removal of Curbs (Concrete) | 60 | LNFT | 6.00 | 360.00 | 5.00 | 300.00 | 17.00 | 1,020.00 | 13.00 | 780.00 | | 0008 | 202-02-14500 | Removal of Guard Rail | 84 | LNFT | 14.00 | 1,176.00 | 15.00 | 1,260.00 | 15.00 | 1,260.00 | 13.00 | 1,092.00 | | 0009 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 1,479 | SQYD | 13.00 | 19,227.00 | 15.00 | 22,185.00 | 14.75 | 21,815.25 | 7.50 | 11,092.50 | | 0010 | 202-02-38240 | Removal of Signs and Supports | 1 | EACH | 165.00 | 165.00 | 60.00 | 60.00 | 1.00 | 1.00 | 1,200.00 | 1,200.00 | | 0011 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 5,200.00 | 5,200.00 | 4,500.00 | 4,500.00 | 7,500.00 | 7,500.00 | 6,600.00 | 6,600.00 | | 0012 | 203-01-00100 | General Excavation | 22,592 | CUYD | 14.00 | 316,288.00 | 10.00 | 225,920.00 | 10.00 | 225,920.00 | 10.00 | 225,920.00 | | 0013 | 203-04-00200 | Nonplastic Embankment (Sand) | 17,905 | CUYD | 27.00 | 483,435.00 | 20.00 | 358,100.00 | 20.00 | 358,100.00 | 25.00 | 447,625.00 | | 0014 | 203-08-00100 | Geotextile Fabric | 26,636 | SQYD | 2.00 | 53,272.00 | 2.00 | 53,272.00 | 0.80 | 21,308.80 | 1.00 | 26,636.00 | | 0015 | 204-02-00100 | Temporary Hay or Straw Bales | 16 | EACH | 10.00 | 160.00 | 20.00 | 320.00 | 20.00 | 320.00 | 13.00 | 208.00 | | 0016 | 204-06-00100 | Temporary Silt Fencing | 4,245 | LNFT | 2.00 | 8,490.00 | 2.50 | 10,612.50 | 1.30 | 5,518.50 | 2.40 | 10,188.00 | | 0017 | 302-01-00500 | Class II Base Course (Asphaltic Concrete Base on Embankment Layer) | 538.3 | CUYD | 30.00 | 16,149.00 | 120.00 | 64,596.00 | 200.00 | 107,660.00 | 281.00 | 151,262.30 | | 0018 | 302-02-06000 | Class II Base Course (12" Thick) | 11,603.1 | SQYD | 22.00 | 255,268.20 | 25.00 | 290,077.50 | 24.00 | 278,474.40 | 20.00 | 232,062.00 | | 0019 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 733.1 | CUYD | 35.00 | 25,658.50 | 1.00 | 733.10 | 37.00 | 27,124.70 | 65.00 | 47,651.50 | | 0020 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 10 | SQYD | 150.00 | 1,500.00 | 200.00 | 2,000.00 | 110.00 | 1,100.00 | 96.00 | 960.00 | | 0021 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 2,674.2 | SQYD | 80.00 | 213,936.00 | 99.00 | 264,745.80 | 110.00 | 294,162.00 | 96.00 | 256,723.20 | | 0022 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 236 | LNFT | 100.00 | 23,600.00 | 80.00 | 18,880.00 | 70.00 | 16,520.00 | 47.00 | 11,092.00 | | 0023 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 726 | LNFT | 95.00 | 68,970.00 | 90.00 | 65,340.00 | 72.00 | 52,272.00 | 52.00 | 37,752.00 | | 0024 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 1,059 | LNFT | 118.00 | 124,962.00 | 100.00 | 105,900.00 | 85.00 | 90,015.00 | 70.00 | 74,130.00 | | 0025 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 1,463 | LNFT | 150.00 | 219,450.00 | 120.00 | 175,560.00 | 105.00 | 153,615.00 | 80.00 | 117,040.00 | | 0026 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 18 | LNFT | 380.00 | 6,840.00 | 170.00 | 3,060.00 | 170.00 | 3,060.00 | 115.00 | 2,070.00 | | 0027 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 25 | LNFT | 302.00 | 7,550.00 | 200.00 | 5,000.00 | 200.00 | 5,000.00 | 310.00 | 7,750.00 | | 0028 | 701-03-01160 | Storm Drain Pipe (72" RCP) | 384 | LNFT | 470.00 | 180,480.00 | 440.00 | 168,960.00 | 325.00 | 124,800.00 | 440.00 | 168,960.00 | | 0029 | 701-03-02040 | Storm Drain Pipe (Outfall) (24" PP or 30" CMP) | 32 | LNFT | 136.00 | 4,352.00 | 150.00 | 4,800.00 | 135.00 | 4,320.00 | 120.00 | 3,840.00 | | 0030 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 67 | LNFT | 114.00 | 7,638.00 | 80.00 | 5,360.00 | 75.00 | 5,025.00 | 70.00 | 4,690.00 | | 0031 | 701-08-00100 | Relaying Pipe | 16 | LNFT | 450.00 | 7,200.00 | 100.00 | 1,600.00 | 100.00 | 1,600.00 | 360.00 | 5,760.00 | | 0032 | 701-09-00100 | Fabricating Pipe Fittings | 2 | EACH | 4,000.00 | 8,000.00 | 5,000.00 | 10,000.00 | 4,500.00 | 9,000.00 | 5,500.00 | 11,000.00 | | 0033 | 702-02-00001 | Manhole (Remove and Replace Frame and Cover) | 2 | EACH | 7,500.00 | 15,000.00 | 1,500.00 | 3,000.00 | 850.00 | 1,700.00 | 450.00 | 900.00 | | 0034 | 702-02-00100 | Manholes (MH-06) | 11 | EACH | 7,000.00 | 77,000.00 | 6,000.00 | 66,000.00 | 4,250.00 | 46,750.00 | 7,000.00 | 77,000.00 | | 0035 | 702-03-00100 | Catch Basins (CB-01) | 19 | EACH | 3,500.00 | 66,500.00 | 3,000.00 | 57,000.00 | 2,950.00 | 56,050.00 | 8,200.00 | 155,800.00 | | 0036 | 702-03-00200 | Catch Basins (CB-02) | 2 | EACH | 6,000.00 | 12,000.00 | 5,000.00 | 10,000.00 | 4,000.00 | 8,000.00 | 10,000.00 | 20,000.00 | | 0037 | 702-03-00500 | Catch Basins (CB-06) | 9 | EACH | 6,500.00 | 58,500.00 | 7,000.00 | 63,000.00 | 6,750.00 | 60,750.00 | 8,600.00 | 77,400.00 | | 0038 | 702-03-00600 | Catch Basins (CB-07) | 3 | EACH | 10,000.00 | 30,000.00 | 9,000.00 | 27,000.00 | 6,750.00 | 20,250.00 | 10,500.00 | 31,500.00 | | 0039 | 702-03-00700 | Catch Basins (CB-08) | 4 | EACH | 14,000.00 | 56,000.00 | 14,000.00 | 56,000.00 | 9,250.00 | 37,000.00 | 11,100.00 | 44,400.00 | | 0040 | 702-03-00800 | Catch Basins (CB-09) | 10 | EACH | 6,500.00 | 65,000.00 | 8,000.00 | 80,000.00 | 5,750.00 | 57,500.00 | 8,900.00 | 89,000.00 | | 0041 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 745.00 | 2,980.00 | 2,000.00 | 8,000.00 | 1,100.00 | 4,400.00 | 1,500.00 | 6,000.00 | | 0042 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 2 | EACH | 110.00 | 220.00 | 400.00 | 800.00 | 195.00 | 390.00 | 250.00 | 500.00 | | 0043 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 20.00 | 5,000.00 | 24.00 | 6,000.00 | 22.50 | 5,625.00 | 19.00 | 4,750.00 | | 0044 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 25 | LNFT | 90.00 | 2,250.00 | 75.00 | 1,875.00 | 75.00 | 1,875.00 | 79.00 | 1,975.00 | | 0045 | 704-11-00100 | Guard Rail End Treatment (Flared) | 1 | EACH | 3,000.00 | 3,000.00 | 2,600.00 | 2,600.00 | 2,950.00 | 2,950.00 | 2,500.00 | 2,500.00 | | 0046 | 705-06-00400 | Chain Link Fence (7 Foot Height) | 751 | LNFT | 47.00 | 35,297.00 | 18.00 | 13,518.00 | 50.00 | 37,550.00 | 32.00 | 24,032.00 | | 0047 | 705-07-08060 | 10-Foot Single Gates for Chain Link Fence (7 Foot Height) | 1 | EACH | 3,000.00 | 3,000.00 | 600.00 | 600.00 | 2,500.00 | 2,500.00 | 2,500.00 | 2,500.00 | | 0048 | 706-01-00100 | Concrete Walk (4" Thick) | 1,034.4 | SQYD | 70.00 | 72,408.00 | 70.00 | 72,408.00 | 65.00 | 67,236.00 | 60.00 | 62,064.00 | | 0049 | 706-02-00200 | Concrete Drive (6" Thick) | 95.2 | SQYD | 85.00 | 8,092.00 | 90.00 | 8,568.00 | 72.00 | 6,854.40 | 65.00 | 6,188.00 | | 0050 | 706-02-00300 | Concrete Drive (8" Thick) | 238.6 | SQYD | 100.00 | 23,860.00 | 100.00 | 23,860.00 | 79.00 | 18,849.40 | 71.00 | 16,940.60 | | 0051 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 444 | SQYD | 70.00 | 31,080.00 | 90.00 | 39,960.00 | 70.00 | 31,080.00 | 63.00 | 27,972.00 | | 0052 | 706-04-00100 | Handicapped Curb Ramps | 25 | EACH | 1,900.00 | 47,500.00 | 2,500.00 | 62,500.00 | 1,750.00 | 43,750.00 | 1,700.00 | 42,500.00 | | 0053 | 707-01-00200 | Concrete Curb (Barrier) | 60 | LNFT | 22.00 | 1,320.00 | 25.00 | 1,500.00 | 25.00 | 1,500.00 | 21.00 | 1,260.00 | | 0054 | 707-03-00100 | Combination Concrete Curb and Gutter | 5,132.1 | LNFT | 36.00 | 184,755.60 | 28.00 | 143,698.80 | 27.00 | 138,566.70 | 26.00 | 133,434.60 | | 0055 | 710-01-00100 | Flowable Fill | 11 | CUYD | 362.00 | 3,982.00 | 250.00 | 2,750.00 | 600.00 | 6,600.00 | 1,000.00 | 11,000.00 | | 0056 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 125,000.00 | 125,000.00 | 115,000.00 | 115,000.00 | | 0057 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 356 | LNFT | 3.00 | 1,068.00 | 2.00 | 712.00 | 3.00 | 1,068.00 | 1.00 | 356.00 | | 0058 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.347 | MILE | 3.50 | 8.21 | 300.00 | 704.10 | 250.00 | 586.75 | 5,800.00 | 13,612.60 | | 0059 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 40 | EACH | 55.00 | 2,200.00 | 60.00 | 2,400.00 | 25.00 | 1,000.00 | 53.00 | 2,120.00 | | 0060 | 714-01-00600 | Slab Sodding (St. Augustine) | 200 | SQYD | 15.00 | 3,000.00 | 20.00 | 4,000.00 | 15.50 | 3,100.00 | 8.50 | 1,700.00 | | 0061 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 4,000.00 | 400.00 | 3,500.00 | 350.00 | 3,500.00 | 350.00 | 845.00 | 84.50 | | 0062 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 18,000.00 | 18,000.00 | 70,000.00 | 70,000.00 | 35,000.00 | 35,000.00 | 29,000.00 | 29,000.00 | | 0063 | 723-01-00100 | Granular Material (Net Section) | 100 | CUYD | 25.00 | 2,500.00 | 30.00 | 3,000.00 | 15.00 | 1,500.00 | 39.00 | 3,900.00 | | 0064 | 726-01-00100 | Bedding Material | 734.9 | CUYD | 60.00 | 44,094.00 | 100.00 | 73,490.00 | 45.00 | 33,070.50 | 60.00 | 44,094.00 | | 0065 | 727-01-00100 | Mobilization | 1 | LUMP | 350,000.00 | 350,000.00 | 610,000.00 | 610,000.00 | 465,000.00 | 465,000.00 | 300,000.00 | 300,000.00 | | 0066 | 729-01-00100 | Sign (Type A) | 428.2 | SQFT | 126.00 | 53,953.20 | 30.00 | 12,846.00 | 30.00 | 12,846.00 | 62.00 | 26,548.40 | | 0067 | 729-01-00103 | Sign (Type A)(Relocate) | 48 | SQFT | 17.00 | 816.00 | 30.00 | 1,440.00 | 30.00 | 1,440.00 | 30.00 | 1,440.00 | | 0068 | 729-08-00220 | Mounting (3 1/2" Size Post)(Median Barrier Mount) | 5 | EACH | 1,800.00 | 9,000.00 | 2,000.00 | 10,000.00 | 2,000.00 | 10,000.00 | 1,700.00 | 8,500.00 | | 0069 | 729-19-00100 | Dead End Road Installations (Type A) | 1 | EACH | 2,100.00 | 2,100.00 | 2,500.00 | 2,500.00 | 3,000.00 | 3,000.00 | 2,000.00 | 2,000.00 | | 0070 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 39 | EACH | 82.00 | 3,198.00 | 100.00 | 3,900.00 | 180.00 | 7,020.00 | 79.00 | 3,081.00 | | 0071 | 730-01-00100 | Trenching and Backfilling | 995 | LNFT | 4.00 | 3,980.00 | 4.00 | 3,980.00 | 9.00 | 8,955.00 | 9.00 | 8,955.00 | | 0072 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") (2#4, 1#4 Bare Stranded Ground) (A) | 2,040 | LNFT | 10.00 | 20,400.00 | 10.00 | 20,400.00 | 9.50 | 19,380.00 | 10.50 | 21,420.00 | | 0073 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") (3#4) (SCH 80) (B) | 10 | LNFT | 14.00 | 140.00 | 12.00 | 120.00 | 14.00 | 140.00 | 14.00 | 140.00 | | 0074 | 730-02-05100 | Conduit with Conductors (Fiberglass) (2") (2#4, 1#4 Bare Stranded Ground) (C) | 10 | LNFT | 70.00 | 700.00 | 65.00 | 650.00 | 35.00 | 350.00 | 28.00 | 280.00 | | 0075 | 730-04-00100 | Jacked or Bored Casing (4" Diameter) (PVC/HDPE) (SCH 80) | 275 | LNFT | 45.00 | 12,375.00 | 45.00 | 12,375.00 | 52.00 | 14,300.00 | 50.00 | 13,750.00 | | 0076 | 730-05-10000 | Light Pole (30') (Single Arm, Ground Mount) (Aluminum) | 10 | EACH | 7,000.00 | 70,000.00 | 5,000.00 | 50,000.00 | 5,750.00 | 57,500.00 | 5,100.00 | 51,000.00 | | 0077 | 730-05-10000 | Light Pole (30') (Twin Arm, Ground Mount) (Aluminum) | 3 | EACH | 7,000.00 | 21,000.00 | 6,000.00 | 18,000.00 | 7,000.00 | 21,000.00 | 5,800.00 | 17,400.00 | | 0078 | 730-05-10000 | Light Pole (30') (Twin Arm, Median Barrier Mount) (Aluminum) | 6 | EACH | 7,000.00 | 42,000.00 | 4,000.00 | 24,000.00 | 4,950.00 | 29,700.00 | 3,700.00 | 22,200.00 | | 0079 | 730-07-10000 | Luminaire (16k) (LED) | 28 | EACH | 1,000.00 | 28,000.00 | 800.00 | 22,400.00 | 900.00 | 25,200.00 | 700.00 | 19,600.00 | | 0080 | 730-08-00200 | Electrical Service Point (Structure) (Combination Lighting Controller) | 1 | EACH | 8,200.00 | 8,200.00 | 6,000.00 | 6,000.00 | 6,500.00 | 6,500.00 | 5,500.00 | 5,500.00 | | 0082 | 730-16-00300 | Underground Junction Box (13" x 24") (JB3) | 6 | EACH | 670.00 | 4,020.00 | 800.00 | 4,800.00 | 825.00 | 4,950.00 | 795.00 | 4,770.00 | | 0083 | 730-19-00010 | Modular Breakaway Cable System | 13 | EACH | 2,100.00 | 27,300.00 | 2,500.00 | 32,500.00 | 2,500.00 | 32,500.00 | 2,400.00 | 31,200.00 | | 0084 | 730-21-00020 | Duct Marker (Concrete) | 6 | EACH | 445.00 | 2,670.00 | 300.00 | 1,800.00 | 250.00 | 1,500.00 | 230.00 | 1,380.00 | | 0085 | 730-22-00420 | Underground Marker Tape (6")(Detectable) | 995 | LNFT | 1.00 | 995.00 | 0.50 | 497.50 | 0.50 | 497.50 | 0.50 | 497.50 | | 0086 | 731-02-00100 | Reflectorized Raised Pavement Markers | 691 | EACH | 9.00 | 6,219.00 | 8.00 | 5,528.00 | 15.00 | 10,365.00 | 8.00 | 5,528.00 | | 0087 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 6,213 | LNFT | 1.00 | 6,213.00 | 0.90 | 5,591.70 | 1.00 | 6,213.00 | 0.80 | 4,970.40 | | 0088 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 3,254 | LNFT | 1.00 | 3,254.00 | 3.50 | 11,389.00 | 3.00 | 9,762.00 | 3.00 | 9,762.00 | | 0089 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,116 | LNFT | 10.00 | 11,160.00 | 13.00 | 14,508.00 | 11.00 | 12,276.00 | 13.00 | 14,508.00 | | 0090 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.481 | MILE | 4,200.00 | 6,220.20 | 4,000.00 | 5,924.00 | 5,000.00 | 7,405.00 | 4,100.00 | 6,072.10 | | 0091 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.076 | MILE | 2,300.00 | 2,474.80 | 1,600.00 | 1,721.60 | 2,150.00 | 2,313.40 | 2,100.00 | 2,259.60 | | 0092 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.558 | MILE | 3,400.00 | 1,897.20 | 4,100.00 | 2,287.80 | 4,500.00 | 2,511.00 | 3,700.00 | 2,064.60 | | 0093 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 6 | EACH | 300.00 | 1,800.00 | 300.00 | 1,800.00 | 225.00 | 1,350.00 | 105.00 | 630.00 | | 0094 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 6 | EACH | 500.00 | 3,000.00 | 450.00 | 2,700.00 | 300.00 | 1,800.00 | 423.00 | 2,538.00 | | 0095 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 19 | EACH | 300.00 | 5,700.00 | 300.00 | 5,700.00 | 250.00 | 4,750.00 | 105.00 | 1,995.00 | | 0096 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 14 | EACH | 300.00 | 4,200.00 | 300.00 | 4,200.00 | 250.00 | 3,500.00 | 290.00 | 4,060.00 | | 0097 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 33 | EACH | 400.00 | 13,200.00 | 300.00 | 9,900.00 | 325.00 | 10,725.00 | 290.00 | 9,570.00 | | 0098 | 732-04-19040 | Plastic Pavement Legends and Symbols (Shield - Interstate) (Preformed Heat Applied Retroreflective Thermoplastic) | 4 | EACH | 1,400.00 | 5,600.00 | 2,100.00 | 8,400.00 | 1,250.00 | 5,000.00 | 1,400.00 | 5,600.00 | | 0099 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) | 1,631.8 | LNFT | 60.00 | 97,908.00 | 70.00 | 114,226.00 | 100.00 | 163,180.00 | 145.00 | 236,611.00 | | 0100 | 733-01-00200 | Concrete Roadway Barrier (Double Faced) | 683.51 | LNFT | 175.00 | 119,614.25 | 100.00 | 68,351.00 | 150.00 | 102,526.50 | 165.00 | 112,779.15 | | 0101 | 736-01-00100 | Trenching and Backfilling | 596 | LNFT | 4.00 | 2,384.00 | 6.00 | 3,576.00 | 6.00 | 3,576.00 | 5.75 | 3,427.00 | | 0102 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 334 | LNFT | 31.00 | 10,354.00 | 25.00 | 8,350.00 | 27.50 | 9,185.00 | 27.00 | 9,018.00 | | 0103 | 736-04-02000 | Signal Support (Pedestal Pole) | 1 | EACH | 3,400.00 | 3,400.00 | 2,200.00 | 2,200.00 | 2,750.00 | 2,750.00 | 2,300.00 | 2,300.00 | | 0104 | 736-04-05009 | Signal Support (45'span, 25' span add-on arm) N/A | 1 | EACH | 18,000.00 | 18,000.00 | 17,000.00 | 17,000.00 | 19,000.00 | 19,000.00 | 18,000.00 | 18,000.00 | | 0105 | 736-04-05012 | Signal Support (45'span, 40' span add-on arm) | 1 | EACH | 20,000.00 | 20,000.00 | 19,000.00 | 19,000.00 | 20,000.00 | 20,000.00 | 19,000.00 | 19,000.00 | | 0106 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 7 | EACH | 1,300.00 | 9,100.00 | 1,000.00 | 7,000.00 | 1,250.00 | 8,750.00 | 1,000.00 | 7,000.00 | | 0107 | 736-05-02060 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) (Arrow Up) | 1 | EACH | 1,250.00 | 1,250.00 | 1,300.00 | 1,300.00 | 1,300.00 | 1,300.00 | 1,300.00 | 1,300.00 | | 0108 | 736-05-02070 | Signal Hds (3 Sec, 12" Led Lens, LT. R, LT. Y, LT. G) | 5 | EACH | 1,250.00 | 6,250.00 | 1,000.00 | 5,000.00 | 1,250.00 | 6,250.00 | 925.00 | 4,625.00 | | 0109 | 736-05-02080 | Signal Hds (3 Sec, 12" Led Lens, RT. R, RT. Y, RT. G) | 3 | EACH | 1,300.00 | 3,900.00 | 1,000.00 | 3,000.00 | 1,250.00 | 3,750.00 | 950.00 | 2,850.00 | | 0110 | 736-05-03000 | Signal Heads (4 Section, 12" Led Lens, R, Y, LT. G, G) | 1 | EACH | 1,500.00 | 1,500.00 | 1,300.00 | 1,300.00 | 1,550.00 | 1,550.00 | 1,400.00 | 1,400.00 | | 0111 | 736-06-00600 | Signal Service (Existing Pole) | 1 | EACH | 3,300.00 | 3,300.00 | 2,000.00 | 2,000.00 | 2,250.00 | 2,250.00 | 1,800.00 | 1,800.00 | | 0112 | 736-09-00100 | Loop Detector | 150 | LNFT | 32.00 | 4,800.00 | 30.00 | 4,500.00 | 32.00 | 4,800.00 | 27.00 | 4,050.00 | | 0113 | 736-10-00300 | Underground Junction Box (Type F) | 7 | EACH | 800.00 | 5,600.00 | 1,000.00 | 7,000.00 | 1,000.00 | 7,000.00 | 1,000.00 | 7,000.00 | | 0114 | 736-10-00400 | Underground Junction Box (Type G) | 1 | EACH | 1,100.00 | 1,100.00 | 1,500.00 | 1,500.00 | 1,500.00 | 1,500.00 | 1,500.00 | 1,500.00 | | 0115 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 20 | LNFT | 5.00 | 100.00 | 7.00 | 140.00 | 6.50 | 130.00 | 6.25 | 125.00 | | 0116 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 580 | LNFT | 6.00 | 3,480.00 | 12.00 | 6,960.00 | 12.00 | 6,960.00 | 11.00 | 6,380.00 | | 0117 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 20 | LNFT | 10.00 | 200.00 | 8.00 | 160.00 | 9.00 | 180.00 | 8.00 | 160.00 | | 0118 | 736-12-04000 | Conductor (6c, #14 awg) | 425 | LNFT | 6.00 | 2,550.00 | 4.00 | 1,700.00 | 4.50 | 1,912.50 | 3.50 | 1,487.50 | | 0119 | 736-12-06000 | Conductor (10c, #14 awg) | 2,234 | LNFT | 7.00 | 15,638.00 | 4.00 | 8,936.00 | 4.75 | 10,611.50 | 3.85 | 8,600.90 | | 0120 | 739-01-00100 | Hydro-Seeding | 1.09 | ACRE | 1,500.00 | 1,635.00 | 1,500.00 | 1,635.00 | 1,650.00 | 1,798.50 | 800.00 | 872.00 | | 0121 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | 100,000.00 | 100,000.00 | 45,000.00 | 45,000.00 | | 0122 | 804-02-00200 | Treated Timber Piles (Coastal Treatment) | 80 | LNFT | 118.00 | 9,440.00 | 100.00 | 8,000.00 | 130.00 | 10,400.00 | 265.00 | 21,200.00 | | 0123 | 805-01-00200 | Class A Concrete (Pipe Headwalls) | 23.95 | CUYD | 1,800.00 | 43,110.00 | 2,000.00 | 47,900.00 | 1,800.00 | 43,110.00 | 1,950.00 | 46,702.50 | | 0124 | 806-01-00100 | Deformed Reinforcing Steel | 42,226 | LB | 1.00 | 42,226.00 | 1.50 | 63,339.00 | 0.60 | 25,335.60 | 1.50 | 63,339.00 | | 0125 | NS-203-00006 | Exploratory Excavation | 400 | CUYD | 50.00 | 20,000.00 | 10.00 | 4,000.00 | 50.00 | 20,000.00 | 53.00 | 21,200.00 | | 0126 | NS-203-00007 | Temporary Sheeting and Bracing | 1 | LUMP | 205,000.00 | 205,000.00 | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 | 62,000.00 | 62,000.00 | | 0127 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 27,210 | INLF | 1.00 | 27,210.00 | 0.40 | 10,884.00 | 0.55 | 14,965.50 | 0.45 | 12,244.50 | | 0128 | NS-502-01000 | Asphalt Concrete | 7,155.4 | TON | 93.00 | 665,452.20 | 85.00 | 608,209.00 | 100.00 | 715,540.00 | 125.00 | 894,425.00 | | 0129 | NS-502-01100 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 617.4 | TON | 93.00 | 57,418.20 | 85.00 | 52,479.00 | 100.00 | 61,740.00 | 125.00 | 77,175.00 | | 0130 | NS-509-01000 | Milling Asphalt Pavement | 14,749 | SQYD | 4.00 | 58,996.00 | 3.55 | 52,358.95 | 4.00 | 58,996.00 | 3.75 | 55,308.75 | | 0131 | NS-509-02000 | Contractor Retained Reclaimed Asphalt Pavement | -820 | CUYD | 10.90 | -8,934.72 | 10.00 | -8,200.00 | 10.00 | -8,200.00 | 1.00 | -820.00 | | 0132 | NS-510-01400 | Pavement Patching (12" Minimum Thickness) | 393 | SQYD | 88.00 | 34,584.00 | 80.00 | 31,440.00 | 90.00 | 35,370.00 | 100.00 | 39,300.00 | | 0133 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,765 | INLF | 1.00 | 2,765.00 | 1.00 | 2,765.00 | 0.85 | 2,350.25 | 0.70 | 1,935.50 | | 0134 | NS-701-00002 | Trench Excavation Safety Protection (Depth > 5 feet) | 1,700 | LNFT | 1.50 | 2,550.00 | 2.00 | 3,400.00 | 15.00 | 25,500.00 | 27.50 | 46,750.00 | | 0135 | NS-702-00002 | Cleaning Existing Manhole | 6 | EACH | 400.00 | 2,400.00 | 400.00 | 2,400.00 | 450.00 | 2,700.00 | 700.00 | 4,200.00 | | 0136 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 2 | EACH | 40,000.00 | 80,000.00 | 10,000.00 | 20,000.00 | 5,000.00 | 10,000.00 | 2,100.00 | 4,200.00 | | 0137 | NS-729-00031 | Breakaway Square Tubing Sign Support - Hard Concrete | 6 | EACH | 300.00 | 1,800.00 | 180.00 | 1,080.00 | 450.00 | 2,700.00 | 290.00 | 1,740.00 | | 0138 | NS-736-00001 | GPS | 1 | EACH | 852.00 | 852.00 | 900.00 | 900.00 | 900.00 | 900.00 | 718.00 | 718.00 | | 0139 | NS-736-00005 | Video Detection Cabinet Components | 1 | EACH | 14.00 | 14.00 | 14,000.00 | 14,000.00 | 15,000.00 | 15,000.00 | 13,250.00 | 13,250.00 | | 0140 | NS-736-00006 | Video Detection Camera | 5 | EACH | 3,900.00 | 19,500.00 | 4,000.00 | 20,000.00 | 3,500.00 | 17,500.00 | 2,150.00 | 10,750.00 | | 0141 | NS-800-00580 | Noise Reduction Systems (LSE - 10' Height) | 15,960 | FTLF | 52.00 | 829,920.00 | 50.00 | 798,000.00 | 55.00 | 877,800.00 | 49.15 | 784,434.00 | | 0142 | NS-MSC-00005 | Construction Photographs And Video (Roadway Surfaces) | 1 | LUMP | 5,000.00 | 5,000.00 | 15,000.00 | 15,000.00 | 5,000.00 | 5,000.00 | 22,000.00 | 22,000.00 | | 0143 | NS-MSC-00080 | Detectable Warning System Retrofit for Curb Ramps | 2 | EACH | 500.00 | 1,000.00 | 300.00 | 600.00 | 350.00 | 700.00 | 1,200.00 | 2,400.00 | | 0144 | NS-MSC-00120 | Drainage Structure Paved Gutter Drain | 6 | EACH | 3,000.00 | 18,000.00 | 4,000.00 | 24,000.00 | 3,750.00 | 22,500.00 | 2,145.00 | 12,870.00 | | 0145 | NS-P26-00002 | Control Cabinet and Related Equipment | 1 | EACH | 12,000.00 | 12,000.00 | 13,000.00 | 13,000.00 | 12,500.00 | 12,500.00 | 11,000.00 | 11,000.00 | | 0146 | NS-P26-00021 | Control Cabinet Foundation | 1 | EACH | 4,900.00 | 4,900.00 | 5,200.00 | 5,200.00 | 5,200.00 | 5,200.00 | 5,000.00 | 5,000.00 | | 0147 | NS-P26-00032 | Signal Controller | 2 | EACH | 5,000.00 | 10,000.00 | 5,400.00 | 10,800.00 | 5,500.00 | 11,000.00 | 4,700.00 | 9,400.00 | | 0148 | NS-P26-00076 | Temporary Dam Removal and Replacement | 2 | EACH | 3,000.00 | 6,000.00 | 20,000.00 | 40,000.00 | 30,000.00 | 60,000.00 | 8,500.00 | 17,000.00 | | 0149 | NS-P26-06000 | Fire Hydrants (Jefferson Parish) | 1 | EACH | 6,000.00 | 6,000.00 | 5,000.00 | 5,000.00 | 4,750.00 | 4,750.00 | 3,900.00 | 3,900.00 | | 0150 | NS-P26-06020 | Fittings for Waterlines (DI) (Jefferson Parish) | 3,390 | LB | 3.14 | 10,651.38 | 4.00 | 13,560.00 | 3.75 | 12,712.50 | 4.50 | 15,255.00 | | 0151 | NS-P26-07000 | Gate Valve and Valve Box (8") (Jefferson Parish) | 5 | EACH | 2,000.00 | 10,000.00 | 2,000.00 | 10,000.00 | 4,500.00 | 22,500.00 | 1,100.00 | 5,500.00 | | 0152 | NS-P26-07001 | Gate Valve and Valve Box (6") | 1 | EACH | 1,000.00 | 1,000.00 | 1,800.00 | 1,800.00 | 1,200.00 | 1,200.00 | 1,000.00 | 1,000.00 | | 0153 | NS-P26-12040 | Long Body Transitional Coupling (8") (Jefferson Parish) | 8 | EACH | 450.00 | 3,600.00 | 2,500.00 | 20,000.00 | 275.00 | 2,200.00 | 1,000.00 | 8,000.00 | | 0154 | NS-P26-12080 | Long Body Transitional Coupling (12 inch) (Jefferson Parish) | 2 | EACH | 606.00 | 1,212.00 | 3,000.00 | 6,000.00 | 700.00 | 1,400.00 | 1,000.00 | 2,000.00 | | 0155 | NS-P26-18000 | Removal and Disposal of Existing AC Waterline (Jefferson Parish) | 245 | LNFT | 11.00 | 2,695.00 | 15.00 | 3,675.00 | 10.00 | 2,450.00 | 200.00 | 49,000.00 | | 0156 | NS-P26-23040 | Waterline (12" DI) (Restrained) (Jefferson Parish) | 135 | LNFT | 211.00 | 28,485.00 | 160.00 | 21,600.00 | 45.00 | 6,075.00 | 115.00 | 15,525.00 | | 0157 | NS-P26-23060 | Waterline (8" PVC) (Jefferson Parish) | 340 | LNFT | 120.00 | 40,800.00 | 70.00 | 23,800.00 | 90.00 | 30,600.00 | 45.00 | 15,300.00 | | 0158 | NS-P26-23080 | Waterline (12" PVC) (Jefferson Parish) | 60 | LNFT | 120.00 | 7,200.00 | 80.00 | 4,800.00 | 95.00 | 5,700.00 | 60.00 | 3,600.00 | | 0159 | NS-P26-23120 | Waterline (6" PVC) (Restrained) (Jefferson Parish) | 10 | LNFT | 110.00 | 1,100.00 | 60.00 | 600.00 | 110.00 | 1,100.00 | 60.00 | 600.00 | | 0160 | NS-P26-23141 | Waterline (8" DI) (Restrained) | 445 | LNFT | 150.00 | 66,750.00 | 140.00 | 62,300.00 | 80.00 | 35,600.00 | 85.00 | 37,825.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 6,461,568.52 | | 6,136,052.85 | | 6,195,042.80 | | 6,499,464.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Cycle Construction Co. L.L.C. | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 5.6 | LUMP | 30,600.00 | 30,600.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 52,600.00 | 52,600.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 194 | SQYD | 14.00 | 2,716.00 | | 0004 | 202-02-02020 | Removal of Asphalt Pavement | 90 | SQYD | 19.00 | 1,710.00 | | 0005 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 2,534.9 | LNFT | 6.00 | 15,209.40 | | 0006 | 202-02-06100 | Removal of Concrete Walks and Drives | 820 | SQYD | 17.00 | 13,940.00 | | 0007 | 202-02-06140 | Removal of Curbs (Concrete) | 60 | LNFT | 8.50 | 510.00 | | 0008 | 202-02-14500 | Removal of Guard Rail | 84 | LNFT | 14.50 | 1,218.00 | | 0009 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 1,479 | SQYD | 20.00 | 29,580.00 | | 0010 | 202-02-38240 | Removal of Signs and Supports | 1 | EACH | 200.00 | 200.00 | | 0011 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 7,300.00 | 7,300.00 | | 0012 | 203-01-00100 | General Excavation | 22,592 | CUYD | 16.00 | 361,472.00 | | 0013 | 203-04-00200 | Nonplastic Embankment (Sand) | 17,905 | CUYD | 21.50 | 384,957.50 | | 0014 | 203-08-00100 | Geotextile Fabric | 26,636 | SQYD | 2.00 | 53,272.00 | | 0015 | 204-02-00100 | Temporary Hay or Straw Bales | 16 | EACH | 17.00 | 272.00 | | 0016 | 204-06-00100 | Temporary Silt Fencing | 4,245 | LNFT | 3.00 | 12,735.00 | | 0017 | 302-01-00500 | Class II Base Course (Asphaltic Concrete Base on Embankment Layer) | 538.3 | CUYD | 187.00 | 100,662.10 | | 0018 | 302-02-06000 | Class II Base Course (12" Thick) | 11,603.1 | SQYD | 18.00 | 208,855.80 | | 0019 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 733.1 | CUYD | 76.00 | 55,715.60 | | 0020 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 10 | SQYD | 111.00 | 1,110.00 | | 0021 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 2,674.2 | SQYD | 111.00 | 296,836.20 | | 0022 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 236 | LNFT | 80.00 | 18,880.00 | | 0023 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 726 | LNFT | 82.00 | 59,532.00 | | 0024 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 1,059 | LNFT | 103.00 | 109,077.00 | | 0025 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 1,463 | LNFT | 145.00 | 212,135.00 | | 0026 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 18 | LNFT | 169.00 | 3,042.00 | | 0027 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 25 | LNFT | 292.00 | 7,300.00 | | 0028 | 701-03-01160 | Storm Drain Pipe (72" RCP) | 384 | LNFT | 470.00 | 180,480.00 | | 0029 | 701-03-02040 | Storm Drain Pipe (Outfall) (24" PP or 30" CMP) | 32 | LNFT | 158.00 | 5,056.00 | | 0030 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 67 | LNFT | 83.00 | 5,561.00 | | 0031 | 701-08-00100 | Relaying Pipe | 16 | LNFT | 287.00 | 4,592.00 | | 0032 | 701-09-00100 | Fabricating Pipe Fittings | 2 | EACH | 3,400.00 | 6,800.00 | | 0033 | 702-02-00001 | Manhole (Remove and Replace Frame and Cover) | 2 | EACH | 1,250.00 | 2,500.00 | | 0034 | 702-02-00100 | Manholes (MH-06) | 11 | EACH | 6,200.00 | 68,200.00 | | 0035 | 702-03-00100 | Catch Basins (CB-01) | 19 | EACH | 3,800.00 | 72,200.00 | | 0036 | 702-03-00200 | Catch Basins (CB-02) | 2 | EACH | 4,500.00 | 9,000.00 | | 0037 | 702-03-00500 | Catch Basins (CB-06) | 9 | EACH | 5,300.00 | 47,700.00 | | 0038 | 702-03-00600 | Catch Basins (CB-07) | 3 | EACH | 10,300.00 | 30,900.00 | | 0039 | 702-03-00700 | Catch Basins (CB-08) | 4 | EACH | 12,200.00 | 48,800.00 | | 0040 | 702-03-00800 | Catch Basins (CB-09) | 10 | EACH | 10,000.00 | 100,000.00 | | 0041 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 1,100.00 | 4,400.00 | | 0042 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 2 | EACH | 115.00 | 230.00 | | 0043 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 21.00 | 5,250.00 | | 0044 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 25 | LNFT | 86.00 | 2,150.00 | | 0045 | 704-11-00100 | Guard Rail End Treatment (Flared) | 1 | EACH | 2,900.00 | 2,900.00 | | 0046 | 705-06-00400 | Chain Link Fence (7 Foot Height) | 751 | LNFT | 50.00 | 37,550.00 | | 0047 | 705-07-08060 | 10-Foot Single Gates for Chain Link Fence (7 Foot Height) | 1 | EACH | 2,500.00 | 2,500.00 | | 0048 | 706-01-00100 | Concrete Walk (4" Thick) | 1,034.4 | SQYD | 50.00 | 51,720.00 | | 0049 | 706-02-00200 | Concrete Drive (6" Thick) | 95.2 | SQYD | 60.00 | 5,712.00 | | 0050 | 706-02-00300 | Concrete Drive (8" Thick) | 238.6 | SQYD | 72.00 | 17,179.20 | | 0051 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 444 | SQYD | 61.00 | 27,084.00 | | 0052 | 706-04-00100 | Handicapped Curb Ramps | 25 | EACH | 1,400.00 | 35,000.00 | | 0053 | 707-01-00200 | Concrete Curb (Barrier) | 60 | LNFT | 20.00 | 1,200.00 | | 0054 | 707-03-00100 | Combination Concrete Curb and Gutter | 5,132.1 | LNFT | 13.00 | 66,717.30 | | 0055 | 710-01-00100 | Flowable Fill | 11 | CUYD | 400.00 | 4,400.00 | | 0056 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 21,000.00 | 21,000.00 | | 0057 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 356 | LNFT | 4.00 | 1,424.00 | | 0058 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.347 | MILE | 2,250.00 | 5,280.75 | | 0059 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 40 | EACH | 58.00 | 2,320.00 | | 0060 | 714-01-00600 | Slab Sodding (St. Augustine) | 200 | SQYD | 15.50 | 3,100.00 | | 0061 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 3,500.00 | 350.00 | | 0062 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 25,000.00 | 25,000.00 | | 0063 | 723-01-00100 | Granular Material (Net Section) | 100 | CUYD | 25.00 | 2,500.00 | | 0064 | 726-01-00100 | Bedding Material | 734.9 | CUYD | 68.00 | 49,973.20 | | 0065 | 727-01-00100 | Mobilization | 1 | LUMP | 488,000.00 | 488,000.00 | | 0066 | 729-01-00100 | Sign (Type A) | 428.2 | SQFT | 25.00 | 10,705.00 | | 0067 | 729-01-00103 | Sign (Type A)(Relocate) | 48 | SQFT | 17.00 | 816.00 | | 0068 | 729-08-00220 | Mounting (3 1/2" Size Post)(Median Barrier Mount) | 5 | EACH | 1,800.00 | 9,000.00 | | 0069 | 729-19-00100 | Dead End Road Installations (Type A) | 1 | EACH | 2,200.00 | 2,200.00 | | 0070 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 39 | EACH | 86.00 | 3,354.00 | | 0071 | 730-01-00100 | Trenching and Backfilling | 995 | LNFT | 10.00 | 9,950.00 | | 0072 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") (2#4, 1#4 Bare Stranded Ground) (A) | 2,040 | LNFT | 11.00 | 22,440.00 | | 0073 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") (3#4) (SCH 80) (B) | 10 | LNFT | 14.50 | 145.00 | | 0074 | 730-02-05100 | Conduit with Conductors (Fiberglass) (2") (2#4, 1#4 Bare Stranded Ground) (C) | 10 | LNFT | 31.00 | 310.00 | | 0075 | 730-04-00100 | Jacked or Bored Casing (4" Diameter) (PVC/HDPE) (SCH 80) | 275 | LNFT | 54.00 | 14,850.00 | | 0076 | 730-05-10000 | Light Pole (30') (Single Arm, Ground Mount) (Aluminum) | 10 | EACH | 5,560.00 | 55,600.00 | | 0077 | 730-05-10000 | Light Pole (30') (Twin Arm, Ground Mount) (Aluminum) | 3 | EACH | 6,300.00 | 18,900.00 | | 0078 | 730-05-10000 | Light Pole (30') (Twin Arm, Median Barrier Mount) (Aluminum) | 6 | EACH | 4,100.00 | 24,600.00 | | 0079 | 730-07-10000 | Luminaire (16k) (LED) | 28 | EACH | 766.00 | 21,448.00 | | 0080 | 730-08-00200 | Electrical Service Point (Structure) (Combination Lighting Controller) | 1 | EACH | 6,000.00 | 6,000.00 | | 0082 | 730-16-00300 | Underground Junction Box (13" x 24") (JB3) | 6 | EACH | 865.00 | 5,190.00 | | 0083 | 730-19-00010 | Modular Breakaway Cable System | 13 | EACH | 2,600.00 | 33,800.00 | | 0084 | 730-21-00020 | Duct Marker (Concrete) | 6 | EACH | 250.00 | 1,500.00 | | 0085 | 730-22-00420 | Underground Marker Tape (6")(Detectable) | 995 | LNFT | 0.50 | 497.50 | | 0086 | 731-02-00100 | Reflectorized Raised Pavement Markers | 691 | EACH | 8.50 | 5,873.50 | | 0087 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 6,213 | LNFT | 0.75 | 4,659.75 | | 0088 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 3,254 | LNFT | 2.00 | 6,508.00 | | 0089 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,116 | LNFT | 11.50 | 12,834.00 | | 0090 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.481 | MILE | 4,500.00 | 6,664.50 | | 0091 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.076 | MILE | 2,300.00 | 2,474.80 | | 0092 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.558 | MILE | 4,025.00 | 2,245.95 | | 0093 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 6 | EACH | 315.00 | 1,890.00 | | 0094 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 6 | EACH | 450.00 | 2,700.00 | | 0095 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 19 | EACH | 315.00 | 5,985.00 | | 0096 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 14 | EACH | 315.00 | 4,410.00 | | 0097 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 33 | EACH | 315.00 | 10,395.00 | | 0098 | 732-04-19040 | Plastic Pavement Legends and Symbols (Shield - Interstate) (Preformed Heat Applied Retroreflective Thermoplastic) | 4 | EACH | 1,400.00 | 5,600.00 | | 0099 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) | 1,631.8 | LNFT | 105.00 | 171,339.00 | | 0100 | 733-01-00200 | Concrete Roadway Barrier (Double Faced) | 683.51 | LNFT | 400.00 | 273,404.00 | | 0101 | 736-01-00100 | Trenching and Backfilling | 596 | LNFT | 6.00 | 3,576.00 | | 0102 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 334 | LNFT | 29.00 | 9,686.00 | | 0103 | 736-04-02000 | Signal Support (Pedestal Pole) | 1 | EACH | 2,500.00 | 2,500.00 | | 0104 | 736-04-05009 | Signal Support (45'span, 25' span add-on arm) N/A | 1 | EACH | 19,500.00 | 19,500.00 | | 0105 | 736-04-05012 | Signal Support (45'span, 40' span add-on arm) | 1 | EACH | 9,500.00 | 9,500.00 | | 0106 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 7 | EACH | 1,100.00 | 7,700.00 | | 0107 | 736-05-02060 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) (Arrow Up) | 1 | EACH | 1,450.00 | 1,450.00 | | 0108 | 736-05-02070 | Signal Hds (3 Sec, 12" Led Lens, LT. R, LT. Y, LT. G) | 5 | EACH | 1,000.00 | 5,000.00 | | 0109 | 736-05-02080 | Signal Hds (3 Sec, 12" Led Lens, RT. R, RT. Y, RT. G) | 3 | EACH | 600.00 | 1,800.00 | | 0110 | 736-05-03000 | Signal Heads (4 Section, 12" Led Lens, R, Y, LT. G, G) | 1 | EACH | 1,450.00 | 1,450.00 | | 0111 | 736-06-00600 | Signal Service (Existing Pole) | 1 | EACH | 2,100.00 | 2,100.00 | | 0112 | 736-09-00100 | Loop Detector | 150 | LNFT | 29.00 | 4,350.00 | | 0113 | 736-10-00300 | Underground Junction Box (Type F) | 7 | EACH | 1,100.00 | 7,700.00 | | 0114 | 736-10-00400 | Underground Junction Box (Type G) | 1 | EACH | 1,700.00 | 1,700.00 | | 0115 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 20 | LNFT | 7.00 | 140.00 | | 0116 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 580 | LNFT | 12.00 | 6,960.00 | | 0117 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 20 | LNFT | 9.00 | 180.00 | | 0118 | 736-12-04000 | Conductor (6c, #14 awg) | 425 | LNFT | 4.00 | 1,700.00 | | 0119 | 736-12-06000 | Conductor (10c, #14 awg) | 2,234 | LNFT | 4.00 | 8,936.00 | | 0120 | 739-01-00100 | Hydro-Seeding | 1.09 | ACRE | 1,550.00 | 1,689.50 | | 0121 | 740-01-00100 | Construction Layout | 1 | LUMP | 125,000.00 | 125,000.00 | | 0122 | 804-02-00200 | Treated Timber Piles (Coastal Treatment) | 80 | LNFT | 83.00 | 6,640.00 | | 0123 | 805-01-00200 | Class A Concrete (Pipe Headwalls) | 23.95 | CUYD | 4,400.00 | 105,380.00 | | 0124 | 806-01-00100 | Deformed Reinforcing Steel | 42,226 | LB | 1.50 | 63,339.00 | | 0125 | NS-203-00006 | Exploratory Excavation | 400 | CUYD | 62.00 | 24,800.00 | | 0126 | NS-203-00007 | Temporary Sheeting and Bracing | 1 | LUMP | 1,850.00 | 1,850.00 | | 0127 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 27,210 | INLF | 0.50 | 13,605.00 | | 0128 | NS-502-01000 | Asphalt Concrete | 7,155.4 | TON | 98.00 | 701,229.20 | | 0129 | NS-502-01100 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 617.4 | TON | 98.00 | 60,505.20 | | 0130 | NS-509-01000 | Milling Asphalt Pavement | 14,749 | SQYD | 4.00 | 58,996.00 | | 0131 | NS-509-02000 | Contractor Retained Reclaimed Asphalt Pavement | -820 | CUYD | 10.00 | -8,200.00 | | 0132 | NS-510-01400 | Pavement Patching (12" Minimum Thickness) | 393 | SQYD | 92.00 | 36,156.00 | | 0133 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,765 | INLF | 0.75 | 2,073.75 | | 0134 | NS-701-00002 | Trench Excavation Safety Protection (Depth > 5 feet) | 1,700 | LNFT | 137.00 | 232,900.00 | | 0135 | NS-702-00002 | Cleaning Existing Manhole | 6 | EACH | 620.00 | 3,720.00 | | 0136 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 2 | EACH | 18,000.00 | 36,000.00 | | 0137 | NS-729-00031 | Breakaway Square Tubing Sign Support - Hard Concrete | 6 | EACH | 315.00 | 1,890.00 | | 0138 | NS-736-00001 | GPS | 1 | EACH | 900.00 | 900.00 | | 0139 | NS-736-00005 | Video Detection Cabinet Components | 1 | EACH | 14,500.00 | 14,500.00 | | 0140 | NS-736-00006 | Video Detection Camera | 5 | EACH | 2,400.00 | 12,000.00 | | 0141 | NS-800-00580 | Noise Reduction Systems (LSE - 10' Height) | 15,960 | FTLF | 64.00 | 1,021,440.00 | | 0142 | NS-MSC-00005 | Construction Photographs And Video (Roadway Surfaces) | 1 | LUMP | 7,000.00 | 7,000.00 | | 0143 | NS-MSC-00080 | Detectable Warning System Retrofit for Curb Ramps | 2 | EACH | 350.00 | 700.00 | | 0144 | NS-MSC-00120 | Drainage Structure Paved Gutter Drain | 6 | EACH | 2,400.00 | 14,400.00 | | 0145 | NS-P26-00002 | Control Cabinet and Related Equipment | 1 | EACH | 11,000.00 | 11,000.00 | | 0146 | NS-P26-00021 | Control Cabinet Foundation | 1 | EACH | 5,900.00 | 5,900.00 | | 0147 | NS-P26-00032 | Signal Controller | 2 | EACH | 3,800.00 | 7,600.00 | | 0148 | NS-P26-00076 | Temporary Dam Removal and Replacement | 2 | EACH | 17,500.00 | 35,000.00 | | 0149 | NS-P26-06000 | Fire Hydrants (Jefferson Parish) | 1 | EACH | 4,000.00 | 4,000.00 | | 0150 | NS-P26-06020 | Fittings for Waterlines (DI) (Jefferson Parish) | 3,390 | LB | 3.25 | 11,017.50 | | 0151 | NS-P26-07000 | Gate Valve and Valve Box (8") (Jefferson Parish) | 5 | EACH | 2,700.00 | 13,500.00 | | 0152 | NS-P26-07001 | Gate Valve and Valve Box (6") | 1 | EACH | 2,200.00 | 2,200.00 | | 0153 | NS-P26-12040 | Long Body Transitional Coupling (8") (Jefferson Parish) | 8 | EACH | 260.00 | 2,080.00 | | 0154 | NS-P26-12080 | Long Body Transitional Coupling (12 inch) (Jefferson Parish) | 2 | EACH | 450.00 | 900.00 | | 0155 | NS-P26-18000 | Removal and Disposal of Existing AC Waterline (Jefferson Parish) | 245 | LNFT | 125.00 | 30,625.00 | | 0156 | NS-P26-23040 | Waterline (12" DI) (Restrained) (Jefferson Parish) | 135 | LNFT | 185.00 | 24,975.00 | | 0157 | NS-P26-23060 | Waterline (8" PVC) (Jefferson Parish) | 340 | LNFT | 98.00 | 33,320.00 | | 0158 | NS-P26-23080 | Waterline (12" PVC) (Jefferson Parish) | 60 | LNFT | 125.00 | 7,500.00 | | 0159 | NS-P26-23120 | Waterline (6" PVC) (Restrained) (Jefferson Parish) | 10 | LNFT | 151.00 | 1,510.00 | | 0160 | NS-P26-23141 | Waterline (8" DI) (Restrained) | 445 | LNFT | 125.00 | 55,625.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 7,125,650.20 |
|