Bid Tabulations for the Letting of 4/12/2017 LA DOTD Headquarters

Proposal:H.011007.6
Parish:Jefferson
Description:CITY OF KENNER P.W. NO. 2014-007RB CHATEAU BLVD. RESURFACING
Type Construction:GRADING, MILLING ASPHALT PAVEMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$963,398.76
Rank License BidderConstruction Bid
106276Barriere Construction Co., LLC$695,577.88
200046Barber Bros. Contracting Co., L.L.C$747,425.45
302179Boh Bros. Construction Co., LLC.$756,919.03
462139HUEY P. STOCKSTILL, LLC$837,399.58


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barriere Construction Co., LLC
- 2 -
Barber Bros. Contracting Co., L.L.C
- 3 -
Boh Bros. Construction Co., LLC.
- 4 -
HUEY P. STOCKSTILL, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02020Removal of Asphalt Pavement 1,489.1   SQYD23.0034,249.3018.0026,803.808.0011,912.8012.0017,869.20
0002202-02-06080Removal of Concrete Combination Curb and Gutter 2,960     LNFT5.0014,800.0013.0038,480.004.0011,840.006.0017,760.00
0003202-02-06120Removal of Curbs (Asphalt) 54     LNFT5.00270.0015.00810.004.00216.006.00324.00
0004202-02-38300Removal of Sign and U-Channel Post 51     EACH5.00255.0010.00510.0025.001,275.0025.001,275.00
0005202-02-40120Removal of Traffic Detectors and Associated Equipment 1     LUMP100.00100.003,000.003,000.00500.00500.005,000.005,000.00
0006203-01-00100General Excavation 598     CUYD10.005,980.0020.0011,960.0025.0014,950.0025.0014,950.00
0007203-04-00200Nonplastic Embankment (Sand) 124     CUYD5.00620.0060.007,440.0025.003,100.008.00992.00
0008203-07-00100Borrow (Vehicular Measurement) 102     CUYD75.007,650.0050.005,100.0075.007,650.00110.0011,220.00
0009203-08-00100Geotextile Fabric 662     SQYD0.50331.001.00662.002.501,655.001.50993.00
0010204-02-00100Temporary Hay or Straw Bales 352     EACH3.001,056.005.001,760.0013.004,576.0010.003,520.00
0011204-06-00100Temporary Silt Fencing 7,724     LNFT0.10772.401.007,724.001.5011,586.001.6012,358.40
0012402-01-00100Traffic Maintenance Aggregate (Vehicular Measurement) 50     CUYD0.010.5040.002,000.0015.00750.00100.005,000.00
0013702-04-00200Adjusting Catch Basins 2     EACH500.001,000.002,000.004,000.002,000.004,000.001,650.003,300.00
0014707-03-00100Combination Concrete Curb and Gutter 3,014     LNFT25.0075,350.0027.0081,378.0024.0072,336.0045.00135,630.00
0015713-01-00100Temporary Signs and Barricades 1     LUMP22,000.0022,000.0030,000.0030,000.0035,500.0035,500.0024,800.0024,800.00
0016713-02-00300Temporary Pavement Markings (8" Width) 611     LNFT0.35213.850.25152.750.1061.100.016.11
0017713-02-00500Temporary Pavement Markings (24" Width) 36     LNFT1.5054.001.0036.000.103.600.010.36
0018713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 1.432 MILE500.00716.00300.00429.600.100.14200.00286.40
0019713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 2.916 MILE900.002,624.40500.001,458.000.100.290.010.03
0020713-05-00100Temporary Pavement Legends & Symbols (Arrow) 3     EACH60.00180.0050.00150.001.003.000.010.03
0021713-05-00200Temporary Pavement Legends & Symbols (Double Arrow) 2     EACH60.00120.0050.00100.001.002.000.010.02
0022714-01-00600Slab Sodding (St. Augustine) 1,761     SQYD5.008,805.008.5014,968.506.5011,446.507.7013,559.70
0023727-01-00100Mobilization 1     LUMP69,000.0069,000.0035,000.0035,000.0066,000.0066,000.0083,000.0083,000.00
0024729-01-00102Sign (Type A)(Furnish and Install) 252.3   SQFT5.001,261.5016.004,036.8017.004,289.1020.005,046.00
0025729-02-00102Sign (Type B)(Furnish and Install) 141.5   SQFT5.00707.5022.003,113.0024.003,396.0025.003,537.50
0026729-16-00300Object Marker Assembly (Type 3) 4     EACH92.00368.0090.00360.0090.00360.00100.00400.00
0027729-21-00100U-Channel Post 47     EACH70.003,290.0070.003,290.0075.003,525.0070.003,290.00
0028731-02-00100Reflectorized Raised Pavement Markers 190     EACH10.001,900.0010.001,900.007.001,330.0010.001,900.00
0029731-02-00100Reflectorized Raised Pavement Markers (Blue)12     EACH10.00120.0010.00120.0015.00180.0010.00120.00
0030732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 499     LNFT1.00499.003.251,621.752.00998.003.001,497.00
0031732-01-02040Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) 112     LNFT3.00336.003.75420.005.00560.003.50392.00
0032732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 36     LNFT15.00540.0016.25585.0015.00540.0015.00540.00
0033732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 2.916 MILE4,000.0011,664.004,300.0012,538.804,000.0011,664.004,000.0011,664.00
0034732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.432 MILE1,500.002,148.001,600.002,291.202,000.002,864.001,500.002,148.00
0035732-03-02030Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) 0.017 MILE6,000.00102.003,200.0054.405,000.0085.005,000.0085.00
0036732-04-01040Plastic Pavement Legends and Symbols (Arrow - Double) 2     EACH400.00800.00430.00860.00500.001,000.00400.00800.00
0037732-04-01080Plastic Pavement Legends and Symbols (Arrow - Left Turn) 1     EACH300.00300.00325.00325.00300.00300.00300.00300.00
0038732-04-01100Plastic Pavement Legends and Symbols (Arrow - Right Turn) 2     EACH300.00600.00325.00650.00300.00600.00300.00600.00
0039740-01-00100Construction Layout 1     LUMP8,000.008,000.0010,000.0010,000.004,000.004,000.0014,000.0014,000.00
0040741-11-00100Adjusting Water Valve 1     EACH10.0010.00300.00300.00150.00150.00500.00500.00
0041NS-203-00006Exploratory Excavation 20     CUYD50.001,000.0065.001,300.00125.002,500.00100.002,000.00
0042NS-500-00340Saw Cutting Asphaltic Concrete Pavement 28,643     INLF0.01286.430.4512,889.350.308,592.900.01286.43
0043NS-502-01000Asphalt Concrete 4,050.6   TON80.00324,048.0080.00324,048.0088.00356,452.8086.00348,351.60
0044NS-502-01100Asphalt Concrete, Drives, Turnouts and Miscellaneous 221.1   TON80.0017,688.00125.0027,637.5088.0019,456.8086.0019,014.60
0045NS-507-00003Clean and Seal Ran Cracks in Asph Conc Pave (Hot Poured) 3,000     LNFT1.504,500.001.253,750.001.003,000.001.103,300.00
0046NS-509-01000Milling Asphalt Pavement 25,356     SQYD2.0050,712.002.0050,712.002.0050,712.002.2055,783.20
0048NS-P26-00091Tree Trimming 1     LUMP18,000.0018,000.002,700.002,700.0020,000.0020,000.005,000.005,000.00
0049NS-P26-00092Root Pruning 1     LUMP550.00550.008,000.008,000.001,000.001,000.005,000.005,000.00
             
  CONTRACTOR TOTAL   695,577.88 747,425.45 756,919.03 837,399.58