Proposal:H.012294.6
Parish:Acadia, Evangeline, Iberia, St. Landry, St. Martin, Vermilion
Routes:LA 103, LA 31, LA 96, LA 320, LA 91, LA 93, LA 328, LA 347, LA 333, LA 352, LA 82, LA 95, LA 10, LA 29
Description:DISTRIST 03 LOW COST SAFETY IMPROV.
Type Construction:CLEARING AND GRUBBING, GRADING, SIGNING, PAVEMENT MARKINGS, HIGH FRICTION SURFACING TREATMENT, AND RELATED WORK.
Estimated Construction Cost:$2,524,225.20
| Rank | License | Bidder | Construction Bid |
| 1 | C0001 | Blue Cube Operations LLC | $1,828,672.20 |
| 2 | 51607 | Total Highway Maintenance Llc | $2,186,671.91 |
| 3 | 35849 | T.L. CONSTRUCTION LLC | $2,311,789.60 |
| 4 | 53622 | Deangelo Brothers, LLC | $2,352,936.25 |
| 5 | C0001 | American Civil Constructors West Coast LLC | $2,472,414.10 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Blue Cube Operations LLC | - 2 - Total Highway Maintenance Llc | - 3 - T.L. CONSTRUCTION LLC | - 4 - Deangelo Brothers, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 1,000.00 | 1,000.00 | 20,000.00 | 20,000.00 | 11,000.00 | 11,000.00 | | 0002 | 202-02-38300 | Removal of Sign and U-Channel Post | 91 | EACH | 40.00 | 3,640.00 | 38.00 | 3,458.00 | 46.00 | 4,186.00 | 15.75 | 1,433.25 | | 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 20,000.00 | 20,000.00 | 4,000.00 | 4,000.00 | 20,000.00 | 20,000.00 | 22,000.00 | 22,000.00 | | 0004 | 510-02-00100 | Pavement Widening | 1,764 | SQYD | 80.00 | 141,120.00 | 97.00 | 171,108.00 | 95.00 | 167,580.00 | 106.00 | 186,984.00 | | 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 75,000.00 | 75,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 128,000.00 | 128,000.00 | | 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | 115,000.00 | 115,000.00 | 125,000.00 | 125,000.00 | 34,125.00 | 34,125.00 | | 0007 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 4,516 | SQFT | 20.00 | 90,320.00 | 19.50 | 88,062.00 | 24.00 | 108,384.00 | 17.75 | 80,159.00 | | 0008 | 729-08-00310 | Mounting (5" Size Post)(Structure Mount) | 4 | EACH | 3,500.00 | 14,000.00 | 3,500.00 | 14,000.00 | 4,200.00 | 16,800.00 | 3,150.00 | 12,600.00 | | 0009 | 729-16-00200 | Object Marker Assembly (Type 2) | 16 | EACH | 150.00 | 2,400.00 | 150.00 | 2,400.00 | 180.00 | 2,880.00 | 68.25 | 1,092.00 | | 0010 | 729-22-00200 | Square Tubing Post with 2-1/4" Omni-Directional Anchor | 552 | EACH | 100.00 | 55,200.00 | 95.00 | 52,440.00 | 115.00 | 63,480.00 | 105.00 | 57,960.00 | | 0011 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 16.908 | MILE | 3,600.00 | 60,868.80 | 2,600.00 | 43,960.80 | 5,100.00 | 86,230.80 | 3,775.00 | 63,827.70 | | 0012 | 732-02-02020 | Plastic Pavement Striping (Solid Line) (6" Width) (Thermoplastic 90 mil) | 20.522 | MILE | 4,600.00 | 94,401.20 | 3,500.00 | 71,827.00 | 6,000.00 | 123,132.00 | 6,000.00 | 123,132.00 | | 0013 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.228 | MILE | 1,000.00 | 3,228.00 | 904.00 | 2,918.11 | 2,200.00 | 7,101.60 | 997.50 | 3,219.93 | | 0014 | 732-05-00100 | Removal of Existing Markings | 10.416 | MILE | 3,500.00 | 36,456.00 | 7,000.00 | 72,912.00 | 10,200.00 | 106,243.20 | 3,675.00 | 38,278.80 | | 0015 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 | 25,000.00 | 25,000.00 | 2,000.00 | 2,000.00 | | 0016 | NS-502-04100 | Flexible Pavement High Friction Surfacing Treatment | 63,656 | SQYD | 18.45 | 1,174,453.20 | 23.00 | 1,464,088.00 | 21.00 | 1,336,776.00 | 24.50 | 1,559,572.00 | | 0017 | NS-700-00013 | Inclusion of Traffic Devices in LaSET Database | 1,080 | EACH | 5.25 | 5,670.00 | 5.00 | 5,400.00 | 10.00 | 10,800.00 | 5.50 | 5,940.00 | | 0018 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,183 | EACH | 5.00 | 15,915.00 | 6.00 | 19,098.00 | 12.00 | 38,196.00 | 6.79 | 21,612.57 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,828,672.20 | | 2,186,671.91 | | 2,311,789.60 | | 2,352,936.25 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - American Civil Constructors West Coast LLC | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 12,000.00 | 12,000.00 | | 0002 | 202-02-38300 | Removal of Sign and U-Channel Post | 91 | EACH | 38.00 | 3,458.00 | | 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 20,000.00 | 20,000.00 | | 0004 | 510-02-00100 | Pavement Widening | 1,764 | SQYD | 75.00 | 132,300.00 | | 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 150,000.00 | 150,000.00 | | 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 240,000.00 | 240,000.00 | | 0007 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 4,516 | SQFT | 19.50 | 88,062.00 | | 0008 | 729-08-00310 | Mounting (5" Size Post)(Structure Mount) | 4 | EACH | 3,500.00 | 14,000.00 | | 0009 | 729-16-00200 | Object Marker Assembly (Type 2) | 16 | EACH | 150.00 | 2,400.00 | | 0010 | 729-22-00200 | Square Tubing Post with 2-1/4" Omni-Directional Anchor | 552 | EACH | 95.00 | 52,440.00 | | 0011 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 16.908 | MILE | 3,600.00 | 60,868.80 | | 0012 | 732-02-02020 | Plastic Pavement Striping (Solid Line) (6" Width) (Thermoplastic 90 mil) | 20.522 | MILE | 4,600.00 | 94,401.20 | | 0013 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.228 | MILE | 950.00 | 3,066.60 | | 0014 | 732-05-00100 | Removal of Existing Markings | 10.416 | MILE | 4,000.00 | 41,664.00 | | 0015 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | | 0016 | NS-502-04100 | Flexible Pavement High Friction Surfacing Treatment | 63,656 | SQYD | 24.00 | 1,527,744.00 | | 0017 | NS-700-00013 | Inclusion of Traffic Devices in LaSET Database | 1,080 | EACH | 4.00 | 4,320.00 | | 0018 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,183 | EACH | 6.50 | 20,689.50 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,472,414.10 |
|