Bid Tabulations for the Letting of 11/16/2016 LA DOTD Headquarters

Proposal:H.009277.6
Parish:Lincoln
Description:GRAMBLING SR2S PROJECT
Type Construction:SIDEWALKS, GRADING, DRAINAGE STRUCTURES, PAVEMENT MARKINGS AND RELATED WORK.
Estimated Construction Cost:$246,355.80
Rank License BidderConstruction Bid
118546C W & W Contractors, Inc.$231,408.00
239001JD's Rebar & Construction Inc.$269,297.22
332563The Mabry Company Llc$277,184.00
454549Chad Pody Construction Company, LLC$339,710.00


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
C W & W Contractors, Inc.
- 2 -
JD's Rebar & Construction Inc.
- 3 -
The Mabry Company Llc
- 4 -
Chad Pody Construction Company, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP5,000.005,000.003,336.113,336.112,500.002,500.0015,000.0015,000.00
0002202-02-02000Removal of Asphalt Drives 7     SQYD20.00140.00341.232,388.6120.00140.0050.00350.00
0003202-02-06100Removal of Concrete Walks and Drives 27     SQYD20.00540.0095.242,571.4820.00540.0060.001,620.00
0004202-02-06140Removal of Curbs (Concrete) 15     LNFT20.00300.0078.911,183.6520.00300.0010.00150.00
0005202-02-32180Removal of Pipe Headwalls 1     EACH1,500.001,500.001,075.681,075.681,000.001,000.001,500.001,500.00
0006203-05-00100Excavation and Embankment 1     LUMP10,000.0010,000.004,342.584,342.5820,000.0020,000.0030,000.0030,000.00
0007204-02-00100Temporary Hay or Straw Bales 40     EACH17.75710.0064.012,560.4015.00600.0015.00600.00
0008204-06-00100Temporary Silt Fencing 3,486     LNFT2.006,972.003.0010,458.003.0010,458.002.006,972.00
0009701-03-01000Storm Drain Pipe (15" RCP/PP) 30     LNFT40.001,200.00125.143,754.2075.002,250.0081.002,430.00
0010701-03-01020Storm Drain Pipe (18" RCP/PP) 76     LNFT45.003,420.0087.906,680.4085.006,460.0082.006,232.00
0011701-07-00200Yard Drain Pipe (6") 20     LNFT20.00400.00162.253,245.0030.00600.0075.001,500.00
0012701-10-01040Reinforced Concrete Pipe (Extension) (18") 28     LNFT55.001,540.00135.453,792.60125.003,500.00150.004,200.00
0013701-10-01060Reinforced Concrete Pipe (Extension) (24") 16     LNFT70.001,120.00238.173,810.72135.002,160.00175.002,800.00
0014701-15-00100Concrete Collar 3     EACH1,000.003,000.001,443.994,331.97750.002,250.001,300.003,900.00
0015702-03-00100Catch Basins (CB-01) 3     EACH2,500.007,500.003,043.649,130.923,000.009,000.003,500.0010,500.00
0016702-04-00100Adjusting Manholes 3     EACH1,500.004,500.001,937.115,811.33900.002,700.001,700.005,100.00
0017706-01-00100Concrete Walk (4" Thick) 1,853.4   SQYD45.0083,403.0031.4658,307.9650.0092,670.0060.00111,204.00
0018706-01-00300Concrete Walk (6" Thick) 6.7   SQYD70.00469.00428.822,873.0955.00368.5075.00502.50
0019706-02-00200Concrete Drive (6" Thick) 119.1   SQYD70.008,337.0053.336,351.6055.006,550.5080.009,528.00
0020706-04-00100Handicapped Curb Ramps 9     EACH1,000.009,000.001,443.9912,995.91900.008,100.002,500.0022,500.00
0021713-01-00100Temporary Signs and Barricades 1     LUMP10,000.0010,000.0012,444.9212,444.9210,000.0010,000.0010,000.0010,000.00
0022715-01-00100Topsoil 120     CUYD25.003,000.0022.632,715.6020.002,400.0060.007,200.00
0023726-01-00100Bedding Material 17.4   CUYD100.001,740.00107.481,870.15100.001,740.0095.001,653.00
0024727-01-00100Mobilization 1     LUMP25,000.0025,000.0056,567.8056,567.8057,000.0057,000.0029,000.0029,000.00
0025729-01-00100Sign (Type A) 39.5   SQFT50.001,975.0033.941,340.6350.001,975.0045.001,777.50
0026729-21-00100U-Channel Post 5     EACH125.00625.00152.73763.65125.00625.00100.00500.00
0027731-02-00100Reflectorized Raised Pavement Markers 17     EACH75.001,275.0073.541,250.1865.001,105.0065.001,105.00
0028732-01-01000Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) 412     LNFT25.0010,300.0020.938,623.1620.008,240.0020.008,240.00
0029732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 184     LNFT60.0011,040.0055.4410,200.9650.009,200.0052.009,568.00
0030739-01-00100Hydro-Seeding 1.7   ACRE1,500.002,550.001,810.173,077.293,000.005,100.008,000.0013,600.00
0031740-01-00100Construction Layout 1     LUMP10,000.0010,000.0013,576.2713,576.274,500.004,500.0011,000.0011,000.00
0032741-11-00200Adjusting Water Valve and Meter Box 2     EACH700.001,400.00906.501,813.00600.001,200.00750.001,500.00
0033NS-500-00340Saw Cutting Asphaltic Concrete Pavement 92     INLF2.00184.003.39311.882.00184.0010.00920.00
0034NS-600-00220Saw Cutting Portland Cement Concrete Pavement 384     INLF2.00768.004.531,739.522.00768.0012.004,608.00
0035NS-ENH-20100Trench Drains Metal10     LNFT250.002,500.00400.004,000.00100.001,000.00245.002,450.00
             
  CONTRACTOR TOTAL   231,408.00 269,297.22 277,184.00 339,710.00