Proposal:H.002048.6
Parish:Vermilion
Routes:LA 82
Description:LA 82 BRIDGES NEAR ESTHER
Type Construction:Clearing and Grubbing, Grading, Drainage Structures, Cold Planing Asphaltic Concrete, Class II Base Course, Lime Treatment, Superpave Asphaltic Concrete Overlay, Bridge Replacement, and Related Work.
Estimated Construction Cost:$2,971,060.15
| Rank | License | Bidder | Construction Bid |
| 1 | 39462 | JB JAMES CONSTRUCTION LLC | $3,887,201.15 |
| 2 | 00044 | GUINN CONSTRUCTION, LLC | $4,110,846.85 |
| 3 | 00481 | COASTAL BRIDGE CO., L.L.C. | $4,464,789.84 |
| 4 | 56994 | MATT L GUINN CONSTRUCTION, LLC | $4,814,842.54 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - JB JAMES CONSTRUCTION LLC | - 2 - GUINN CONSTRUCTION, LLC | - 3 - COASTAL BRIDGE CO., L.L.C. | - 4 - MATT L GUINN CONSTRUCTION, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 3.5 | LUMP | 380,000.00 | 380,000.00 | 150,000.00 | 150,000.00 | 200,000.00 | 200,000.00 | 155,000.00 | 155,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 100,000.00 | 100,000.00 | 8,000.00 | 8,000.00 | | 0003 | 202-02-04000 | Removal of Bridge (39'x26' Timber Bridge) (Site 1) | 1 | EACH | 29,500.00 | 29,500.00 | 25,000.00 | 25,000.00 | 100,000.00 | 100,000.00 | 25,500.00 | 25,500.00 | | 0004 | 202-02-04000 | Removal of Bridge (59'X26' Timber Bridge)(Site 2) | 1 | EACH | 42,500.00 | 42,500.00 | 45,000.00 | 45,000.00 | 125,000.00 | 125,000.00 | 35,500.00 | 35,500.00 | | 0005 | 202-02-12000 | Removal of Fence | 623 | LNFT | 4.00 | 2,492.00 | 10.00 | 6,230.00 | 9.00 | 5,607.00 | 6.00 | 3,738.00 | | 0006 | 202-02-14500 | Removal of Guard Rail | 1,136 | LNFT | 9.00 | 10,224.00 | 4.00 | 4,544.00 | 12.50 | 14,200.00 | 15.00 | 17,040.00 | | 0007 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 2,032.2 | SQYD | 5.05 | 10,262.61 | 6.00 | 12,193.20 | 10.00 | 20,322.00 | 7.50 | 15,241.50 | | 0008 | 203-01-00100 | General Excavation | 2,763 | CUYD | 5.80 | 16,025.40 | 8.50 | 23,485.50 | 12.00 | 33,156.00 | 12.50 | 34,537.50 | | 0009 | 203-02-00100 | Drainage Excavation | 275 | CUYD | 5.80 | 1,595.00 | 25.00 | 6,875.00 | 68.00 | 18,700.00 | 15.00 | 4,125.00 | | 0010 | 203-03-00100 | Embankment | 4,303 | CUYD | 17.36 | 74,700.08 | 25.00 | 107,575.00 | 22.00 | 94,666.00 | 28.50 | 122,635.50 | | 0011 | 203-04-00200 | Nonplastic Embankment (Sand) | 1,841 | CUYD | 22.70 | 41,790.70 | 30.00 | 55,230.00 | 25.00 | 46,025.00 | 30.00 | 55,230.00 | | 0012 | 203-04-00300 | Nonplastic Embankment (Stone) | 308 | CUYD | 82.74 | 25,483.92 | 125.00 | 38,500.00 | 135.00 | 41,580.00 | 105.00 | 32,340.00 | | 0013 | 203-07-00300 | Borrow (Vehicular Measurement) (Plastic Soils) | 453 | CUYD | 9.08 | 4,113.24 | 20.00 | 9,060.00 | 30.00 | 13,590.00 | 30.00 | 13,590.00 | | 0014 | 203-08-00100 | Geotextile Fabric | 2,177 | SQYD | 1.11 | 2,416.47 | 3.00 | 6,531.00 | 2.50 | 5,442.50 | 5.00 | 10,885.00 | | 0015 | 204-02-00100 | Temporary Hay or Straw Bales | 56 | EACH | 12.00 | 672.00 | 50.00 | 2,800.00 | 12.00 | 672.00 | 40.00 | 2,240.00 | | 0016 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 125.00 | 2,000.00 | 250.00 | 4,000.00 | 125.00 | 2,000.00 | 150.00 | 2,400.00 | | 0017 | 204-06-00100 | Temporary Silt Fencing | 3,182 | LNFT | 2.19 | 6,968.58 | 4.00 | 12,728.00 | 1.75 | 5,568.50 | 3.75 | 11,932.50 | | 0018 | 302-02-03080 | Class II Base Course (8" Thick) (Asphaltic Concrete Base on Embankment Layer) | 188 | SQYD | 63.07 | 11,857.16 | 75.00 | 14,100.00 | 60.00 | 11,280.00 | 115.00 | 21,620.00 | | 0019 | 302-02-04121 | Class II Base Course (8 1/2" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 4,871.8 | SQYD | 21.44 | 104,451.39 | 30.00 | 146,154.00 | 40.00 | 194,872.00 | 36.50 | 177,820.70 | | 0020 | 304-05-00100 | Lime Treatment (Type E) | 71.73 | TON | 481.00 | 34,502.13 | 700.00 | 50,211.00 | 350.00 | 25,105.50 | 650.00 | 46,624.50 | | 0021 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 30 | CUYD | 48.44 | 1,453.20 | 125.00 | 3,750.00 | 100.00 | 3,000.00 | 100.00 | 3,000.00 | | 0022 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 50.45 | 5,045.00 | 75.00 | 7,500.00 | 50.00 | 5,000.00 | 100.00 | 10,000.00 | | 0023 | 502-01-00100 | Superpave Asphaltic Concrete | 1,512.6 | TON | 125.00 | 189,075.00 | 125.00 | 189,075.00 | 100.00 | 151,260.00 | 160.00 | 242,016.00 | | 0024 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 601.2 | TON | 140.00 | 84,168.00 | 150.00 | 90,180.00 | 120.00 | 72,144.00 | 170.00 | 102,204.00 | | 0025 | 509-01-00100 | Cold Planing Asphaltic Pavement | 2,367 | SQYD | 8.00 | 18,936.00 | 7.00 | 16,569.00 | 3.00 | 7,101.00 | 9.00 | 21,303.00 | | 0026 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -191 | CUYD | 0.01 | -1.91 | 0.00 | 0.00 | 0.01 | -1.91 | 0.01 | -1.91 | | 0027 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 106 | LNFT | 57.01 | 6,043.06 | 65.00 | 6,890.00 | 55.00 | 5,830.00 | 60.00 | 6,360.00 | | 0028 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 1,082 | LNFT | 82.24 | 88,983.68 | 95.00 | 102,790.00 | 81.00 | 87,642.00 | 140.00 | 151,480.00 | | 0029 | 701-03-02040 | Storm Drain Pipe (Outfall) (24" PP or 30" CMP) | 400 | LNFT | 82.24 | 32,896.00 | 95.00 | 38,000.00 | 110.00 | 44,000.00 | 140.00 | 56,000.00 | | 0030 | 701-09-00100 | Fabricating Pipe Fittings | 9 | EACH | 474.27 | 4,268.43 | 1,000.00 | 9,000.00 | 1,000.00 | 9,000.00 | 1,700.00 | 15,300.00 | | 0031 | 702-03-00100 | Catch Basins (CB-01) | 9 | EACH | 2,542.89 | 22,886.01 | 4,500.00 | 40,500.00 | 2,750.00 | 24,750.00 | 5,500.00 | 49,500.00 | | 0032 | 702-08-00100 | Side Drain Safety End (Type I) | 2 | EACH | 2,078.71 | 4,157.42 | 3,000.00 | 6,000.00 | 2,050.00 | 4,100.00 | 5,000.00 | 10,000.00 | | 0033 | 704-03-00100 | Blocked Out Guard Rail | 387.5 | LNFT | 20.00 | 7,750.00 | 25.00 | 9,687.50 | 25.00 | 9,687.50 | 28.50 | 11,043.75 | | 0034 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 61.00 | 12,200.00 | 70.00 | 14,000.00 | 73.00 | 14,600.00 | 75.00 | 15,000.00 | | 0035 | 704-11-00100 | Guard Rail End Treatment (Flared) | 1 | EACH | 2,050.00 | 2,050.00 | 2,500.00 | 2,500.00 | 3,000.00 | 3,000.00 | 2,800.00 | 2,800.00 | | 0036 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 7 | EACH | 2,450.00 | 17,150.00 | 2,850.00 | 19,950.00 | 3,000.00 | 21,000.00 | 2,800.00 | 19,600.00 | | 0037 | 705-01-00100 | Barbed Wire Fence | 623 | LNFT | 12.00 | 7,476.00 | 15.00 | 9,345.00 | 15.00 | 9,345.00 | 8.50 | 5,295.50 | | 0038 | 708-01-00100 | Right-of-Way Monument | 24 | EACH | 165.00 | 3,960.00 | 275.00 | 6,600.00 | 250.00 | 6,000.00 | 400.00 | 9,600.00 | | 0039 | 708-02-00100 | Right-of-Way Monument Witness Post | 24 | EACH | 165.00 | 3,960.00 | 275.00 | 6,600.00 | 250.00 | 6,000.00 | 400.00 | 9,600.00 | | 0040 | 712-04-00100 | Flexible Revetment | 750 | SQYD | 63.00 | 47,250.00 | 95.00 | 71,250.00 | 72.00 | 54,000.00 | 74.50 | 55,875.00 | | 0041 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 30,000.00 | 30,000.00 | 60,000.00 | 60,000.00 | 75,000.00 | 75,000.00 | 80,000.00 | 80,000.00 | | 0042 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 220 | LNFT | 2.00 | 440.00 | 4.00 | 880.00 | 1.20 | 264.00 | 4.50 | 990.00 | | 0043 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 24 | LNFT | 0.50 | 12.00 | 1.00 | 24.00 | 6.00 | 144.00 | 3.00 | 72.00 | | 0044 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 10 | EACH | 8.00 | 80.00 | 20.00 | 200.00 | 13.00 | 130.00 | 15.00 | 150.00 | | 0045 | 716-01-00100 | Mulch (Vegetative) | 4 | TON | 980.00 | 3,920.00 | 1,000.00 | 4,000.00 | 980.00 | 3,920.00 | 2,500.00 | 10,000.00 | | 0046 | 717-01-00100 | Seeding | 54 | LB | 15.00 | 810.00 | 35.00 | 1,890.00 | 15.00 | 810.00 | 20.00 | 1,080.00 | | 0047 | 718-01-00100 | Fertilizer | 1,800 | LB | 0.80 | 1,440.00 | 1.50 | 2,700.00 | 0.80 | 1,440.00 | 3.00 | 5,400.00 | | 0048 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | 35,000.00 | 35,000.00 | 20,000.00 | 20,000.00 | | 0049 | 725-01-00100 | Temporary Detour Roads | 4,954.2 | SQYD | 80.00 | 396,336.00 | 98.00 | 485,511.60 | 145.00 | 718,359.00 | 125.00 | 619,275.00 | | 0050 | 725-02-00100 | Temporary Detour Bridging | 140 | LNFT | 6,607.00 | 924,980.00 | 3,750.00 | 525,000.00 | 2,720.00 | 380,800.00 | 4,500.00 | 630,000.00 | | 0051 | 726-01-00100 | Bedding Material | 153.2 | CUYD | 58.73 | 8,997.44 | 100.00 | 15,320.00 | 160.00 | 24,512.00 | 150.00 | 22,980.00 | | 0052 | 727-01-00100 | Mobilization | 1 | LUMP | 190,000.00 | 190,000.00 | 325,000.00 | 325,000.00 | 439,000.00 | 439,000.00 | 425,000.00 | 425,000.00 | | 0053 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 80.00 | 640.00 | 100.00 | 800.00 | 70.00 | 560.00 | 150.00 | 1,200.00 | | 0054 | 731-02-00100 | Reflectorized Raised Pavement Markers | 100 | EACH | 9.00 | 900.00 | 20.00 | 2,000.00 | 13.00 | 1,300.00 | 15.00 | 1,500.00 | | 0055 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 7,628 | LNFT | 1.00 | 7,628.00 | 1.50 | 11,442.00 | 2.40 | 18,307.20 | 1.50 | 11,442.00 | | 0056 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 19 | LNFT | 18.00 | 342.00 | 25.00 | 475.00 | 30.00 | 570.00 | 25.00 | 475.00 | | 0057 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.229 | MILE | 2,511.00 | 575.02 | 5,000.00 | 1,145.00 | 5,700.00 | 1,305.30 | 4,500.00 | 1,030.50 | | 0058 | 732-05-00100 | Removal of Existing Markings | 0.114 | MILE | 6,272.00 | 715.01 | 13,000.00 | 1,482.00 | 23,000.00 | 2,622.00 | 8,500.00 | 969.00 | | 0059 | 740-01-00100 | Construction Layout | 1 | LUMP | 40,000.00 | 40,000.00 | 60,000.00 | 60,000.00 | 60,000.00 | 60,000.00 | 80,000.00 | 80,000.00 | | 0060 | 803-05-00100 | Temporary Sheeting | 1 | LUMP | 77,000.00 | 77,000.00 | 45,000.00 | 45,000.00 | 50,000.00 | 50,000.00 | 185,000.00 | 185,000.00 | | 0061 | 804-01-00300 | Precast Concrete Piles (16") | 2,352 | LNFT | 75.00 | 176,400.00 | 80.00 | 188,160.00 | 81.00 | 190,512.00 | 75.00 | 176,400.00 | | 0062 | 804-12-00100 | Loading Permanent Piles | 2 | EACH | 2,500.00 | 5,000.00 | 1.00 | 2.00 | 150.00 | 300.00 | 1.00 | 2.00 | | 0063 | 805-02-00400 | Class A(M) Concrete (Bents) | 67.9 | CUYD | 1,500.00 | 101,850.00 | 1,850.00 | 125,615.00 | 2,600.00 | 176,540.00 | 1,800.00 | 122,220.00 | | 0064 | 805-04-00100 | Class AA(M) Concrete | 250.6 | CUYD | 700.00 | 175,420.00 | 1,600.00 | 400,960.00 | 1,200.00 | 300,720.00 | 1,500.00 | 375,900.00 | | 0065 | 805-06-00100 | Class R Concrete | 24.72 | CUYD | 1,000.00 | 24,720.00 | 1,000.00 | 24,720.00 | 400.00 | 9,888.00 | 500.00 | 12,360.00 | | 0066 | 806-01-00100 | Deformed Reinforcing Steel | 64,373 | LB | 1.50 | 96,559.50 | 1.25 | 80,466.25 | 1.25 | 80,466.25 | 1.50 | 96,559.50 | | 0067 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 280 | LNFT | 100.00 | 28,000.00 | 165.00 | 46,200.00 | 120.00 | 33,600.00 | 120.00 | 33,600.00 | | 0068 | 813-01-00100 | Concrete Approach Slabs | 728.88 | SQYD | 223.00 | 162,540.24 | 285.00 | 207,730.80 | 250.00 | 182,220.00 | 300.00 | 218,664.00 | | 0069 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 156 | LNFT | 7.06 | 1,101.36 | 20.00 | 3,120.00 | 10.00 | 1,560.00 | 5.50 | 858.00 | | 0070 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 5 | TON | 350.00 | 1,750.00 | 500.00 | 2,500.00 | 150.00 | 750.00 | 500.00 | 2,500.00 | | 0071 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 95 | INLF | 3.03 | 287.85 | 21.00 | 1,995.00 | 2.00 | 190.00 | 3.00 | 285.00 | | 0072 | NS-701-00002 | Trench Excavation Safety Protection (Depth > 5 feet) | 907 | LNFT | 14.88 | 13,496.16 | 15.00 | 13,605.00 | 8.00 | 7,256.00 | 65.00 | 58,955.00 | | 0073 | NS-713-00008 | Portable Changeable Message Sign | 2 | EACH | 7,500.00 | 15,000.00 | 20,000.00 | 40,000.00 | 25,000.00 | 50,000.00 | 10,000.00 | 20,000.00 | | 0074 | NS-804-00001 | Vibration Monitoring | 1 | EACH | 2,500.00 | 2,500.00 | 10,000.00 | 10,000.00 | 6,500.00 | 6,500.00 | 3,000.00 | 3,000.00 | | 0075 | NS-804-00002 | Construction Site Survey | 1 | LUMP | 6,500.00 | 6,500.00 | 12,500.00 | 12,500.00 | 15,000.00 | 15,000.00 | 5,000.00 | 5,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,887,201.15 | | 4,110,846.85 | | 4,464,789.84 | | 4,814,842.54 |
|