Proposal:H.011482.6
Parish:Jefferson
Routes:US 90
Description:US 90 HUEY P. LONG BRIDGE CLEAN & PAINT
Type Construction:CLEANING, PAINTING, AND DISPOSAL (NEAR WHITE FINISH), AND RELATED WORK.
Estimated Construction Cost:$20,778,632.50
Maximum Number of Days Allowed for Construction:970
Calculated Daily User Cost:$5,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 55663 | Intech Contracting, LLC | $19,776,914.50 | 240.00 | $20,976,914.50 |
| 2 | 28182 | Liberty Maintenance, Inc. | $19,717,977.40 | 400.00 | $21,717,977.40 |
| 3 | 57588 | NORTH STAR PAINTING COMPANY, INC. | $20,611,894.50 | 300.00 | $22,111,894.50 |
| 4 | 46474 | Alpha Painting & Constr. Co., Inc. | $22,696,559.00 | 545.00 | $25,421,559.00 |
| 5 | 39452 | M&J CONST CO OF PINELLAS COUNTY INC | $29,112,963.40 | 920.00 | $33,712,963.40 |
| 6 | 24429 | Abhe & Svoboda, Inc. | $34,477,770.00 | 540.00 | $37,177,770.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Intech Contracting, LLC | - 2 - Liberty Maintenance, Inc. | - 3 - NORTH STAR PAINTING COMPANY, INC. | - 4 - Alpha Painting & Constr. Co., Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 95,000.00 | 95,000.00 | 25,200.00 | 25,200.00 | 45,000.00 | 45,000.00 | 50,000.00 | 50,000.00 | | 0002 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 4.216 | MILE | 14,000.00 | 59,024.00 | 16,800.00 | 70,828.80 | 14,000.00 | 59,024.00 | 20,000.00 | 84,320.00 | | 0003 | 713-08-00100 | Temporary Precast Concrete Barrier (Department Furnished) | 340 | EACH | 515.00 | 175,100.00 | 500.00 | 170,000.00 | 515.00 | 175,100.00 | 300.00 | 102,000.00 | | 0004 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 15,000.00 | 15,000.00 | 50,000.00 | 50,000.00 | 25,000.00 | 25,000.00 | 100,000.00 | 100,000.00 | | 0005 | 727-01-00100 | Mobilization | 1 | LUMP | 1,950,000.00 | 1,950,000.00 | 1,900,000.00 | 1,900,000.00 | 1,000,000.00 | 1,000,000.00 | 2,060,000.00 | 2,060,000.00 | | 0006 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,329 | EACH | 7.50 | 17,467.50 | 9.00 | 20,961.00 | 7.50 | 17,467.50 | 17.00 | 39,593.00 | | 0007 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 2.672 | MILE | 7,500.00 | 20,040.00 | 9,000.00 | 24,048.00 | 7,500.00 | 20,040.00 | 11,500.00 | 30,728.00 | | 0008 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 2.672 | MILE | 4,000.00 | 10,688.00 | 4,800.00 | 12,825.60 | 4,000.00 | 10,688.00 | 11,500.00 | 30,728.00 | | 0009 | 732-05-00100 | Removal of Existing Markings | 1.973 | MILE | 15,000.00 | 29,595.00 | 18,000.00 | 35,514.00 | 15,000.00 | 29,595.00 | 30,000.00 | 59,190.00 | | 0010 | NS-700-00180 | Impact Attenuator (Construction Zone) | 2 | EACH | 2,500.00 | 5,000.00 | 10,800.00 | 21,600.00 | 5,000.00 | 10,000.00 | 15,000.00 | 30,000.00 | | 0011 | NS-700-00182 | Repair and Restoration of Impact Attenuator (Const Zone) | 2 | EACH | 5,000.00 | 10,000.00 | 3,000.00 | 6,000.00 | 9,500.00 | 19,000.00 | 10,000.00 | 20,000.00 | | 0012 | NS-713-00008 | Portable Changeable Message Sign | 2 | EACH | 15,000.00 | 30,000.00 | 10,000.00 | 20,000.00 | 490.00 | 980.00 | 15,000.00 | 30,000.00 | | 0013 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) (Pier A to Pier I) | 1 | LUMP | 3,500,000.00 | 3,500,000.00 | 3,300,000.00 | 3,300,000.00 | 4,100,000.00 | 4,100,000.00 | 4,250,000.00 | 4,250,000.00 | | 0014 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) (Pier I to Pier II) | 1 | LUMP | 6,460,000.00 | 6,460,000.00 | 6,945,000.00 | 6,945,000.00 | 6,100,000.00 | 6,100,000.00 | 6,750,000.00 | 6,750,000.00 | | 0015 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) (Pier II to Pier III) | 1 | LUMP | 3,500,000.00 | 3,500,000.00 | 3,300,000.00 | 3,300,000.00 | 4,100,000.00 | 4,100,000.00 | 4,250,000.00 | 4,250,000.00 | | 0016 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) (Pier III to Pier IV) | 1 | LUMP | 3,500,000.00 | 3,500,000.00 | 3,148,000.00 | 3,148,000.00 | 3,900,000.00 | 3,900,000.00 | 3,850,000.00 | 3,850,000.00 | | 0017 | NS-805-00016 | Bridge Superstructure Repair (Cleaning & Painting of Roadway Barriers) | 4 | EACH | 100,000.00 | 400,000.00 | 167,000.00 | 668,000.00 | 250,000.00 | 1,000,000.00 | 240,000.00 | 960,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 19,776,914.50 | | 19,717,977.40 | | 20,611,894.50 | | 22,696,559.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - M&J CONST CO OF PINELLAS COUNTY INC | - 6 - Abhe & Svoboda, Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 135,240.00 | 135,240.00 | 18,175.00 | 18,175.00 | | 0002 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 4.216 | MILE | 16,800.00 | 70,828.80 | 2,700.00 | 11,383.20 | | 0003 | 713-08-00100 | Temporary Precast Concrete Barrier (Department Furnished) | 340 | EACH | 618.00 | 210,120.00 | 597.00 | 202,980.00 | | 0004 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 80,000.00 | 80,000.00 | 11,700.00 | 11,700.00 | | 0005 | 727-01-00100 | Mobilization | 1 | LUMP | 2,647,994.00 | 2,647,994.00 | 3,447,775.00 | 3,447,775.00 | | 0006 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,329 | EACH | 9.00 | 20,961.00 | 5.70 | 13,275.30 | | 0007 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 2.672 | MILE | 9,000.00 | 24,048.00 | 5,700.00 | 15,230.40 | | 0008 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 2.672 | MILE | 4,800.00 | 12,825.60 | 3,700.00 | 9,886.40 | | 0009 | 732-05-00100 | Removal of Existing Markings | 1.973 | MILE | 18,000.00 | 35,514.00 | 4,070.00 | 8,030.11 | | 0010 | NS-700-00180 | Impact Attenuator (Construction Zone) | 2 | EACH | 6,000.00 | 12,000.00 | 8,700.00 | 17,400.00 | | 0011 | NS-700-00182 | Repair and Restoration of Impact Attenuator (Const Zone) | 2 | EACH | 11,400.00 | 22,800.00 | 8,700.00 | 17,400.00 | | 0012 | NS-713-00008 | Portable Changeable Message Sign | 2 | EACH | 18,816.00 | 37,632.00 | 12,675.00 | 25,350.00 | | 0013 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) (Pier A to Pier I) | 1 | LUMP | 5,501,160.00 | 5,501,160.00 | 6,052,490.35 | 6,052,490.35 | | 0014 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) (Pier I to Pier II) | 1 | LUMP | 8,226,960.00 | 8,226,960.00 | 10,844,075.00 | 10,844,075.00 | | 0015 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) (Pier II to Pier III) | 1 | LUMP | 5,525,940.00 | 5,525,940.00 | 6,052,374.24 | 6,052,374.24 | | 0016 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) (Pier III to Pier IV) | 1 | LUMP | 5,525,940.00 | 5,525,940.00 | 6,632,470.00 | 6,632,470.00 | | 0017 | NS-805-00016 | Bridge Superstructure Repair (Cleaning & Painting of Roadway Barriers) | 4 | EACH | 255,750.00 | 1,023,000.00 | 274,443.75 | 1,097,775.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 29,112,963.40 | | 34,477,770.00 |
|