Proposal:H.011760.6
Parish:Orleans
Description:Path to Progress - Franklin Avenue
Type Construction:COLD PLANE ASPHALTIC CONCRETE, ASPHALTIC CONCRETE OVERLAY. CONCRETE PAVEMENT REPAIR, STRIPING, CONCRETE ADA RAMPS AND RELATED WORK.
Estimated Construction Cost:$1,271,536.48
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$5,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 24901 | Hard Rock Construction LLC | $1,222,323.73 | 25.00 | $1,347,323.73 |
| 2 | 48896 | Command Construction Industries LLC | $1,346,879.35 | 55.00 | $1,621,879.35 |
| 3 | 60022 | D. O'BRIAN CONSTRUCTION, LLC | $1,482,430.23 | 40.00 | $1,682,430.23 |
| 4 | 06276 | BARRIERE CONSTRUCTION CO., LLC. | $1,548,532.69 | 43.00 | $1,763,532.69 |
| 5 | 02179 | Boh Bros. Construction Co., LLC. | $1,441,957.49 | 70.00 | $1,791,957.49 |
| 6 | 38610 | Three C's Properties Inc | $1,431,521.60 | 75.00 | $1,806,521.60 |
| 7 | 57835 | Roubion Roads & Streets LLC | $1,521,906.48 | 75.00 | $1,896,906.48 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Hard Rock Construction LLC | - 2 - Command Construction Industries LLC | - 3 - D. O'BRIAN CONSTRUCTION, LLC | - 4 - BARRIERE CONSTRUCTION CO., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 139 | SQYD | 20.00 | 2,780.00 | 10.00 | 1,390.00 | 12.00 | 1,668.00 | 11.00 | 1,529.00 | | 0002 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 200 | CUYD | 10.00 | 2,000.00 | 1.00 | 200.00 | 40.00 | 8,000.00 | 1.00 | 200.00 | | 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 4.22 | TON | 500.00 | 2,110.00 | 300.00 | 1,266.00 | 380.00 | 1,603.60 | 500.00 | 2,110.00 | | 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 38.33 | SQYD | 20.00 | 766.60 | 10.00 | 383.30 | 200.00 | 7,666.00 | 100.00 | 3,833.00 | | 0005 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 38.33 | SQYD | 150.00 | 5,749.50 | 75.00 | 2,874.75 | 150.00 | 5,749.50 | 180.00 | 6,899.40 | | 0006 | 602-02-00100 | Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints | 4,500 | LNFT | 1.50 | 6,750.00 | 1.00 | 4,500.00 | 2.25 | 10,125.00 | 1.50 | 6,750.00 | | 0007 | 602-03-00100 | Cleaning and Sealing Random cracks | 3,000 | LNFT | 2.25 | 6,750.00 | 2.00 | 6,000.00 | 2.25 | 6,750.00 | 3.50 | 10,500.00 | | 0008 | 706-01-00100 | Concrete Walk (4" Thick) | 293.7 | SQYD | 75.00 | 22,027.50 | 70.00 | 20,559.00 | 55.00 | 16,153.50 | 72.00 | 21,146.40 | | 0009 | 706-01-00300 | Concrete Walk (6" Thick) | 3 | SQYD | 100.00 | 300.00 | 100.00 | 300.00 | 65.00 | 195.00 | 80.00 | 240.00 | | 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 22,000.00 | 22,000.00 | 150,000.00 | 150,000.00 | 33,000.00 | 33,000.00 | 84,000.00 | 84,000.00 | | 0011 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 500 | LNFT | 2.00 | 1,000.00 | 2.00 | 1,000.00 | 4.00 | 2,000.00 | 0.30 | 150.00 | | 0012 | 719-01-01080 | Plants (Tree) (Balled and Burlapped) (3" cal) Crape Myrtle | 10 | EACH | 500.00 | 5,000.00 | 500.00 | 5,000.00 | 650.00 | 6,500.00 | 490.00 | 4,900.00 | | 0013 | 719-01-01080 | Plants (Tree) (Balled and Burlapped) (3" cal) Live Oak | 18 | EACH | 500.00 | 9,000.00 | 650.00 | 11,700.00 | 725.00 | 13,050.00 | 490.00 | 8,820.00 | | 0014 | 727-01-00100 | Mobilization | 1 | LUMP | 66,000.00 | 66,000.00 | 150,000.00 | 150,000.00 | 68,000.00 | 68,000.00 | 148,000.00 | 148,000.00 | | 0015 | 729-01-00100 | Sign (Type A) | 24 | SQFT | 23.00 | 552.00 | 30.00 | 720.00 | 70.00 | 1,680.00 | 24.00 | 576.00 | | 0016 | 729-21-00100 | U-Channel Post | 6 | EACH | 100.00 | 600.00 | 250.00 | 1,500.00 | 150.00 | 900.00 | 100.00 | 600.00 | | 0017 | 731-02-00100 | Reflectorized Raised Pavement Markers | 83 | EACH | 21.00 | 1,743.00 | 20.00 | 1,660.00 | 25.00 | 2,075.00 | 16.00 | 1,328.00 | | 0018 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 4,823 | LNFT | 2.75 | 13,263.25 | 3.00 | 14,469.00 | 2.25 | 10,851.75 | 1.60 | 7,716.80 | | 0019 | 732-01-01020 | Plastic Pavement Striping (6" Width) (Thermoplastic 90 mil) | 3,474 | LNFT | 4.25 | 14,764.50 | 4.00 | 13,896.00 | 4.00 | 13,896.00 | 2.70 | 9,379.80 | | 0020 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 114 | LNFT | 6.25 | 712.50 | 6.00 | 684.00 | 8.00 | 912.00 | 4.50 | 513.00 | | 0021 | 732-01-01060 | Plastic Pavement Striping (12" Width) (Thermoplastic 90 mil) | 1,004 | LNFT | 10.50 | 10,542.00 | 5.00 | 5,020.00 | 10.00 | 10,040.00 | 11.00 | 11,044.00 | | 0022 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 481 | LNFT | 19.00 | 9,139.00 | 10.00 | 4,810.00 | 18.00 | 8,658.00 | 22.00 | 10,582.00 | | 0023 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 20 | EACH | 220.00 | 4,400.00 | 100.00 | 2,000.00 | 250.00 | 5,000.00 | 380.00 | 7,600.00 | | 0024 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 320.00 | 320.00 | 500.00 | 500.00 | 300.00 | 300.00 | 430.00 | 430.00 | | 0025 | 732-04-02000 | Plastic Pavement Legends and Symbols (Bicycle) | 20 | EACH | 510.00 | 10,200.00 | 250.00 | 5,000.00 | 450.00 | 9,000.00 | 540.00 | 10,800.00 | | 0026 | 732-05-00100 | Removal of Existing Markings | 0.3 | MILE | 10,000.00 | 3,000.00 | 1,000.00 | 300.00 | 8,000.00 | 2,400.00 | 11,000.00 | 3,300.00 | | 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,500.00 | 3,500.00 | 150,000.00 | 150,000.00 | 2,500.00 | 2,500.00 | 52,000.00 | 52,000.00 | | 0028 | 741-11-00100 | Adjusting Water Valve | 2 | EACH | 500.00 | 1,000.00 | 500.00 | 1,000.00 | 250.00 | 500.00 | 480.00 | 960.00 | | 0029 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 3 | EACH | 675.00 | 2,025.00 | 1,000.00 | 3,000.00 | 2,000.00 | 6,000.00 | 710.00 | 2,130.00 | | 0030 | NS-300-00060 | Geogrid | 8,189.1 | SQYD | 1.25 | 10,236.38 | 3.00 | 24,567.30 | 1.25 | 10,236.38 | 1.35 | 11,055.29 | | 0031 | NS-700-00140 | Flexible Post Traffic Delineators | 60 | EACH | 75.00 | 4,500.00 | 50.00 | 3,000.00 | 85.00 | 5,100.00 | 76.00 | 4,560.00 | | 0032 | NS-SRP-00002 | ADA Ramps (Type B) | 12 | EACH | 1,800.00 | 21,600.00 | 1,500.00 | 18,000.00 | 1,900.00 | 22,800.00 | 1,800.00 | 21,600.00 | | 0033 | NS-SRP-00004 | Adjust (Manhole) | 2 | EACH | 1,500.00 | 3,000.00 | 5,000.00 | 10,000.00 | 1,500.00 | 3,000.00 | 620.00 | 1,240.00 | | 0034 | NS-SRP-00005 | Adjust Catch Basin (Type A) | 11 | EACH | 450.00 | 4,950.00 | 750.00 | 8,250.00 | 1,100.00 | 12,100.00 | 980.00 | 10,780.00 | | 0035 | NS-SRP-00013 | Concrete Pavement Repair (18.1 sq. yd. to 48.0 sq. yd.) | 23.4 | SQYD | 109.00 | 2,550.60 | 250.00 | 5,850.00 | 180.00 | 4,212.00 | 200.00 | 4,680.00 | | 0036 | NS-SRP-00014 | Concrete Pavement Repair (48.1 sq. yd. and Over) | 8,109.1 | SQYD | 109.00 | 883,891.90 | 80.00 | 648,728.00 | 135.00 | 1,094,728.50 | 120.00 | 973,092.00 | | 0037 | NS-SRP-00016 | Concrete Curb (Barrier) (Doweled) | 2,680 | LNFT | 11.00 | 29,480.00 | 10.00 | 26,800.00 | 14.00 | 37,520.00 | 25.00 | 67,000.00 | | 0038 | NS-SRP-00029 | Project Signs (SRP) | 2 | EACH | 400.00 | 800.00 | 500.00 | 1,000.00 | 750.00 | 1,500.00 | 800.00 | 1,600.00 | | 0039 | NS-SRP-00030 | Recon of Concrete Curb and Gutterbottom (Barrier Curb) | 278 | LNFT | 65.00 | 18,070.00 | 75.00 | 20,850.00 | 70.00 | 19,460.00 | 61.00 | 16,958.00 | | 0040 | NS-SRP-00038 | Replace Frame and Cover (Catch Basin) | 3 | EACH | 2,300.00 | 6,900.00 | 3,000.00 | 9,000.00 | 950.00 | 2,850.00 | 2,000.00 | 6,000.00 | | 0041 | NS-SRP-00044 | Tree Protection | 1 | LUMP | 1,100.00 | 1,100.00 | 10,000.00 | 10,000.00 | 3,500.00 | 3,500.00 | 2,100.00 | 2,100.00 | | 0042 | NS-SRP-00045 | Tree Trimming | 1 | LUMP | 2,600.00 | 2,600.00 | 1.00 | 1.00 | 4,000.00 | 4,000.00 | 4,900.00 | 4,900.00 | | 0043 | NS-SRP-00046 | Root Pruning and Trenching | 1 | LUMP | 3,000.00 | 3,000.00 | 1.00 | 1.00 | 3,500.00 | 3,500.00 | 3,500.00 | 3,500.00 | | 0044 | NS-SRP-00071 | Temporary Curb and Gutter Inlet Protection System | 22 | EACH | 75.00 | 1,650.00 | 50.00 | 1,100.00 | 125.00 | 2,750.00 | 65.00 | 1,430.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,222,323.73 | | 1,346,879.35 | | 1,482,430.23 | | 1,548,532.69 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Boh Bros. Construction Co., LLC. | - 6 - Three C's Properties Inc | - 7 - Roubion Roads & Streets LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 139 | SQYD | 25.00 | 3,475.00 | 13.00 | 1,807.00 | 15.00 | 2,085.00 | | 0002 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 200 | CUYD | 30.00 | 6,000.00 | 50.00 | 10,000.00 | 21.00 | 4,200.00 | | 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 4.22 | TON | 250.00 | 1,055.00 | 300.00 | 1,266.00 | 300.00 | 1,266.00 | | 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 38.33 | SQYD | 5.00 | 191.65 | 135.00 | 5,174.55 | 21.00 | 804.93 | | 0005 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 38.33 | SQYD | 165.00 | 6,324.45 | 185.00 | 7,091.05 | 210.00 | 8,049.30 | | 0006 | 602-02-00100 | Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints | 4,500 | LNFT | 1.60 | 7,200.00 | 4.00 | 18,000.00 | 1.80 | 8,100.00 | | 0007 | 602-03-00100 | Cleaning and Sealing Random cracks | 3,000 | LNFT | 3.20 | 9,600.00 | 4.00 | 12,000.00 | 3.15 | 9,450.00 | | 0008 | 706-01-00100 | Concrete Walk (4" Thick) | 293.7 | SQYD | 70.00 | 20,559.00 | 60.00 | 17,622.00 | 60.00 | 17,622.00 | | 0009 | 706-01-00300 | Concrete Walk (6" Thick) | 3 | SQYD | 76.00 | 228.00 | 352.00 | 1,056.00 | 90.00 | 270.00 | | 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 35,000.00 | 35,000.00 | 23,758.00 | 23,758.00 | 90,000.00 | 90,000.00 | | 0011 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 500 | LNFT | 1.10 | 550.00 | 10.00 | 5,000.00 | 0.60 | 300.00 | | 0012 | 719-01-01080 | Plants (Tree) (Balled and Burlapped) (3" cal) Crape Myrtle | 10 | EACH | 530.00 | 5,300.00 | 719.00 | 7,190.00 | 525.00 | 5,250.00 | | 0013 | 719-01-01080 | Plants (Tree) (Balled and Burlapped) (3" cal) Live Oak | 18 | EACH | 530.00 | 9,540.00 | 719.00 | 12,942.00 | 630.00 | 11,340.00 | | 0014 | 727-01-00100 | Mobilization | 1 | LUMP | 88,000.00 | 88,000.00 | 63,110.00 | 63,110.00 | 300,000.00 | 300,000.00 | | 0015 | 729-01-00100 | Sign (Type A) | 24 | SQFT | 24.00 | 576.00 | 25.00 | 600.00 | 24.00 | 576.00 | | 0016 | 729-21-00100 | U-Channel Post | 6 | EACH | 103.00 | 618.00 | 109.00 | 654.00 | 75.00 | 450.00 | | 0017 | 731-02-00100 | Reflectorized Raised Pavement Markers | 83 | EACH | 16.00 | 1,328.00 | 23.00 | 1,909.00 | 15.00 | 1,245.00 | | 0018 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 4,823 | LNFT | 1.60 | 7,716.80 | 3.00 | 14,469.00 | 1.50 | 7,234.50 | | 0019 | 732-01-01020 | Plastic Pavement Striping (6" Width) (Thermoplastic 90 mil) | 3,474 | LNFT | 2.70 | 9,379.80 | 5.00 | 17,370.00 | 2.70 | 9,379.80 | | 0020 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 114 | LNFT | 4.30 | 490.20 | 7.00 | 798.00 | 4.20 | 478.80 | | 0021 | 732-01-01060 | Plastic Pavement Striping (12" Width) (Thermoplastic 90 mil) | 1,004 | LNFT | 11.00 | 11,044.00 | 12.00 | 12,048.00 | 12.00 | 12,048.00 | | 0022 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 481 | LNFT | 22.00 | 10,582.00 | 21.00 | 10,101.00 | 21.00 | 10,101.00 | | 0023 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 20 | EACH | 380.00 | 7,600.00 | 230.00 | 4,600.00 | 360.00 | 7,200.00 | | 0024 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 435.00 | 435.00 | 345.00 | 345.00 | 420.00 | 420.00 | | 0025 | 732-04-02000 | Plastic Pavement Legends and Symbols (Bicycle) | 20 | EACH | 545.00 | 10,900.00 | 575.00 | 11,500.00 | 510.00 | 10,200.00 | | 0026 | 732-05-00100 | Removal of Existing Markings | 0.3 | MILE | 10,000.00 | 3,000.00 | 23,000.00 | 6,900.00 | 12,000.00 | 3,600.00 | | 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 37,950.00 | 37,950.00 | 30,000.00 | 30,000.00 | | 0028 | 741-11-00100 | Adjusting Water Valve | 2 | EACH | 1,800.00 | 3,600.00 | 1,868.00 | 3,736.00 | 300.00 | 600.00 | | 0029 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 3 | EACH | 750.00 | 2,250.00 | 1,214.00 | 3,642.00 | 1,800.00 | 5,400.00 | | 0030 | NS-300-00060 | Geogrid | 8,189.1 | SQYD | 1.35 | 11,055.29 | 1.00 | 8,189.10 | 1.50 | 12,283.65 | | 0031 | NS-700-00140 | Flexible Post Traffic Delineators | 60 | EACH | 75.00 | 4,500.00 | 80.00 | 4,800.00 | 75.00 | 4,500.00 | | 0032 | NS-SRP-00002 | ADA Ramps (Type B) | 12 | EACH | 2,100.00 | 25,200.00 | 1,570.00 | 18,840.00 | 1,800.00 | 21,600.00 | | 0033 | NS-SRP-00004 | Adjust (Manhole) | 2 | EACH | 1,500.00 | 3,000.00 | 771.00 | 1,542.00 | 1,500.00 | 3,000.00 | | 0034 | NS-SRP-00005 | Adjust Catch Basin (Type A) | 11 | EACH | 600.00 | 6,600.00 | 791.00 | 8,701.00 | 1,200.00 | 13,200.00 | | 0035 | NS-SRP-00013 | Concrete Pavement Repair (18.1 sq. yd. to 48.0 sq. yd.) | 23.4 | SQYD | 127.00 | 2,971.80 | 200.00 | 4,680.00 | 150.00 | 3,510.00 | | 0036 | NS-SRP-00014 | Concrete Pavement Repair (48.1 sq. yd. and Over) | 8,109.1 | SQYD | 125.00 | 1,013,637.50 | 119.00 | 964,982.90 | 105.00 | 851,455.50 | | 0037 | NS-SRP-00016 | Concrete Curb (Barrier) (Doweled) | 2,680 | LNFT | 20.00 | 53,600.00 | 27.00 | 72,360.00 | 12.00 | 32,160.00 | | 0038 | NS-SRP-00029 | Project Signs (SRP) | 2 | EACH | 650.00 | 1,300.00 | 1,035.00 | 2,070.00 | 600.00 | 1,200.00 | | 0039 | NS-SRP-00030 | Recon of Concrete Curb and Gutterbottom (Barrier Curb) | 278 | LNFT | 45.00 | 12,510.00 | 59.00 | 16,402.00 | 36.00 | 10,008.00 | | 0040 | NS-SRP-00038 | Replace Frame and Cover (Catch Basin) | 3 | EACH | 1,800.00 | 5,400.00 | 1,630.00 | 4,890.00 | 600.00 | 1,800.00 | | 0041 | NS-SRP-00044 | Tree Protection | 1 | LUMP | 1,100.00 | 1,100.00 | 281.00 | 281.00 | 999.00 | 999.00 | | 0042 | NS-SRP-00045 | Tree Trimming | 1 | LUMP | 2,700.00 | 2,700.00 | 4,025.00 | 4,025.00 | 3,300.00 | 3,300.00 | | 0043 | NS-SRP-00046 | Root Pruning and Trenching | 1 | LUMP | 3,200.00 | 3,200.00 | 2,588.00 | 2,588.00 | 3,900.00 | 3,900.00 | | 0044 | NS-SRP-00071 | Temporary Curb and Gutter Inlet Protection System | 22 | EACH | 120.00 | 2,640.00 | 206.00 | 4,532.00 | 60.00 | 1,320.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,441,957.49 | | 1,431,521.60 | | 1,521,906.48 |
|