Proposal:H.009595.6
Parish:Livingston
Routes:I-12
Description:I-12: LIVINGSTON PAR APPROACH SLAB REP P2
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, CLASS II BASE COURSE, LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, PRECAST PRESTRESSED CONCRETE GIRDER SPANS BRIDGE, ASPHALTIC OR PORTLAND CEMENT CONCRETE PAVEMENT ALTERNATE, AND RELATED WORK.
Estimated Construction Cost:$15,348,982.10
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$10,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 12312 | GILCHRIST CONSTRUCTION CO. LLC | $16,135,564.80 | 500.00 | $21,135,564.80 |
| 2 | 34567 | James Construction Group LLC | $16,132,570.80 | 525.00 | $21,382,570.80 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $16,800,642.75 | 551.00 | $22,310,642.75 |
| 4 | 00481 | COASTAL BRIDGE CO., L.L.C. | $19,295,352.43 | 495.00 | $24,245,352.43 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - GILCHRIST CONSTRUCTION CO. LLC | - 2 - James Construction Group LLC | - 3 - Diamond B Construction Co., L.L.C. | - 4 - COASTAL BRIDGE CO., L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 90,000.00 | 90,000.00 | 222,500.00 | 222,500.00 | 140,000.00 | 140,000.00 | 400,000.00 | 400,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 326,000.00 | 326,000.00 | 744,965.00 | 744,965.00 | 850,000.00 | 850,000.00 | 800,000.00 | 800,000.00 | | 0003 | 202-02-00010 | Removal of Light Standard in Barrier | 4 | EACH | 3,000.00 | 12,000.00 | 800.00 | 3,200.00 | 500.00 | 2,000.00 | 2,000.00 | 8,000.00 | | 0004 | 202-02-02020 | Removal of Asphalt Pavement | 1,420 | SQYD | 11.00 | 15,620.00 | 7.00 | 9,940.00 | 16.50 | 23,430.00 | 10.00 | 14,200.00 | | 0005 | 202-02-06000 | Removal of Concrete Approach Slabs | 256 | SQYD | 67.00 | 17,152.00 | 70.00 | 17,920.00 | 160.00 | 40,960.00 | 50.00 | 12,800.00 | | 0006 | 202-02-06060 | Removal of Concrete Catch Basin | 4 | EACH | 900.00 | 3,600.00 | 600.00 | 2,400.00 | 600.00 | 2,400.00 | 1,500.00 | 6,000.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 1,030 | LNFT | 11.00 | 11,330.00 | 7.00 | 7,210.00 | 10.00 | 10,300.00 | 10.00 | 10,300.00 | | 0008 | 202-02-32100 | Removal of Pipe (Cross Drain) as per table | 32 | LNFT | 62.00 | 1,984.00 | 40.00 | 1,280.00 | 35.00 | 1,120.00 | 25.00 | 800.00 | | 0009 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 5,810 | SQYD | 14.00 | 81,340.00 | 12.00 | 69,720.00 | 13.00 | 75,530.00 | 10.00 | 58,100.00 | | 0010 | 202-02-38300 | Removal of Sign and U-Channel Post | 4 | EACH | 34.00 | 136.00 | 350.00 | 1,400.00 | 125.00 | 500.00 | 250.00 | 1,000.00 | | 0011 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 4,994 | SQYD | 10.00 | 49,940.00 | 8.60 | 42,948.40 | 6.00 | 29,964.00 | 5.00 | 24,970.00 | | 0012 | 202-03-38000 | Relocation of Sign Existing | 6 | EACH | 450.00 | 2,700.00 | 650.00 | 3,900.00 | 130.00 | 780.00 | 250.00 | 1,500.00 | | 0013 | 203-01-00100 | General Excavation | 2,760 | CUYD | 11.00 | 30,360.00 | 4.00 | 11,040.00 | 10.00 | 27,600.00 | 14.86 | 41,013.60 | | 0014 | 203-03-00100 | Embankment | 15,486 | CUYD | 30.00 | 464,580.00 | 20.00 | 309,720.00 | 27.00 | 418,122.00 | 21.00 | 325,206.00 | | 0015 | 204-02-00100 | Temporary Hay or Straw Bales | 36 | EACH | 16.00 | 576.00 | 19.00 | 684.00 | 30.00 | 1,080.00 | 10.00 | 360.00 | | 0016 | 204-06-00100 | Temporary Silt Fencing | 1,600 | LNFT | 3.00 | 4,800.00 | 3.00 | 4,800.00 | 2.50 | 4,000.00 | 5.00 | 8,000.00 | | 0017 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 5,000.00 | 10,000.00 | 5,500.00 | 11,000.00 | 22,000.00 | 44,000.00 | 2,000.00 | 4,000.00 | | 0018 | 302-02-01060 | Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete) | 40,138 | SQYD | 12.00 | 481,656.00 | 16.00 | 642,208.00 | 12.50 | 501,725.00 | 15.00 | 602,070.00 | | 0019 | 302-02-03020 | Class II Base Course (8" Thick) (Soil Cement) | 40,138 | SQYD | 13.00 | 521,794.00 | 14.00 | 561,932.00 | 9.00 | 361,242.00 | 16.00 | 642,208.00 | | 0020 | 304-05-00100 | Lime Treatment (Type E) | 569 | TON | 425.00 | 241,825.00 | 100.00 | 56,900.00 | 210.00 | 119,490.00 | 25.00 | 14,225.00 | | 0021 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 140 | TON | 185.00 | 25,900.00 | 250.00 | 35,000.00 | 288.00 | 40,320.00 | 250.00 | 35,000.00 | | 0022 | 509-01-00100 | Cold Planing Asphaltic Pavement | 58,240 | SQYD | 2.00 | 116,480.00 | 2.50 | 145,600.00 | 2.00 | 116,480.00 | 2.00 | 116,480.00 | | 0023 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,427 | CUYD | 1.00 | -2,427.00 | 1.00 | -2,427.00 | 0.10 | -242.70 | 0.01 | -24.27 | | 0024 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 100 | LNFT | 100.00 | 10,000.00 | 80.00 | 8,000.00 | 130.00 | 13,000.00 | 65.00 | 6,500.00 | | 0025 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 4,500.00 | 4,500.00 | 4,500.00 | 4,500.00 | 4,000.00 | 4,000.00 | 3,000.00 | 3,000.00 | | 0026 | 702-07-00400 | Cross Drain Safety End (Type 4) | 4 | EACH | 15,000.00 | 60,000.00 | 2,000.00 | 8,000.00 | 3,000.00 | 12,000.00 | 8,500.00 | 34,000.00 | | 0027 | 703-01-00100 | Shoulder Underdrain Systems | 1,572 | LNFT | 14.00 | 22,008.00 | 14.00 | 22,008.00 | 26.00 | 40,872.00 | 15.00 | 23,580.00 | | 0028 | 703-02-00100 | Shoulder Outlet Underdrains | 8 | EACH | 1,200.00 | 9,600.00 | 450.00 | 3,600.00 | 260.00 | 2,080.00 | 475.00 | 3,800.00 | | 0029 | 704-02-00100 | Guard Rail (Double Faced) | 75 | LNFT | 21.00 | 1,575.00 | 25.00 | 1,875.00 | 25.00 | 1,875.00 | 30.00 | 2,250.00 | | 0030 | 704-03-00100 | Blocked Out Guard Rail | 375 | LNFT | 27.00 | 10,125.00 | 20.00 | 7,500.00 | 20.00 | 7,500.00 | 20.00 | 7,500.00 | | 0031 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 62 | LNFT | 50.00 | 3,100.00 | 35.00 | 2,170.00 | 36.00 | 2,232.00 | 50.00 | 3,100.00 | | 0032 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 65.00 | 13,000.00 | 55.00 | 11,000.00 | 57.00 | 11,400.00 | 65.00 | 13,000.00 | | 0033 | 704-11-00100 | Guard Rail End Treatment (Flared) | 2 | EACH | 2,300.00 | 4,600.00 | 2,250.00 | 4,500.00 | 2,350.00 | 4,700.00 | 2,200.00 | 4,400.00 | | 0034 | 704-11-00300 | Guard Rail End Treatment (Bi-Directional) | 2 | EACH | 5,500.00 | 11,000.00 | 5,500.00 | 11,000.00 | 5,700.00 | 11,400.00 | 5,400.00 | 10,800.00 | | 0035 | 707-01-00100 | Concrete Curb | 20 | LNFT | 160.00 | 3,200.00 | 23.60 | 472.00 | 50.00 | 1,000.00 | 55.00 | 1,100.00 | | 0036 | 710-01-00100 | Flowable Fill | 26 | CUYD | 130.00 | 3,380.00 | 400.00 | 10,400.00 | 500.00 | 13,000.00 | 225.00 | 5,850.00 | | 0037 | 711-01-05000 | Riprap (130 lb, 24" Thick) | 1,018 | SQYD | 125.00 | 127,250.00 | 250.00 | 254,500.00 | 125.00 | 127,250.00 | 150.00 | 152,700.00 | | 0038 | 711-04-00100 | Geotextile Fabric | 1,018 | SQYD | 6.00 | 6,108.00 | 10.00 | 10,180.00 | 3.50 | 3,563.00 | 2.00 | 2,036.00 | | 0039 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 44 | SQYD | 100.00 | 4,400.00 | 200.00 | 8,800.00 | 340.00 | 14,960.00 | 150.00 | 6,600.00 | | 0040 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 280,000.00 | 280,000.00 | 175,000.00 | 175,000.00 | 250,000.00 | 250,000.00 | 300,000.00 | 300,000.00 | | 0041 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 7,643 | EACH | 6.00 | 45,858.00 | 6.50 | 49,679.50 | 6.75 | 51,590.25 | 8.00 | 61,144.00 | | 0042 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 288 | EACH | 400.00 | 115,200.00 | 625.00 | 180,000.00 | 400.00 | 115,200.00 | 900.00 | 259,200.00 | | 0043 | 713-08-00100 | Temporary Precast Concrete Barrier (Department Furnished) | 760 | EACH | 350.00 | 266,000.00 | 300.00 | 228,000.00 | 155.00 | 117,800.00 | 250.00 | 190,000.00 | | 0044 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 467 | EACH | 95.00 | 44,365.00 | 140.00 | 65,380.00 | 100.00 | 46,700.00 | 150.00 | 70,050.00 | | 0045 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 25,000.00 | 25,000.00 | 45,000.00 | 45,000.00 | 30,000.00 | 30,000.00 | 10,000.00 | 10,000.00 | | 0046 | 725-01-00100 | Temporary Detour Roads | 2,546 | SQYD | 85.00 | 216,410.00 | 115.00 | 292,790.00 | 160.00 | 407,360.00 | 110.00 | 280,060.00 | | 0047 | 726-01-00100 | Bedding Material | 9 | CUYD | 120.00 | 1,080.00 | 90.00 | 810.00 | 100.00 | 900.00 | 125.00 | 1,125.00 | | 0048 | 727-01-00100 | Mobilization | 1 | LUMP | 1,600,000.00 | 1,600,000.00 | 1,600,000.00 | 1,600,000.00 | 1,250,000.00 | 1,250,000.00 | 1,800,000.00 | 1,800,000.00 | | 0049 | 729-16-00300 | Object Marker Assembly (Type 3) | 14 | EACH | 80.00 | 1,120.00 | 65.00 | 910.00 | 70.00 | 980.00 | 75.00 | 1,050.00 | | 0050 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 1,867 | EACH | 14.00 | 26,138.00 | 13.00 | 24,271.00 | 12.00 | 22,404.00 | 10.00 | 18,670.00 | | 0051 | 731-02-00100 | Reflectorized Raised Pavement Markers | 4,475 | EACH | 8.00 | 35,800.00 | 7.50 | 33,562.50 | 7.50 | 33,562.50 | 10.00 | 44,750.00 | | 0052 | 732-01-04080 | Plastic Pavement Striping (24" Width) (Preformed Retroreflective Thermoplastic) (Heat Applied) (125 mil) | 800 | LNFT | 17.00 | 13,600.00 | 16.00 | 12,800.00 | 15.00 | 12,000.00 | 6.00 | 4,800.00 | | 0053 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.37 | MILE | 6,700.00 | 35,979.00 | 6,500.00 | 34,905.00 | 6,750.00 | 36,247.50 | 8,500.00 | 45,645.00 | | 0054 | 732-05-00100 | Removal of Existing Markings | 1.44 | MILE | 15,000.00 | 21,600.00 | 14,000.00 | 20,160.00 | 14,000.00 | 20,160.00 | 25,000.00 | 36,000.00 | | 0055 | 733-01-00200 | Concrete Roadway Barrier (Double Faced) | 5,450 | LNFT | 320.00 | 1,744,000.00 | 300.00 | 1,635,000.00 | 330.00 | 1,798,500.00 | 500.00 | 2,725,000.00 | | 0056 | 739-01-00100 | Hydro-Seeding | 2 | ACRE | 1,300.00 | 2,600.00 | 1,225.00 | 2,450.00 | 2,600.00 | 5,200.00 | 1,500.00 | 3,000.00 | | 0057 | 740-01-00100 | Construction Layout | 1 | LUMP | 100,000.00 | 100,000.00 | 150,000.00 | 150,000.00 | 160,000.00 | 160,000.00 | 110,000.00 | 110,000.00 | | 0058 | 804-01-00600 | Precast Concrete Piles (24") | 9,240 | LNFT | 75.00 | 693,000.00 | 90.00 | 831,600.00 | 130.00 | 1,201,200.00 | 100.00 | 924,000.00 | | 0059 | 804-09-00100 | Loading Test Piles | 1 | EACH | 10,000.00 | 10,000.00 | 80,000.00 | 80,000.00 | 62,000.00 | 62,000.00 | 50,000.00 | 50,000.00 | | 0060 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1.00 | 1.00 | 1,001.00 | 1,001.00 | 62,000.00 | 62,000.00 | 20,000.00 | 20,000.00 | | 0061 | 804-13-00100 | Precast Concrete Indicator Piles | 1 | EACH | 40,000.00 | 40,000.00 | 120,000.00 | 120,000.00 | 18,000.00 | 18,000.00 | 50,000.00 | 50,000.00 | | 0062 | 804-17-00100 | Dynamic Monitoring | 12 | EACH | 625.00 | 7,500.00 | 2,000.00 | 24,000.00 | 11,500.00 | 138,000.00 | 1,200.00 | 14,400.00 | | 0063 | 805-01-00700 | Class A Concrete (Bents) | 279.22 | CUYD | 1,700.00 | 474,674.00 | 1,600.00 | 446,752.00 | 1,800.00 | 502,596.00 | 2,100.00 | 586,362.00 | | 0064 | 805-03-00100 | Class AA Concrete | 1,140.24 | CUYD | 950.00 | 1,083,228.00 | 675.00 | 769,662.00 | 1,000.00 | 1,140,240.00 | 1,250.00 | 1,425,300.00 | | 0065 | 805-08-00300 | Precast-Prestressed Concrete Girder (Type III) | 4,723 | LNFT | 108.00 | 510,084.00 | 90.00 | 425,070.00 | 135.00 | 637,605.00 | 145.00 | 684,835.00 | | 0066 | 806-01-00100 | Deformed Reinforcing Steel | 367,982 | LB | 0.80 | 294,385.60 | 1.00 | 367,982.00 | 1.35 | 496,775.70 | 2.00 | 735,964.00 | | 0067 | 807-08-00100 | Structural Metalwork | 6,660 | LUMP | 60,000.00 | 60,000.00 | 59,820.00 | 59,820.00 | 68,500.00 | 68,500.00 | 85,000.00 | 85,000.00 | | 0068 | 810-01-00100 | Concrete Railing (Standard Barrier) | 1,360 | LNFT | 70.00 | 95,200.00 | 52.00 | 70,720.00 | 75.00 | 102,000.00 | 75.00 | 102,000.00 | | 0069 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 1,040 | LNFT | 74.00 | 76,960.00 | 60.00 | 62,400.00 | 80.00 | 83,200.00 | 80.00 | 83,200.00 | | 0070 | 813-01-00100 | Concrete Approach Slabs | 1,097.76 | SQYD | 300.00 | 329,328.00 | 275.00 | 301,884.00 | 210.00 | 230,529.60 | 275.00 | 301,884.00 | | 0071 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 95,800 | INLF | 0.10 | 9,580.00 | 0.60 | 57,480.00 | 0.80 | 76,640.00 | 0.50 | 47,900.00 | | 0072 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 39,744 | INLF | 1.25 | 49,680.00 | 0.60 | 23,846.40 | 1.60 | 63,590.40 | 0.65 | 25,833.60 | | 0073 | NS-700-00180 | Impact Attenuator (Construction Zone) | 2 | EACH | 2,600.00 | 5,200.00 | 12,500.00 | 25,000.00 | 9,000.00 | 18,000.00 | 60,000.00 | 120,000.00 | | 0074 | NS-700-00181 | Impact Attenuator Relocation (Construction Zone) | 2 | EACH | 2,600.00 | 5,200.00 | 5,375.00 | 10,750.00 | 1,600.00 | 3,200.00 | 16,500.00 | 33,000.00 | | 0075 | NS-713-00008 | Portable Changeable Message Sign | 2 | EACH | 16,000.00 | 32,000.00 | 20,000.00 | 40,000.00 | 17,000.00 | 34,000.00 | 16,000.00 | 32,000.00 | | 0077 | NS-805-00005 | Joint Sealing System (Preformed Silicone) | 1,200 | LNFT | 38.50 | 46,200.00 | 70.00 | 84,000.00 | 70.00 | 84,000.00 | 70.00 | 84,000.00 | | 0078 | NS-805-00018 | Structural Polymer Concrete (Joint Repairs) | 520 | LNFT | 115.00 | 59,800.00 | 300.00 | 156,000.00 | 250.00 | 130,000.00 | 125.00 | 65,000.00 | | 0079 | NS-MSC-00120 | Drainage Structure CAPPING CATCH BASIN | 2 | EACH | 2,700.00 | 5,400.00 | 1,500.00 | 3,000.00 | 5,200.00 | 10,400.00 | 1,000.00 | 2,000.00 | | 0098 | NS-724-00005 | Rumble Strips (Shoulder) | 11.86 | MILE | 395.00 | 4,684.70 | 250.00 | 2,965.00 | 500.00 | 5,930.00 | 650.00 | 7,709.00 | | 0099 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 500 | SQYD | 180.00 | 90,000.00 | 160.00 | 80,000.00 | 125.00 | 62,500.00 | 125.00 | 62,500.00 | | | | SUBTOTAL GENERAL | | | | 11,358,047 | | 11,866,996 | | 12,671,143 | | 14,909,806 | | | | | | | | | | | | | | | | | Alternate AA1 | Alternate AA1 (Pavement Replacement w/ Asphalt) | | | | | | | | | | | | | | | | | | | | | | | | | | 0080 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 5,010 | TON | 155.00 | 776,550.00 | 95.00 | 475,950.00 | 125.00 | 626,250.00 | 135.00 | 676,350.00 | | 0081 | 501-02-00001 | Tack Coat | 17,611 | GAL | 3.50 | 61,638.50 | 3.00 | 52,833.00 | 3.50 | 61,638.50 | 3.50 | 61,638.50 | | 0082 | 502-01-00100 | Superpave Asphaltic Concrete | 42,822 | TON | 90.00 | 3,853,980.00 | 86.00 | 3,682,692.00 | 79.00 | 3,382,938.00 | 84.00 | 3,597,048.00 | | 0083 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 53 | SQYD | 600.00 | 31,800.00 | 50.00 | 2,650.00 | 105.00 | 5,565.00 | 75.00 | 3,975.00 | | 0084 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 13 | MILE | 1,300.00 | 16,900.00 | 1,200.00 | 15,600.00 | 1,250.00 | 16,250.00 | 2,500.00 | 32,500.00 | | 0085 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 1.8 | MILE | 14,200.00 | 25,560.00 | 14,000.00 | 25,200.00 | 14,500.00 | 26,100.00 | 3,500.00 | 6,300.00 | | 0086 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.59 | MILE | 3,100.00 | 8,029.00 | 3,000.00 | 7,770.00 | 3,000.00 | 7,770.00 | 2,500.00 | 6,475.00 | | 0087 | 732-03-02101 | Plastic Pavement Striping (Broken Line) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black Contrast) | 0.36 | MILE | 8,500.00 | 3,060.00 | 8,000.00 | 2,880.00 | 8,300.00 | 2,988.00 | 3,500.00 | 1,260.00 | | | | SUBTOTAL ALT AA1 | | | | 4,777,517.50 | | 4,265,575.00 | | 4,129,499.50 | | 4,385,546.50 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 16,135,564.80 | | 16,132,570.80 | | 16,800,642.75 | | 19,295,352.43 |
|