Bid Tabulations for the Letting of 5/13/2015 LA DOTD Headquarters

Proposal:H.010598.6
Parish:Iberville
Description:DERRICK ROAD BRIDGE
Type Construction:DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PILINGS, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$492,631.20
Rank License BidderConstruction Bid
100044GUINN CONSTRUCTION, LLC$486,204.70
240312GRAY CONSTRUCTION CORP.$528,771.94
302109Chambers Construction Co, Inc.$565,562.57
400481COASTAL BRIDGE CO., L.L.C.$658,985.05
556994MATT L GUINN CONSTRUCTION, LLC$659,582.90
639462JB JAMES CONSTRUCTION LLC$769,506.40


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
GUINN CONSTRUCTION, LLC
- 2 -
GRAY CONSTRUCTION CORP.
- 3 -
Chambers Construction Co, Inc.
- 4 -
COASTAL BRIDGE CO., L.L.C.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-01-00100Removal of Structures and Obstructions (INCLUDES REMOVAL OF SIGNS, EMBANKMENT ON BRIDGE, PIPES, GUARD RAILS, TREES AND BUSHES)1     LUMP4,000.004,000.0012,600.0012,600.003,947.393,947.3915,000.0015,000.00
0002202-02-04000Removal of Bridge (STA 105+22.48 - 56'X20' PRECAST WITH TIMBER PILES)1     EACH10,000.0010,000.0023,700.0023,700.0016,773.3516,773.3545,000.0045,000.00
0003202-02-38500Removal of Surfacing and Stabilized Base 587.4   SQYD5.002,937.006.653,906.2112.627,412.9929.0017,034.60
0004203-05-00100Excavation and Embankment 1     LUMP17,000.0017,000.0018,000.0018,000.0024,258.1324,258.1330,000.0030,000.00
0005204-02-00100Temporary Hay or Straw Bales 22     EACH10.00220.0015.00330.0043.71961.6215.00330.00
0006204-05-00200Temporary Sediment Check Dams (Stone) 1     EACH500.00500.00500.00500.00981.18981.18500.00500.00
0007204-06-00100Temporary Silt Fencing 747     LNFT3.002,241.002.301,718.103.952,950.652.301,718.10
0008302-02-04100Class II Base Course (8 1/2" Thick) (Stone) (CRUSHED)746.5   SQYD24.0017,916.0036.0526,911.3338.0728,419.2632.5024,261.25
0009402-01-00100Traffic Maintenance Aggregate (Vehicular Measurement) (INCLUDES TYPE D GEOTEXTILE FABRIC FOR TEMPORARY DRIVEWAY AND REMOVAL OF TEMPORARY DRIVEWAY UPON COMPLETION OF PROJECT)50     CUYD135.006,750.00103.255,162.50208.4410,422.0050.002,500.00
0010403-01-00100Aggregate Roadway Surfacing (Vehicular Measurement) (STONE ONLY)28.05  CUYD110.003,085.5099.002,776.95127.363,572.4550.001,402.50
0011502-01-00100Superpave Asphaltic Concrete 138.6   TON175.0024,255.00274.0037,976.40302.4241,915.41150.0020,790.00
0012502-01-00200Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 12.2   TON200.002,440.00290.003,538.00302.423,689.52500.006,100.00
0013701-05-01060Side Drain Pipe (24" RCP/PP/CMP) 104     LNFT52.005,408.0046.504,836.0078.748,188.96105.0010,920.00
0014701-05-02060Side Drain Pipe (Erosion) (24" PP/CMP) 90     LNFT52.004,680.0045.004,050.0073.626,625.80115.0010,350.00
0015701-05-02200Side Drain Pipe (Erosion) (72" CMP) 136     LNFT325.0044,200.00239.0032,504.00368.2750,084.72335.0045,560.00
0016701-15-00100Concrete Collar 1     EACH2,000.002,000.001,550.001,550.001,011.401,011.401,000.001,000.00
0017702-03-00100Catch Basins (CB-01) 1     EACH3,500.003,500.003,000.003,000.003,596.383,596.383,500.003,500.00
0018704-03-00100Blocked Out Guard Rail 25     LNFT25.00625.0022.00550.0027.13678.2524.00600.00
0019704-08-00200Guard Rail Transitions (Double Thrie Beam) 50     LNFT55.002,750.0060.003,000.0098.674,933.5066.003,300.00
0020704-11-00100Guard Rail End Treatment (Flared) 2     EACH3,000.006,000.002,200.004,400.003,360.906,721.802,400.004,800.00
0021711-01-02000Riprap (10 lb, 10" Thick) 105     SQYD70.007,350.0040.204,221.0030.923,246.6050.005,250.00
0022711-01-03000Riprap (30 lb, 14" Thick) 360     SQYD70.0025,200.0049.2517,730.0051.1418,410.4057.0020,520.00
0023711-04-00100Geotextile Fabric 465     SQYD3.001,395.002.651,232.254.281,990.202.501,162.50
0024713-01-00100Temporary Signs and Barricades 1     LUMP7,500.007,500.006,000.006,000.0013,724.4713,724.476,500.006,500.00
0025715-01-00100Topsoil 70     CUYD50.003,500.0058.004,060.0028.391,987.3040.002,800.00
0026716-01-00100Mulch (Vegetative) 0.4   TON2,500.001,000.002,850.001,140.008,323.633,329.452,850.001,140.00
0027717-01-00100Seeding 8     LB25.00200.0020.00160.0024.67197.3620.00160.00
0028718-01-00100Fertilizer 177     LB1.00177.002.50442.503.08545.162.50442.50
0029726-01-00100Bedding Material 150.9   CUYD80.0012,072.00105.2015,874.6898.8214,911.94100.0015,090.00
0030727-01-00100Mobilization 1     LUMP40,000.0040,000.0040,250.0040,250.0046,259.5646,259.5665,000.0065,000.00
0031729-16-00300Object Marker Assembly (Type 3) 4     EACH100.00400.0085.00340.00104.84419.3690.00360.00
0032740-01-00100Construction Layout 1     LUMP4,000.004,000.002,600.002,600.007,098.587,098.5815,000.0015,000.00
0033804-01-00200Precast Concrete Piles (14") 1,540     LNFT55.0084,700.0048.5074,690.0047.5473,211.6065.00100,100.00
0034804-12-00100Loading Permanent Piles 1     EACH1.001.00100.00100.00123.33123.33100.00100.00
0035804-17-00100Dynamic Monitoring 4     EACH750.003,000.00218.00872.00419.401,677.601,250.005,000.00
0036805-10-02140Bridge Superstructure and Substructure (28' Clear Roadway; 60 Degree Crossing) (Cast-in-Place Bents Only) (INCLUDES MODIFIED END BENTS TO ACCOMMODATE TAPERED BARRIER RAILS ON APPROACH SLAB)3     SPAN32,000.0096,000.0043,000.00129,000.0035,468.46106,405.3845,000.00135,000.00
0037813-01-00100Concrete Approach Slabs (WITH TAPERED BARRIER RAIL AT SE AND NW CORNERS)66.12  SQYD335.0022,150.20346.0022,877.52420.9527,833.21305.0020,166.60
0038NS-500-00340Saw Cutting Asphaltic Concrete Pavement 138     INLF4.00552.001.25172.506.27865.2611.501,587.00
0039NS-804-00001Vibration Monitoring 22     EACH500.0011,000.00500.0011,000.00494.9010,887.80520.0011,440.00
0040NS-804-00002Construction Site Survey 1     LUMP5,500.005,500.005,000.005,000.005,293.255,293.257,500.007,500.00
             
  CONTRACTOR TOTAL   486,204.70 528,771.94 565,562.57 658,985.05



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
MATT L GUINN CONSTRUCTION, LLC
- 6 -
JB JAMES CONSTRUCTION LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-01-00100Removal of Structures and Obstructions (INCLUDES REMOVAL OF SIGNS, EMBANKMENT ON BRIDGE, PIPES, GUARD RAILS, TREES AND BUSHES)1     LUMP16,000.0016,000.0011,000.0011,000.00
0002202-02-04000Removal of Bridge (STA 105+22.48 - 56'X20' PRECAST WITH TIMBER PILES)1     EACH18,500.0018,500.0050,000.0050,000.00
0003202-02-38500Removal of Surfacing and Stabilized Base 587.4   SQYD8.004,699.208.504,992.90
0004203-05-00100Excavation and Embankment 1     LUMP48,500.0048,500.0040,000.0040,000.00
0005204-02-00100Temporary Hay or Straw Bales 22     EACH180.003,960.0020.00440.00
0006204-05-00200Temporary Sediment Check Dams (Stone) 1     EACH300.00300.00750.00750.00
0007204-06-00100Temporary Silt Fencing 747     LNFT2.852,128.953.002,241.00
0008302-02-04100Class II Base Course (8 1/2" Thick) (Stone) (CRUSHED)746.5   SQYD35.0026,127.5031.0023,141.50
0009402-01-00100Traffic Maintenance Aggregate (Vehicular Measurement) (INCLUDES TYPE D GEOTEXTILE FABRIC FOR TEMPORARY DRIVEWAY AND REMOVAL OF TEMPORARY DRIVEWAY UPON COMPLETION OF PROJECT)50     CUYD145.007,250.00100.005,000.00
0010403-01-00100Aggregate Roadway Surfacing (Vehicular Measurement) (STONE ONLY)28.05  CUYD145.004,067.25150.004,207.50
0011502-01-00100Superpave Asphaltic Concrete 138.6   TON300.0041,580.00240.0033,264.00
0012502-01-00200Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 12.2   TON300.003,660.00240.002,928.00
0013701-05-01060Side Drain Pipe (24" RCP/PP/CMP) 104     LNFT85.008,840.0064.006,656.00
0014701-05-02060Side Drain Pipe (Erosion) (24" PP/CMP) 90     LNFT85.007,650.0055.004,950.00
0015701-05-02200Side Drain Pipe (Erosion) (72" CMP) 136     LNFT300.0040,800.00260.0035,360.00
0016701-15-00100Concrete Collar 1     EACH5,000.005,000.00750.00750.00
0017702-03-00100Catch Basins (CB-01) 1     EACH6,500.006,500.004,100.004,100.00
0018704-03-00100Blocked Out Guard Rail 25     LNFT38.50962.5025.00625.00
0019704-08-00200Guard Rail Transitions (Double Thrie Beam) 50     LNFT90.004,500.0085.004,250.00
0020704-11-00100Guard Rail End Treatment (Flared) 2     EACH3,000.006,000.002,600.005,200.00
0021711-01-02000Riprap (10 lb, 10" Thick) 105     SQYD85.008,925.0060.006,300.00
0022711-01-03000Riprap (30 lb, 14" Thick) 360     SQYD75.0027,000.0070.0025,200.00
0023711-04-00100Geotextile Fabric 465     SQYD3.001,395.004.001,860.00
0024713-01-00100Temporary Signs and Barricades 1     LUMP10,000.0010,000.0025,000.0025,000.00
0025715-01-00100Topsoil 70     CUYD50.003,500.0030.002,100.00
0026716-01-00100Mulch (Vegetative) 0.4   TON1,800.00720.001,800.00720.00
0027717-01-00100Seeding 8     LB25.00200.0025.00200.00
0028718-01-00100Fertilizer 177     LB1.50265.503.00531.00
0029726-01-00100Bedding Material 150.9   CUYD110.0016,599.0085.0012,826.50
0030727-01-00100Mobilization 1     LUMP50,000.0050,000.0070,000.0070,000.00
0031729-16-00300Object Marker Assembly (Type 3) 4     EACH125.00500.0090.00360.00
0032740-01-00100Construction Layout 1     LUMP6,000.006,000.0020,000.0020,000.00
0033804-01-00200Precast Concrete Piles (14") 1,540     LNFT68.00104,720.0065.00100,100.00
0034804-12-00100Loading Permanent Piles 1     EACH1.001.001,000.001,000.00
0035804-17-00100Dynamic Monitoring 4     EACH3,500.0014,000.001,500.006,000.00
0036805-10-02140Bridge Superstructure and Substructure (28' Clear Roadway; 60 Degree Crossing) (Cast-in-Place Bents Only) (INCLUDES MODIFIED END BENTS TO ACCOMMODATE TAPERED BARRIER RAILS ON APPROACH SLAB)3     SPAN40,000.00120,000.0075,000.00225,000.00
0037813-01-00100Concrete Approach Slabs (WITH TAPERED BARRIER RAIL AT SE AND NW CORNERS)66.12  SQYD350.0023,142.00275.0018,183.00
0038NS-500-00340Saw Cutting Asphaltic Concrete Pavement 138     INLF5.00690.0015.002,070.00
0039NS-804-00001Vibration Monitoring 22     EACH450.009,900.00100.002,200.00
0040NS-804-00002Construction Site Survey 1     LUMP5,000.005,000.0010,000.0010,000.00
         
  CONTRACTOR TOTAL   659,582.90 769,506.40