Proposal:H.011175.6
Parish:Concordia
Routes:US 425
Description:US 425: DELAWARE ST. - ARKANSAS ST. IN FERRIDAY
Type Construction:COLD PLANING ASPHALTIC PAVEMENT, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,145,562.01
| Rank | License | Bidder | Construction Bid |
| 1 | 21982 | Forby Contracting, Inc. | $1,224,345.81 |
| 2 | 02214 | W. E. BLAIN & SONS, INC. | $1,260,034.98 |
| 3 | 05789 | D & J CONSTRUCTION CO., LLC | $1,605,630.85 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Forby Contracting, Inc. | - 2 - W. E. BLAIN & SONS, INC. | - 3 - D & J CONSTRUCTION CO., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 84 | LNFT | 20.00 | 1,680.00 | 30.00 | 2,520.00 | 25.00 | 2,100.00 | | 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 125 | SQYD | 25.00 | 3,125.00 | 24.00 | 3,000.00 | 30.00 | 3,750.00 | | 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 4 | CUYD | 60.00 | 240.00 | 270.00 | 1,080.00 | 300.00 | 1,200.00 | | 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 2,695.1 | TON | 125.00 | 336,887.50 | 121.00 | 326,107.10 | 118.00 | 318,021.80 | | 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 945.1 | TON | 165.00 | 155,941.50 | 152.00 | 143,655.20 | 148.00 | 139,874.80 | | 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 24,490 | SQYD | 2.50 | 61,225.00 | 2.70 | 66,123.00 | 5.00 | 122,450.00 | | 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -680 | CUYD | 0.10 | -68.00 | 0.10 | -68.00 | 1.00 | -680.00 | | 0008 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 487.8 | SQYD | 190.00 | 92,682.00 | 200.00 | 97,560.00 | 375.00 | 182,925.00 | | 0009 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 415.6 | SQYD | 170.00 | 70,652.00 | 180.00 | 74,808.00 | 275.00 | 114,290.00 | | 0010 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 913.2 | SQYD | 160.00 | 146,112.00 | 160.00 | 146,112.00 | 225.00 | 205,470.00 | | 0011 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 83 | LNFT | 75.00 | 6,225.00 | 90.00 | 7,470.00 | 130.00 | 10,790.00 | | 0012 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 4,000.00 | 4,000.00 | 5,500.00 | 5,500.00 | 5,000.00 | 5,000.00 | | 0013 | 706-02-00200 | Concrete Drive (6" Thick) | 20 | SQYD | 80.00 | 1,600.00 | 75.00 | 1,500.00 | 110.00 | 2,200.00 | | 0014 | 706-04-00100 | Handicapped Curb Ramps | 35 | EACH | 1,800.00 | 63,000.00 | 1,000.00 | 35,000.00 | 2,500.00 | 87,500.00 | | 0015 | 707-01-00200 | Concrete Curb (Barrier) | 20 | LNFT | 18.00 | 360.00 | 25.00 | 500.00 | 45.00 | 900.00 | | 0016 | 707-03-00100 | Combination Concrete Curb and Gutter | 84 | LNFT | 45.00 | 3,780.00 | 35.00 | 2,940.00 | 60.00 | 5,040.00 | | 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 75,000.00 | 75,000.00 | 125,000.00 | 125,000.00 | | 0018 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 7.788 | MILE | 500.00 | 3,894.00 | 340.00 | 2,647.92 | 250.00 | 1,947.00 | | 0019 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.735 | MILE | 275.00 | 1,027.13 | 290.00 | 1,083.15 | 300.00 | 1,120.50 | | 0020 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 4.215 | MILE | 475.00 | 2,002.13 | 500.00 | 2,107.50 | 500.00 | 2,107.50 | | 0021 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 3 | EACH | 15.00 | 45.00 | 15.00 | 45.00 | 15.00 | 45.00 | | 0022 | 726-01-00100 | Bedding Material | 7.8 | CUYD | 60.00 | 468.00 | 47.00 | 366.60 | 150.00 | 1,170.00 | | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 105,000.00 | 105,000.00 | 147,000.00 | 147,000.00 | 125,000.00 | 125,000.00 | | 0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 773 | EACH | 8.00 | 6,184.00 | 8.50 | 6,570.50 | 8.00 | 6,184.00 | | 0025 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 210 | LNFT | 8.00 | 1,680.00 | 8.50 | 1,785.00 | 8.00 | 1,680.00 | | 0026 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 76 | LNFT | 25.00 | 1,900.00 | 25.00 | 1,900.00 | 25.00 | 1,900.00 | | 0027 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 2.107 | MILE | 3,900.00 | 8,217.30 | 4,000.00 | 8,428.00 | 5,000.00 | 10,535.00 | | 0028 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.868 | MILE | 1,500.00 | 2,802.00 | 1,595.00 | 2,979.46 | 2,000.00 | 3,736.00 | | 0029 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 350.00 | 1,050.00 | 370.00 | 1,110.00 | 600.00 | 1,800.00 | | 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | | 0031 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 25,703 | LNFT | 1.10 | 28,273.30 | 1.20 | 30,843.60 | 1.75 | 44,980.25 | | 0032 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 11,417 | LNFT | 1.35 | 15,412.95 | 1.35 | 15,412.95 | 2.00 | 22,834.00 | | 0033 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 37,120 | LNFT | 1.15 | 42,688.00 | 1.15 | 42,688.00 | 1.25 | 46,400.00 | | 0034 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 840 | INLF | 1.50 | 1,260.00 | 1.50 | 1,260.00 | 4.00 | 3,360.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,224,345.81 | | 1,260,034.98 | | 1,605,630.85 |
|