Proposal:H.009185.6
Parish:St. Tammany
Routes:I-12
Description:I-12: NORTHSHORE/AIRPORT RD. - US 11
Type Construction:CLEARING AND GRUBBING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, CLASS II BASE COURSE, LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PRECAST PRESTRESSED CONCRETE GIRDER SPANS BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$21,243,801.61
Maximum Number of Days Allowed for Construction:540
Calculated Daily User Cost:$5,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 34567 | James Construction Group LLC | $20,684,655.70 | 355.00 | $22,459,655.70 |
| 2 | 06487 | Huey Stockstill, Inc. | $22,594,372.91 | 480.00 | $24,994,372.91 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $23,244,714.29 | 450.00 | $25,494,714.29 |
| 4 | 39462 | JB JAMES CONSTRUCTION LLC | $22,847,145.20 | 540.00 | $25,547,145.20 |
| 5 | 12312 | GILCHRIST CONSTRUCTION CO. LLC | $23,551,777.45 | 410.00 | $25,601,777.45 |
| 6 | 12487 | Diamond B Construction Co., L.L.C. | $26,586,849.38 | 500.00 | $29,086,849.38 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - James Construction Group LLC | - 2 - Huey Stockstill, Inc. | - 3 - Boh Bros. Construction Co., LLC. | - 4 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 200,500.00 | 200,500.00 | 45,000.00 | 45,000.00 | 10,000.00 | 10,000.00 | 50,000.00 | 50,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 200,500.00 | 200,500.00 | 200,000.00 | 200,000.00 | 85,000.00 | 85,000.00 | 75,000.00 | 75,000.00 | | 0003 | 202-02-04001 | Removal of Bridge (Partial Removal) END BENTS AND WINGWALLS | 1 | LUMP | 50,400.00 | 50,400.00 | 22,000.00 | 22,000.00 | 95,000.00 | 95,000.00 | 25,000.00 | 25,000.00 | | 0004 | 202-02-04110 | Removal of Bridge Superstructure (Concrete Girder Span) | 3,920 | SQFT | 29.00 | 113,680.00 | 22.00 | 86,240.00 | 20.00 | 78,400.00 | 75.00 | 294,000.00 | | 0005 | 202-02-06000 | Removal of Concrete Approach Slabs | 448.67 | SQYD | 1.00 | 448.67 | 38.00 | 17,049.46 | 45.00 | 20,190.15 | 40.00 | 17,946.80 | | 0006 | 202-02-06060 | Removal of Concrete Catch Basin | 4 | EACH | 530.00 | 2,120.00 | 700.00 | 2,800.00 | 200.00 | 800.00 | 1,000.00 | 4,000.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 1,059.53 | LNFT | 15.00 | 15,892.95 | 7.70 | 8,158.38 | 80.00 | 84,762.40 | 9.00 | 9,535.77 | | 0008 | 202-02-32100 | Removal of Pipe (Cross Drain) END JOINTS (1001, 1007, 1008, 1009, 1010, 1011) | 48 | LNFT | 40.00 | 1,920.00 | 15.00 | 720.00 | 10.00 | 480.00 | 12.00 | 576.00 | | 0009 | 202-02-32180 | Removal of Pipe Headwalls | 6 | EACH | 450.00 | 2,700.00 | 1,300.00 | 7,800.00 | 200.00 | 1,200.00 | 900.00 | 5,400.00 | | 0010 | 202-02-38220 | Removal of Sign Supports | 18 | EACH | 320.00 | 5,760.00 | 55.00 | 990.00 | 260.00 | 4,680.00 | 225.00 | 4,050.00 | | 0011 | 202-02-38360 | Removal of Sign Faces | 18 | EACH | 95.00 | 1,710.00 | 55.00 | 990.00 | 58.00 | 1,044.00 | 50.00 | 900.00 | | 0012 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 13,796.02 | SQYD | 14.50 | 200,042.29 | 2.50 | 34,490.05 | 9.09 | 125,405.82 | 5.00 | 68,980.10 | | 0013 | 203-01-00100 | General Excavation | 25,649.42 | CUYD | 4.00 | 102,597.68 | 9.60 | 246,234.43 | 20.00 | 512,988.40 | 9.00 | 230,844.78 | | 0014 | 203-03-00100 | Embankment | 21,615.32 | CUYD | 21.00 | 453,921.72 | 18.00 | 389,075.76 | 26.00 | 561,998.32 | 20.00 | 432,306.40 | | 0015 | 203-07-00100 | Borrow (Vehicular Measurement) | 3,892.68 | CUYD | 18.00 | 70,068.24 | 18.00 | 70,068.24 | 26.00 | 101,209.68 | 33.00 | 128,458.44 | | 0016 | 204-02-00100 | Temporary Hay or Straw Bales | 273 | EACH | 19.00 | 5,187.00 | 16.00 | 4,368.00 | 58.00 | 15,834.00 | 15.00 | 4,095.00 | | 0017 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 145.00 | 2,320.00 | 160.00 | 2,560.00 | 500.00 | 8,000.00 | 125.00 | 2,000.00 | | 0018 | 204-06-00100 | Temporary Silt Fencing | 28,650 | LNFT | 2.65 | 75,922.50 | 2.00 | 57,300.00 | 2.50 | 71,625.00 | 2.00 | 57,300.00 | | 0019 | 302-02-06000 | Class II Base Course (12" Thick) (Soil Cement or 6" Asph. Conc. Base on 6" Embankment Layer) | 76,294.9 | SQYD | 21.50 | 1,640,340.35 | 22.00 | 1,678,487.80 | 11.00 | 839,243.90 | 22.00 | 1,678,487.80 | | 0020 | 304-05-00100 | Lime Treatment (Type E) | 1,081.48 | TON | 25.00 | 27,037.00 | 330.00 | 356,888.40 | 400.00 | 432,592.00 | 300.00 | 324,444.00 | | 0021 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 7,493.09 | TON | 120.00 | 899,170.80 | 147.00 | 1,101,484.23 | 170.00 | 1,273,825.30 | 125.00 | 936,636.25 | | 0022 | 501-02-00001 | Tack Coat | 29,016.53 | GAL | 4.00 | 116,066.12 | 3.80 | 110,262.81 | 3.50 | 101,557.86 | 6.00 | 174,099.18 | | 0023 | 502-01-00100 | Superpave Asphaltic Concrete | 65,812.33 | TON | 74.00 | 4,870,112.42 | 84.25 | 5,544,688.80 | 80.00 | 5,264,986.40 | 76.00 | 5,001,737.08 | | 0024 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 821.88 | TON | 150.00 | 123,282.00 | 168.00 | 138,075.84 | 123.00 | 101,091.24 | 155.00 | 127,391.40 | | 0025 | 509-01-00100 | Cold Planing Asphaltic Pavement | 108,618.16 | SQYD | 2.00 | 217,236.32 | 2.60 | 282,407.22 | 2.25 | 244,390.86 | 2.00 | 217,236.32 | | 0026 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,879.35 | CUYD | 0.30 | -1,463.81 | 0.00 | 0.00 | 0.25 | -1,219.84 | 1.00 | -4,879.35 | | 0027 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 2,824 | LNFT | 84.00 | 237,216.00 | 68.00 | 192,032.00 | 120.00 | 338,880.00 | 66.00 | 186,384.00 | | 0028 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 8 | LNFT | 229.00 | 1,832.00 | 88.00 | 704.00 | 130.00 | 1,040.00 | 115.00 | 920.00 | | 0029 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 4 | LNFT | 420.00 | 1,680.00 | 132.00 | 528.00 | 180.00 | 720.00 | 210.00 | 840.00 | | 0030 | 701-14-00100 | Cleaning Existing Pipes | 500 | LNFT | 22.00 | 11,000.00 | 17.00 | 8,500.00 | 10.00 | 5,000.00 | 22.00 | 11,000.00 | | 0031 | 701-15-00100 | Concrete Collar | 3 | EACH | 1,200.00 | 3,600.00 | 900.00 | 2,700.00 | 1,500.00 | 4,500.00 | 1,300.00 | 3,900.00 | | 0032 | 702-03-00100 | Catch Basins (CB-01) | 32 | EACH | 3,800.00 | 121,600.00 | 3,200.00 | 102,400.00 | 2,600.00 | 83,200.00 | 4,000.00 | 128,000.00 | | 0033 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 162.5 | LNFT | 65.00 | 10,562.50 | 70.00 | 11,375.00 | 75.00 | 12,187.50 | 65.00 | 10,562.50 | | 0034 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | 281.55 | LNFT | 55.00 | 15,485.25 | 60.00 | 16,893.00 | 60.00 | 16,893.00 | 55.00 | 15,485.25 | | 0035 | 704-02-00100 | Guard Rail (Double Faced) | 37.5 | LNFT | 30.00 | 1,125.00 | 33.00 | 1,237.50 | 35.00 | 1,312.50 | 30.00 | 1,125.00 | | 0036 | 704-03-00100 | Blocked Out Guard Rail | 1,025 | LNFT | 21.00 | 21,525.00 | 23.00 | 23,575.00 | 25.00 | 25,625.00 | 21.00 | 21,525.00 | | 0037 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 43.75 | LNFT | 95.00 | 4,156.25 | 105.00 | 4,593.75 | 110.00 | 4,812.50 | 95.00 | 4,156.25 | | 0038 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 25 | LNFT | 40.00 | 1,000.00 | 44.00 | 1,100.00 | 45.00 | 1,125.00 | 40.00 | 1,000.00 | | 0039 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 93.75 | LNFT | 65.00 | 6,093.75 | 71.00 | 6,656.25 | 75.00 | 7,031.25 | 65.00 | 6,093.75 | | 0040 | 704-11-00100 | Guard Rail End Treatment (Flared) | 11 | EACH | 2,300.00 | 25,300.00 | 2,500.00 | 27,500.00 | 2,600.00 | 28,600.00 | 2,300.00 | 25,300.00 | | 0041 | 704-11-00300 | Guard Rail End Treatment (Bi-Directional) | 1 | EACH | 5,800.00 | 5,800.00 | 6,400.00 | 6,400.00 | 6,600.00 | 6,600.00 | 5,800.00 | 5,800.00 | | 0042 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 13.9 | SQYD | 165.00 | 2,293.50 | 66.00 | 917.40 | 350.00 | 4,865.00 | 145.00 | 2,015.50 | | 0043 | 710-01-00100 | Flowable Fill | 5 | CUYD | 400.00 | 2,000.00 | 220.00 | 1,100.00 | 1,200.00 | 6,000.00 | 300.00 | 1,500.00 | | 0044 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 350 | SQYD | 96.00 | 33,600.00 | 117.00 | 40,950.00 | 110.00 | 38,500.00 | 75.00 | 26,250.00 | | 0045 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 75,000.00 | 75,000.00 | 500,000.00 | 500,000.00 | 170,000.00 | 170,000.00 | 125,000.00 | 125,000.00 | | 0046 | 713-02-00100 | Temporary Pavement Markings (4" Width) TEMP. DOTTED | 1,500 | LNFT | 0.20 | 300.00 | 0.20 | 300.00 | 0.25 | 375.00 | 0.20 | 300.00 | | 0047 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 10.25 | MILE | 230.00 | 2,357.50 | 180.00 | 1,845.00 | 900.00 | 9,225.00 | 625.00 | 6,406.25 | | 0048 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 20.5 | MILE | 625.00 | 12,812.50 | 690.00 | 14,145.00 | 17,500.00 | 358,750.00 | 625.00 | 12,812.50 | | 0049 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 2 | EACH | 50.00 | 100.00 | 55.00 | 110.00 | 60.00 | 120.00 | 50.00 | 100.00 | | 0050 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 8,400 | EACH | 5.00 | 42,000.00 | 5.50 | 46,200.00 | 6.00 | 50,400.00 | 5.00 | 42,000.00 | | 0051 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 1,720 | EACH | 650.00 | 1,118,000.00 | 1,000.00 | 1,720,000.00 | 550.00 | 946,000.00 | 675.00 | 1,161,000.00 | | 0052 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 750 | EACH | 150.00 | 112,500.00 | 92.00 | 69,000.00 | 380.00 | 285,000.00 | 200.00 | 150,000.00 | | 0053 | 716-01-00100 | Mulch (Vegetative) | 48.5 | TON | 550.00 | 26,675.00 | 830.00 | 40,255.00 | 620.00 | 30,070.00 | 550.00 | 26,675.00 | | 0054 | 717-01-00100 | Seeding | 970 | LB | 10.00 | 9,700.00 | 16.50 | 16,005.00 | 11.00 | 10,670.00 | 10.00 | 9,700.00 | | 0055 | 718-01-00100 | Fertilizer | 24,250 | LB | 0.55 | 13,337.50 | 0.55 | 13,337.50 | 0.60 | 14,550.00 | 0.55 | 13,337.50 | | 0056 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | 123,000.00 | 123,000.00 | 30,000.00 | 30,000.00 | | 0057 | 726-01-00100 | Bedding Material | 243.65 | CUYD | 67.04 | 16,334.30 | 66.00 | 16,080.90 | 85.00 | 20,710.25 | 90.00 | 21,928.50 | | 0058 | 727-01-00100 | Mobilization | 1 | LUMP | 2,050,000.00 | 2,050,000.00 | 1,588,000.00 | 1,588,000.00 | 1,816,000.00 | 1,816,000.00 | 2,200,000.00 | 2,200,000.00 | | 0059 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 92.1 | SQFT | 22.00 | 2,026.20 | 22.00 | 2,026.20 | 25.00 | 2,302.50 | 22.00 | 2,026.20 | | 0060 | 729-04-00102 | Sign (Type D)(Furnish and Install) | 30 | SQFT | 25.00 | 750.00 | 22.00 | 660.00 | 30.00 | 900.00 | 25.00 | 750.00 | | 0061 | 729-05-00102 | Sign (Type E)(Furnish and Install) | 57 | SQFT | 25.00 | 1,425.00 | 22.00 | 1,254.00 | 30.00 | 1,710.00 | 25.00 | 1,425.00 | | 0062 | 729-06-00102 | Sign (Overhead Mounted)(Furnish and Install) | 546 | SQFT | 32.00 | 17,472.00 | 27.00 | 14,742.00 | 35.00 | 19,110.00 | 32.00 | 17,472.00 | | 0063 | 729-08-00200 | Mounting (3 1/2" Size Post) | 4 | EACH | 950.00 | 3,800.00 | 770.00 | 3,080.00 | 1,100.00 | 4,400.00 | 950.00 | 3,800.00 | | 0064 | 729-08-00210 | Mounting (3 1/2" Size Post)(Structure Mount) | 1 | EACH | 800.00 | 800.00 | 800.00 | 800.00 | 915.00 | 915.00 | 800.00 | 800.00 | | 0065 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 2 | EACH | 1,100.00 | 2,200.00 | 1,100.00 | 2,200.00 | 1,250.00 | 2,500.00 | 1,100.00 | 2,200.00 | | 0066 | 729-11-00100 | Mounting (Overhead Cantilever) (Ground Mounted) | 3 | EACH | 37,000.00 | 111,000.00 | 29,000.00 | 87,000.00 | 43,000.00 | 129,000.00 | 37,000.00 | 111,000.00 | | 0067 | 729-16-00300 | Object Marker Assembly (Type 3) | 19 | EACH | 85.00 | 1,615.00 | 93.00 | 1,767.00 | 100.00 | 1,900.00 | 85.00 | 1,615.00 | | 0068 | 729-17-00100 | Milepost Assembly (Ground Mounted) | 1 | EACH | 300.00 | 300.00 | 220.00 | 220.00 | 350.00 | 350.00 | 300.00 | 300.00 | | 0069 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 24 | EACH | 275.00 | 6,600.00 | 270.00 | 6,480.00 | 315.00 | 7,560.00 | 275.00 | 6,600.00 | | 0070 | 729-20-00600 | Footings for Overhead Mountings (Cantilever) | 3 | EACH | 20,000.00 | 60,000.00 | 18,000.00 | 54,000.00 | 18,000.00 | 54,000.00 | 37,500.00 | 112,500.00 | | 0071 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") Conduit w/ Conductors (PVC)(2")(Empty Conduit with Pull Rope) | 3,500 | LNFT | 2.42 | 8,470.00 | 4.40 | 15,400.00 | 2.00 | 7,000.00 | 4.00 | 14,000.00 | | 0072 | 730-04-00200 | Jacked or Bored Casing (6" Diameter) (PVC/HDPE) (S80 PVC) | 200 | LNFT | 54.50 | 10,900.00 | 34.00 | 6,800.00 | 60.00 | 12,000.00 | 31.00 | 6,200.00 | | 0073 | 730-09-00100 | Electrical System | 1 | LUMP | 28,630.00 | 28,630.00 | 10,000.00 | 10,000.00 | 35,000.00 | 35,000.00 | 9,900.00 | 9,900.00 | | 0074 | 730-16-00200 | Underground Junction Box (11" x 18") (JB-2) | 21 | EACH | 593.00 | 12,453.00 | 1,700.00 | 35,700.00 | 700.00 | 14,700.00 | 1,558.00 | 32,718.00 | | 0075 | 730-16-00300 | Underground Junction Box (13" x 24") (JB-3) | 1 | EACH | 785.00 | 785.00 | 900.00 | 900.00 | 885.00 | 885.00 | 838.00 | 838.00 | | 0076 | 730-21-00020 | Duct Marker (Concrete) | 3 | EACH | 267.00 | 801.00 | 780.00 | 2,340.00 | 300.00 | 900.00 | 708.00 | 2,124.00 | | 0077 | 731-02-00100 | Reflectorized Raised Pavement Markers | 5,295 | EACH | 7.50 | 39,712.50 | 8.20 | 43,419.00 | 10.00 | 52,950.00 | 7.50 | 39,712.50 | | 0078 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.58 | MILE | 3,450.00 | 36,501.00 | 3,800.00 | 40,204.00 | 4,300.00 | 45,494.00 | 3,450.00 | 36,501.00 | | 0079 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.45 | MILE | 7,500.00 | 3,375.00 | 8,000.00 | 3,600.00 | 10,000.00 | 4,500.00 | 7,500.00 | 3,375.00 | | 0080 | 732-02-02080 | Plastic Pavement Striping (Solid Line) (24" Width) (Thermoplastic 90 mil) | 0.15 | MILE | 50,000.00 | 7,500.00 | 55,000.00 | 8,250.00 | 62,000.00 | 9,300.00 | 50,000.00 | 7,500.00 | | 0081 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 9.8 | MILE | 1,000.00 | 9,800.00 | 1,100.00 | 10,780.00 | 1,200.00 | 11,760.00 | 1,000.00 | 9,800.00 | | 0082 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.74 | MILE | 3,000.00 | 2,220.00 | 3,300.00 | 2,442.00 | 3,700.00 | 2,738.00 | 3,000.00 | 2,220.00 | | 0083 | 732-04-05040 | Plastic Pavement Legends and Symbols (EXIT ONLY) | 6 | EACH | 525.00 | 3,150.00 | 580.00 | 3,480.00 | 650.00 | 3,900.00 | 525.00 | 3,150.00 | | 0084 | 732-05-00100 | Removal of Existing Markings | 10.25 | MILE | 5,000.00 | 51,250.00 | 5,500.00 | 56,375.00 | 6,200.00 | 63,550.00 | 5,000.00 | 51,250.00 | | 0085 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) (137+00-148+28) | 1,130 | LNFT | 80.00 | 90,400.00 | 235.00 | 265,550.00 | 75.00 | 84,750.00 | 15.00 | 16,950.00 | | 0086 | 733-01-00200 | Concrete Roadway Barrier (Double Faced) | 11,834 | LNFT | 265.00 | 3,136,010.00 | 248.00 | 2,934,832.00 | 350.00 | 4,141,900.00 | 360.00 | 4,260,240.00 | | 0087 | 736-12-00988 | Conductor (1c, #8 awg) | 300 | LNFT | 0.65 | 195.00 | 1.10 | 330.00 | 0.75 | 225.00 | 1.00 | 300.00 | | 0088 | 740-01-00100 | Construction Layout | 1 | LUMP | 200,000.00 | 200,000.00 | 250,000.00 | 250,000.00 | 358,000.00 | 358,000.00 | 175,000.00 | 175,000.00 | | 0089 | 802-02-00100 | Structural Excavation for Intermediate Bents | 808.89 | CUYD | 20.00 | 16,177.80 | 71.00 | 57,431.19 | 100.00 | 80,889.00 | 42.00 | 33,973.38 | | 0090 | 804-01-00200 | Precast Concrete Piles (14") | 200 | LNFT | 50.00 | 10,000.00 | 55.00 | 11,000.00 | 35.00 | 7,000.00 | 48.00 | 9,600.00 | | 0091 | 804-01-00300 | Precast Concrete Piles (16") | 5,960 | LNFT | 52.00 | 309,920.00 | 71.00 | 423,160.00 | 56.00 | 333,760.00 | 52.00 | 309,920.00 | | 0092 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1,500.00 | 1,500.00 | 5,500.00 | 5,500.00 | 38,000.00 | 38,000.00 | 2,500.00 | 2,500.00 | | 0093 | 804-13-00100 | Precast Concrete Indicator Piles | 1 | EACH | 45,000.00 | 45,000.00 | 12,000.00 | 12,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | | 0094 | 804-17-00100 | Dynamic Monitoring | 6 | EACH | 2,000.00 | 12,000.00 | 3,800.00 | 22,800.00 | 9,000.00 | 54,000.00 | 1,200.00 | 7,200.00 | | 0095 | 805-01-00500 | Class A Concrete (Footings) | 173.82 | CUYD | 400.00 | 69,528.00 | 700.00 | 121,674.00 | 600.00 | 104,292.00 | 560.00 | 97,339.20 | | 0096 | 805-02-00400 | Class A(M) Concrete (Bents) | 313.66 | CUYD | 800.00 | 250,928.00 | 1,380.00 | 432,850.80 | 1,000.00 | 313,660.00 | 1,500.00 | 470,490.00 | | 0097 | 805-04-00100 | Class AA(M) Concrete | 523.12 | CUYD | 700.00 | 366,184.00 | 2,000.00 | 1,046,240.00 | 860.00 | 449,883.20 | 1,650.00 | 863,148.00 | | 0098 | 806-01-00100 | Deformed Reinforcing Steel | 346,037 | LB | 1.70 | 588,262.90 | 1.20 | 415,244.40 | 2.00 | 692,074.00 | 2.00 | 692,074.00 | | 0099 | 807-08-00100 | Structural Metalwork | 8,262 | LUMP | 60,000.00 | 60,000.00 | 71,000.00 | 71,000.00 | 20,000.00 | 20,000.00 | 60,000.00 | 60,000.00 | | 0100 | 810-01-00100 | Concrete Railing (Standard Barrier) | 1,185 | LNFT | 67.00 | 79,395.00 | 67.00 | 79,395.00 | 80.00 | 94,800.00 | 75.00 | 88,875.00 | | 0101 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 702 | LNFT | 70.00 | 49,140.00 | 73.00 | 51,246.00 | 60.00 | 42,120.00 | 88.00 | 61,776.00 | | 0102 | 813-01-00100 | Concrete Approach Slabs | 213.34 | SQYD | 250.00 | 53,335.00 | 330.00 | 70,402.20 | 340.00 | 72,535.60 | 385.00 | 82,135.90 | | 0103 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 500 | TON | 145.00 | 72,500.00 | 175.00 | 87,500.00 | 135.00 | 67,500.00 | 150.00 | 75,000.00 | | 0104 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 22,000 | INLF | 1.00 | 22,000.00 | 0.80 | 17,600.00 | 1.00 | 22,000.00 | 1.00 | 22,000.00 | | 0105 | NS-509-00001 | Micro-Milling Asphaltic Pavement | 22,630 | SQYD | 3.00 | 67,890.00 | 2.40 | 54,312.00 | 3.00 | 67,890.00 | 3.10 | 70,153.00 | | 0106 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 5,000 | INLF | 0.85 | 4,250.00 | 0.90 | 4,500.00 | 1.50 | 7,500.00 | 1.50 | 7,500.00 | | 0107 | NS-700-00180 | Impact Attenuator (Construction Zone) | 5 | EACH | 11,000.00 | 55,000.00 | 9,500.00 | 47,500.00 | 10,000.00 | 50,000.00 | 10,000.00 | 50,000.00 | | 0108 | NS-700-00220 | Impact Attenuator (Kinetic) | 1 | EACH | 22,000.00 | 22,000.00 | 20,000.00 | 20,000.00 | 22,000.00 | 22,000.00 | 20,000.00 | 20,000.00 | | 0109 | NS-704-00001 | High Tension Cable Barrier | 300 | LNFT | 20.00 | 6,000.00 | 22.00 | 6,600.00 | 86.00 | 25,800.00 | 21.00 | 6,300.00 | | 0110 | NS-704-00001 | High Tension Cable Barrier Temporary (134+00 - 135+00) | 100 | LNFT | 20.00 | 2,000.00 | 22.00 | 2,200.00 | 86.00 | 8,600.00 | 82.00 | 8,200.00 | | 0111 | NS-704-00002 | Cable Barrier Gated End Terminal Temporary (Sta. 135+00) | 1 | EACH | 5,000.00 | 5,000.00 | 6,900.00 | 6,900.00 | 7,500.00 | 7,500.00 | 5,000.00 | 5,000.00 | | 0112 | NS-704-00002 | Cable Barrier Gated End Terminal | 1 | EACH | 5,500.00 | 5,500.00 | 6,900.00 | 6,900.00 | 7,500.00 | 7,500.00 | 4,000.00 | 4,000.00 | | 0113 | NS-704-00003 | Concrete Strip Sta. 134+00 - 137+00 | 100 | SQYD | 65.00 | 6,500.00 | 110.00 | 11,000.00 | 150.00 | 15,000.00 | 80.00 | 8,000.00 | | 0114 | NS-713-00008 | Portable Changeable Message Sign | 2 | EACH | 5,000.00 | 10,000.00 | 10,000.00 | 20,000.00 | 19,000.00 | 38,000.00 | 20,000.00 | 40,000.00 | | 0115 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 11.47 | MILE | 300.00 | 3,441.00 | 500.00 | 5,735.00 | 650.00 | 7,455.50 | 475.00 | 5,448.25 | | 0116 | NS-800-00009 | Epoxy-Urethane Overlay System | 54,086 | SQFT | 9.50 | 513,817.00 | 3.90 | 210,935.40 | 12.00 | 649,032.00 | 3.55 | 192,005.30 | | 0117 | NS-800-00181 | Precast Prestressed Concrete Girder (Type III) Class P (HPC) | 2,440.5 | LNFT | 160.00 | 390,480.00 | 138.00 | 336,789.00 | 130.00 | 317,265.00 | 105.00 | 256,252.50 | | 0118 | NS-805-00005 | Joint Sealing System (Preformed Silicone) | 347.4 | LNFT | 70.00 | 24,318.00 | 55.00 | 19,107.00 | 15.00 | 5,211.00 | 60.00 | 20,844.00 | | 0119 | NS-ITS-02010 | Dynamic Message Sign, Install, LED Full Matrix, Walk-in | 1 | EACH | 225,000.00 | 225,000.00 | 128,000.00 | 128,000.00 | 28,000.00 | 28,000.00 | 166,487.00 | 166,487.00 | | 0120 | NS-ITS-03521 | DMS Site, Remove | 1 | EACH | 50,000.00 | 50,000.00 | 13,000.00 | 13,000.00 | 15,000.00 | 15,000.00 | 11,544.00 | 11,544.00 | | 0121 | NS-ITS-10340 | Data Surge Suppressor, Furnish & Install | 2 | EACH | 370.00 | 740.00 | 390.00 | 780.00 | 500.00 | 1,000.00 | 355.00 | 710.00 | | 0122 | NS-ITS-15420 | 2" Rigid Aluminum Conduit | 200 | LNFT | 41.25 | 8,250.00 | 9.60 | 1,920.00 | 50.00 | 10,000.00 | 8.70 | 1,740.00 | | 0123 | NS-MSC-00120 | Drainage Structure CAP CB-01 | 7 | EACH | 2,000.00 | 14,000.00 | 1,900.00 | 13,300.00 | 3,000.00 | 21,000.00 | 2,000.00 | 14,000.00 | | 0124 | NS-MSC-00120 | Drainage Structure PLUG PIPE (1001, 1007, 1008, 1009, 1010, 1011) | 6 | EACH | 2,000.00 | 12,000.00 | 440.00 | 2,640.00 | 400.00 | 2,400.00 | 1,500.00 | 9,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 20,684,655.70 | | 22,594,372.91 | | 23,244,714.29 | | 22,847,145.20 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - GILCHRIST CONSTRUCTION CO. LLC | - 6 - Diamond B Construction Co., L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 200,000.00 | 200,000.00 | 150,000.00 | 150,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 200,000.00 | 200,000.00 | 130,000.00 | 130,000.00 | | 0003 | 202-02-04001 | Removal of Bridge (Partial Removal) END BENTS AND WINGWALLS | 1 | LUMP | 30,000.00 | 30,000.00 | 25,000.00 | 25,000.00 | | 0004 | 202-02-04110 | Removal of Bridge Superstructure (Concrete Girder Span) | 3,920 | SQFT | 16.00 | 62,720.00 | 22.00 | 86,240.00 | | 0005 | 202-02-06000 | Removal of Concrete Approach Slabs | 448.67 | SQYD | 75.00 | 33,650.25 | 40.00 | 17,946.80 | | 0006 | 202-02-06060 | Removal of Concrete Catch Basin | 4 | EACH | 1,000.00 | 4,000.00 | 2,000.00 | 8,000.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 1,059.53 | LNFT | 8.00 | 8,476.24 | 10.00 | 10,595.30 | | 0008 | 202-02-32100 | Removal of Pipe (Cross Drain) END JOINTS (1001, 1007, 1008, 1009, 1010, 1011) | 48 | LNFT | 40.00 | 1,920.00 | 20.00 | 960.00 | | 0009 | 202-02-32180 | Removal of Pipe Headwalls | 6 | EACH | 1,500.00 | 9,000.00 | 1,500.00 | 9,000.00 | | 0010 | 202-02-38220 | Removal of Sign Supports | 18 | EACH | 250.00 | 4,500.00 | 250.00 | 4,500.00 | | 0011 | 202-02-38360 | Removal of Sign Faces | 18 | EACH | 55.00 | 990.00 | 60.00 | 1,080.00 | | 0012 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 13,796.02 | SQYD | 5.00 | 68,980.10 | 15.00 | 206,940.30 | | 0013 | 203-01-00100 | General Excavation | 25,649.42 | CUYD | 4.60 | 117,987.33 | 6.50 | 166,721.23 | | 0014 | 203-03-00100 | Embankment | 21,615.32 | CUYD | 14.00 | 302,614.48 | 15.00 | 324,229.80 | | 0015 | 203-07-00100 | Borrow (Vehicular Measurement) | 3,892.68 | CUYD | 21.00 | 81,746.28 | 12.50 | 48,658.50 | | 0016 | 204-02-00100 | Temporary Hay or Straw Bales | 273 | EACH | 17.00 | 4,641.00 | 25.00 | 6,825.00 | | 0017 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 150.00 | 2,400.00 | 150.00 | 2,400.00 | | 0018 | 204-06-00100 | Temporary Silt Fencing | 28,650 | LNFT | 1.75 | 50,137.50 | 2.00 | 57,300.00 | | 0019 | 302-02-06000 | Class II Base Course (12" Thick) (Soil Cement or 6" Asph. Conc. Base on 6" Embankment Layer) | 76,294.9 | SQYD | 18.00 | 1,373,308.20 | 30.00 | 2,288,847.00 | | 0020 | 304-05-00100 | Lime Treatment (Type E) | 1,081.48 | TON | 200.00 | 216,296.00 | 250.00 | 270,370.00 | | 0021 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 7,493.09 | TON | 150.00 | 1,123,963.50 | 145.00 | 1,086,498.05 | | 0022 | 501-02-00001 | Tack Coat | 29,016.53 | GAL | 4.00 | 116,066.12 | 3.50 | 101,557.86 | | 0023 | 502-01-00100 | Superpave Asphaltic Concrete | 65,812.33 | TON | 98.00 | 6,449,608.34 | 88.00 | 5,791,485.04 | | 0024 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 821.88 | TON | 185.00 | 152,047.80 | 140.00 | 115,063.20 | | 0025 | 509-01-00100 | Cold Planing Asphaltic Pavement | 108,618.16 | SQYD | 2.25 | 244,390.86 | 3.75 | 407,318.10 | | 0026 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,879.35 | CUYD | 1.00 | -4,879.35 | 1.00 | -4,879.35 | | 0027 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 2,824 | LNFT | 95.00 | 268,280.00 | 75.00 | 211,800.00 | | 0028 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 8 | LNFT | 270.00 | 2,160.00 | 95.00 | 760.00 | | 0029 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 4 | LNFT | 300.00 | 1,200.00 | 135.00 | 540.00 | | 0030 | 701-14-00100 | Cleaning Existing Pipes | 500 | LNFT | 40.00 | 20,000.00 | 18.00 | 9,000.00 | | 0031 | 701-15-00100 | Concrete Collar | 3 | EACH | 1,900.00 | 5,700.00 | 1,000.00 | 3,000.00 | | 0032 | 702-03-00100 | Catch Basins (CB-01) | 32 | EACH | 3,400.00 | 108,800.00 | 3,400.00 | 108,800.00 | | 0033 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 162.5 | LNFT | 70.00 | 11,375.00 | 75.00 | 12,187.50 | | 0034 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | 281.55 | LNFT | 60.00 | 16,893.00 | 50.00 | 14,077.50 | | 0035 | 704-02-00100 | Guard Rail (Double Faced) | 37.5 | LNFT | 32.00 | 1,200.00 | 36.00 | 1,350.00 | | 0036 | 704-03-00100 | Blocked Out Guard Rail | 1,025 | LNFT | 23.00 | 23,575.00 | 22.00 | 22,550.00 | | 0037 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 43.75 | LNFT | 100.00 | 4,375.00 | 115.00 | 5,031.25 | | 0038 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 25 | LNFT | 42.00 | 1,050.00 | 44.00 | 1,100.00 | | 0039 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 93.75 | LNFT | 68.00 | 6,375.00 | 70.00 | 6,562.50 | | 0040 | 704-11-00100 | Guard Rail End Treatment (Flared) | 11 | EACH | 2,500.00 | 27,500.00 | 2,500.00 | 27,500.00 | | 0041 | 704-11-00300 | Guard Rail End Treatment (Bi-Directional) | 1 | EACH | 6,000.00 | 6,000.00 | 4,700.00 | 4,700.00 | | 0042 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 13.9 | SQYD | 300.00 | 4,170.00 | 165.00 | 2,293.50 | | 0043 | 710-01-00100 | Flowable Fill | 5 | CUYD | 135.00 | 675.00 | 200.00 | 1,000.00 | | 0044 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 350 | SQYD | 100.00 | 35,000.00 | 125.00 | 43,750.00 | | 0045 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 440,000.00 | 440,000.00 | 500,000.00 | 500,000.00 | | 0046 | 713-02-00100 | Temporary Pavement Markings (4" Width) TEMP. DOTTED | 1,500 | LNFT | 0.22 | 330.00 | 0.22 | 330.00 | | 0047 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 10.25 | MILE | 225.00 | 2,306.25 | 150.00 | 1,537.50 | | 0048 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 20.5 | MILE | 650.00 | 13,325.00 | 625.00 | 12,812.50 | | 0049 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 2 | EACH | 55.00 | 110.00 | 50.00 | 100.00 | | 0050 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 8,400 | EACH | 5.50 | 46,200.00 | 5.00 | 42,000.00 | | 0051 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 1,720 | EACH | 575.00 | 989,000.00 | 900.00 | 1,548,000.00 | | 0052 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 750 | EACH | 200.00 | 150,000.00 | 115.00 | 86,250.00 | | 0053 | 716-01-00100 | Mulch (Vegetative) | 48.5 | TON | 600.00 | 29,100.00 | 650.00 | 31,525.00 | | 0054 | 717-01-00100 | Seeding | 970 | LB | 11.00 | 10,670.00 | 10.00 | 9,700.00 | | 0055 | 718-01-00100 | Fertilizer | 24,250 | LB | 0.58 | 14,065.00 | 0.60 | 14,550.00 | | 0056 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 16,000.00 | 16,000.00 | 20,000.00 | 20,000.00 | | 0057 | 726-01-00100 | Bedding Material | 243.65 | CUYD | 110.00 | 26,801.50 | 75.00 | 18,273.75 | | 0058 | 727-01-00100 | Mobilization | 1 | LUMP | 2,300,000.00 | 2,300,000.00 | 2,400,000.00 | 2,400,000.00 | | 0059 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 92.1 | SQFT | 23.00 | 2,118.30 | 25.00 | 2,302.50 | | 0060 | 729-04-00102 | Sign (Type D)(Furnish and Install) | 30 | SQFT | 27.00 | 810.00 | 30.00 | 900.00 | | 0061 | 729-05-00102 | Sign (Type E)(Furnish and Install) | 57 | SQFT | 27.00 | 1,539.00 | 25.00 | 1,425.00 | | 0062 | 729-06-00102 | Sign (Overhead Mounted)(Furnish and Install) | 546 | SQFT | 35.00 | 19,110.00 | 35.00 | 19,110.00 | | 0063 | 729-08-00200 | Mounting (3 1/2" Size Post) | 4 | EACH | 1,000.00 | 4,000.00 | 1,000.00 | 4,000.00 | | 0064 | 729-08-00210 | Mounting (3 1/2" Size Post)(Structure Mount) | 1 | EACH | 850.00 | 850.00 | 850.00 | 850.00 | | 0065 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 2 | EACH | 1,150.00 | 2,300.00 | 1,200.00 | 2,400.00 | | 0066 | 729-11-00100 | Mounting (Overhead Cantilever) (Ground Mounted) | 3 | EACH | 38,000.00 | 114,000.00 | 41,000.00 | 123,000.00 | | 0067 | 729-16-00300 | Object Marker Assembly (Type 3) | 19 | EACH | 90.00 | 1,710.00 | 75.00 | 1,425.00 | | 0068 | 729-17-00100 | Milepost Assembly (Ground Mounted) | 1 | EACH | 325.00 | 325.00 | 350.00 | 350.00 | | 0069 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 24 | EACH | 300.00 | 7,200.00 | 325.00 | 7,800.00 | | 0070 | 729-20-00600 | Footings for Overhead Mountings (Cantilever) | 3 | EACH | 33,000.00 | 99,000.00 | 50,000.00 | 150,000.00 | | 0071 | 730-02-01100 | Conduit with Conductors (PVC/HDPE) (2") Conduit w/ Conductors (PVC)(2")(Empty Conduit with Pull Rope) | 3,500 | LNFT | 2.50 | 8,750.00 | 3.00 | 10,500.00 | | 0072 | 730-04-00200 | Jacked or Bored Casing (6" Diameter) (PVC/HDPE) (S80 PVC) | 200 | LNFT | 58.00 | 11,600.00 | 65.00 | 13,000.00 | | 0073 | 730-09-00100 | Electrical System | 1 | LUMP | 30,000.00 | 30,000.00 | 35,000.00 | 35,000.00 | | 0074 | 730-16-00200 | Underground Junction Box (11" x 18") (JB-2) | 21 | EACH | 650.00 | 13,650.00 | 600.00 | 12,600.00 | | 0075 | 730-16-00300 | Underground Junction Box (13" x 24") (JB-3) | 1 | EACH | 800.00 | 800.00 | 1,000.00 | 1,000.00 | | 0076 | 730-21-00020 | Duct Marker (Concrete) | 3 | EACH | 300.00 | 900.00 | 300.00 | 900.00 | | 0077 | 731-02-00100 | Reflectorized Raised Pavement Markers | 5,295 | EACH | 8.00 | 42,360.00 | 9.00 | 47,655.00 | | 0078 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.58 | MILE | 3,600.00 | 38,088.00 | 3,900.00 | 41,262.00 | | 0079 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.45 | MILE | 8,000.00 | 3,600.00 | 7,700.00 | 3,465.00 | | 0080 | 732-02-02080 | Plastic Pavement Striping (Solid Line) (24" Width) (Thermoplastic 90 mil) | 0.15 | MILE | 52,000.00 | 7,800.00 | 60,000.00 | 9,000.00 | | 0081 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 9.8 | MILE | 1,100.00 | 10,780.00 | 1,200.00 | 11,760.00 | | 0082 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.74 | MILE | 3,100.00 | 2,294.00 | 3,300.00 | 2,442.00 | | 0083 | 732-04-05040 | Plastic Pavement Legends and Symbols (EXIT ONLY) | 6 | EACH | 600.00 | 3,600.00 | 600.00 | 3,600.00 | | 0084 | 732-05-00100 | Removal of Existing Markings | 10.25 | MILE | 5,200.00 | 53,300.00 | 7,500.00 | 76,875.00 | | 0085 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) (137+00-148+28) | 1,130 | LNFT | 33.00 | 37,290.00 | 300.00 | 339,000.00 | | 0086 | 733-01-00200 | Concrete Roadway Barrier (Double Faced) | 11,834 | LNFT | 350.00 | 4,141,900.00 | 425.00 | 5,029,450.00 | | 0087 | 736-12-00988 | Conductor (1c, #8 awg) | 300 | LNFT | 0.70 | 210.00 | 1.00 | 300.00 | | 0088 | 740-01-00100 | Construction Layout | 1 | LUMP | 100,000.00 | 100,000.00 | 300,000.00 | 300,000.00 | | 0089 | 802-02-00100 | Structural Excavation for Intermediate Bents | 808.89 | CUYD | 30.00 | 24,266.70 | 70.00 | 56,622.30 | | 0090 | 804-01-00200 | Precast Concrete Piles (14") | 200 | LNFT | 47.00 | 9,400.00 | 55.00 | 11,000.00 | | 0091 | 804-01-00300 | Precast Concrete Piles (16") | 5,960 | LNFT | 67.00 | 399,320.00 | 70.00 | 417,200.00 | | 0092 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 5,500.00 | 5,500.00 | 5,500.00 | 5,500.00 | | 0093 | 804-13-00100 | Precast Concrete Indicator Piles | 1 | EACH | 23,400.00 | 23,400.00 | 12,000.00 | 12,000.00 | | 0094 | 804-17-00100 | Dynamic Monitoring | 6 | EACH | 800.00 | 4,800.00 | 4,000.00 | 24,000.00 | | 0095 | 805-01-00500 | Class A Concrete (Footings) | 173.82 | CUYD | 800.00 | 139,056.00 | 700.00 | 121,674.00 | | 0096 | 805-02-00400 | Class A(M) Concrete (Bents) | 313.66 | CUYD | 1,500.00 | 470,490.00 | 1,400.00 | 439,124.00 | | 0097 | 805-04-00100 | Class AA(M) Concrete | 523.12 | CUYD | 1,300.00 | 680,056.00 | 2,000.00 | 1,046,240.00 | | 0098 | 806-01-00100 | Deformed Reinforcing Steel | 346,037 | LB | 1.25 | 432,546.25 | 1.25 | 432,546.25 | | 0099 | 807-08-00100 | Structural Metalwork | 8,262 | LUMP | 32,000.00 | 32,000.00 | 80,000.00 | 80,000.00 | | 0100 | 810-01-00100 | Concrete Railing (Standard Barrier) | 1,185 | LNFT | 72.00 | 85,320.00 | 80.00 | 94,800.00 | | 0101 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 702 | LNFT | 72.00 | 50,544.00 | 80.00 | 56,160.00 | | 0102 | 813-01-00100 | Concrete Approach Slabs | 213.34 | SQYD | 260.00 | 55,468.40 | 250.00 | 53,335.00 | | 0103 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 500 | TON | 115.00 | 57,500.00 | 150.00 | 75,000.00 | | 0104 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 22,000 | INLF | 0.55 | 12,100.00 | 0.65 | 14,300.00 | | 0105 | NS-509-00001 | Micro-Milling Asphaltic Pavement | 22,630 | SQYD | 4.00 | 90,520.00 | 2.50 | 56,575.00 | | 0106 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 5,000 | INLF | 1.25 | 6,250.00 | 2.00 | 10,000.00 | | 0107 | NS-700-00180 | Impact Attenuator (Construction Zone) | 5 | EACH | 9,000.00 | 45,000.00 | 8,500.00 | 42,500.00 | | 0108 | NS-700-00220 | Impact Attenuator (Kinetic) | 1 | EACH | 22,000.00 | 22,000.00 | 14,000.00 | 14,000.00 | | 0109 | NS-704-00001 | High Tension Cable Barrier | 300 | LNFT | 17.00 | 5,100.00 | 60.00 | 18,000.00 | | 0110 | NS-704-00001 | High Tension Cable Barrier Temporary (134+00 - 135+00) | 100 | LNFT | 17.00 | 1,700.00 | 60.00 | 6,000.00 | | 0111 | NS-704-00002 | Cable Barrier Gated End Terminal Temporary (Sta. 135+00) | 1 | EACH | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 | | 0112 | NS-704-00002 | Cable Barrier Gated End Terminal | 1 | EACH | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 | | 0113 | NS-704-00003 | Concrete Strip Sta. 134+00 - 137+00 | 100 | SQYD | 140.00 | 14,000.00 | 60.00 | 6,000.00 | | 0114 | NS-713-00008 | Portable Changeable Message Sign | 2 | EACH | 25,000.00 | 50,000.00 | 15,000.00 | 30,000.00 | | 0115 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 11.47 | MILE | 550.00 | 6,308.50 | 350.00 | 4,014.50 | | 0116 | NS-800-00009 | Epoxy-Urethane Overlay System | 54,086 | SQFT | 4.20 | 227,161.20 | 5.00 | 270,430.00 | | 0117 | NS-800-00181 | Precast Prestressed Concrete Girder (Type III) Class P (HPC) | 2,440.5 | LNFT | 125.00 | 305,062.50 | 150.00 | 366,075.00 | | 0118 | NS-805-00005 | Joint Sealing System (Preformed Silicone) | 347.4 | LNFT | 68.00 | 23,623.20 | 60.00 | 20,844.00 | | 0119 | NS-ITS-02010 | Dynamic Message Sign, Install, LED Full Matrix, Walk-in | 1 | EACH | 26,000.00 | 26,000.00 | 30,000.00 | 30,000.00 | | 0120 | NS-ITS-03521 | DMS Site, Remove | 1 | EACH | 14,000.00 | 14,000.00 | 15,000.00 | 15,000.00 | | 0121 | NS-ITS-10340 | Data Surge Suppressor, Furnish & Install | 2 | EACH | 400.00 | 800.00 | 400.00 | 800.00 | | 0122 | NS-ITS-15420 | 2" Rigid Aluminum Conduit | 200 | LNFT | 45.00 | 9,000.00 | 45.00 | 9,000.00 | | 0123 | NS-MSC-00120 | Drainage Structure CAP CB-01 | 7 | EACH | 1,600.00 | 11,200.00 | 2,000.00 | 14,000.00 | | 0124 | NS-MSC-00120 | Drainage Structure PLUG PIPE (1001, 1007, 1008, 1009, 1010, 1011) | 6 | EACH | 1,600.00 | 9,600.00 | 500.00 | 3,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 23,551,777.45 | | 26,586,849.38 |
|