Proposal:H.006138.6
Parish:Jefferson
Description:POPLAR STREET BRIDGE OVER BONNABEL CANAL
Type Construction:CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE SURFACING, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$604,639.00
| Rank | License | Bidder | Construction Bid |
| 1 | 34567 | James Construction Group LLC | $707,778.97 |
| 2 | 39462 | JB JAMES CONSTRUCTION LLC | $889,969.59 |
| 3 | 36961 | Cycle Construction Co. L.L.C. | $942,200.00 |
| 4 | 46722 | Bld Services Llc | $1,341,420.40 |
| 5 | 04435 | Thigpen Construction Co., Inc. | $1,479,000.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - James Construction Group LLC | - 2 - JB JAMES CONSTRUCTION LLC | - 3 - Cycle Construction Co. L.L.C. | - 4 - Bld Services Llc | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 6,000.00 | 6,000.00 | 35,000.00 | 35,000.00 | 3,000.00 | 3,000.00 | 12,500.00 | 12,500.00 | | 0002 | 202-02-04000 | Removal of Bridge (STA 6+75; 29.3.' X 99.85' TIMBER BRIDGE WITH ASPHALT) | 1 | EACH | 49,125.00 | 49,125.00 | 43,000.00 | 43,000.00 | 23,000.00 | 23,000.00 | 41,000.00 | 41,000.00 | | 0003 | 202-02-06000 | Removal of Concrete Approach Slabs | 95 | SQYD | 32.00 | 3,040.00 | 34.45 | 3,272.75 | 26.00 | 2,470.00 | 16.00 | 1,520.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 36 | SQYD | 11.00 | 396.00 | 34.43 | 1,239.48 | 18.00 | 648.00 | 10.00 | 360.00 | | 0005 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 461 | SQYD | 11.00 | 5,071.00 | 10.03 | 4,623.83 | 14.00 | 6,454.00 | 12.00 | 5,532.00 | | 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 7,000.00 | 7,000.00 | 26,000.00 | 26,000.00 | 22,000.00 | 22,000.00 | 45,000.00 | 45,000.00 | | 0007 | 204-06-00100 | Temporary Silt Fencing | 358 | LNFT | 5.00 | 1,790.00 | 6.46 | 2,312.68 | 3.00 | 1,074.00 | 4.00 | 1,432.00 | | 0008 | 302-01-00800 | Class II Base Course (Stone or Recycled Portland Cement Concrete) | 113.9 | CUYD | 97.48 | 11,102.97 | 86.34 | 9,834.13 | 101.00 | 11,503.90 | 86.00 | 9,795.40 | | 0009 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 20 | CUYD | 50.00 | 1,000.00 | 66.63 | 1,332.60 | 65.00 | 1,300.00 | 67.00 | 1,340.00 | | 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 89.6 | TON | 200.00 | 17,920.00 | 248.71 | 22,284.42 | 232.00 | 20,787.20 | 250.00 | 22,400.00 | | 0011 | 702-04-00100 | Adjusting Manholes | 1 | EACH | 3,000.00 | 3,000.00 | 2,567.59 | 2,567.59 | 1,000.00 | 1,000.00 | 700.00 | 700.00 | | 0012 | 705-09-00100 | Rebuilt Fence | 50 | LNFT | 60.00 | 3,000.00 | 49.74 | 2,487.00 | 55.00 | 2,750.00 | 40.00 | 2,000.00 | | 0013 | 706-01-00100 | Concrete Walk (4" Thick) | 7 | SQYD | 104.00 | 728.00 | 87.26 | 610.82 | 200.00 | 1,400.00 | 80.00 | 560.00 | | 0014 | 706-02-00200 | Concrete Drive (6" Thick) | 29 | SQYD | 110.00 | 3,190.00 | 78.31 | 2,270.99 | 205.00 | 5,945.00 | 90.00 | 2,610.00 | | 0015 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 238 | SQYD | 96.00 | 22,848.00 | 87.99 | 20,941.62 | 155.00 | 36,890.00 | 80.00 | 19,040.00 | | 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,820.00 | 6,820.00 | 16,164.11 | 16,164.11 | 10,000.00 | 10,000.00 | 26,000.00 | 26,000.00 | | 0017 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 8,500.00 | 850.00 | 10,570.30 | 1,057.03 | 1,200.00 | 120.00 | 4,000.00 | 400.00 | | 0018 | 717-01-00100 | Seeding | 2 | LB | 100.00 | 200.00 | 124.36 | 248.72 | 20.00 | 40.00 | 100.00 | 200.00 | | 0019 | 718-01-00100 | Fertilizer | 39 | LB | 5.00 | 195.00 | 6.22 | 242.58 | 2.00 | 78.00 | 3.00 | 117.00 | | 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 70,000.00 | 70,000.00 | 85,000.00 | 85,000.00 | 126,718.40 | 126,718.40 | 125,000.00 | 125,000.00 | | 0021 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 95.00 | 380.00 | 93.27 | 373.08 | 110.00 | 440.00 | 110.00 | 440.00 | | 0022 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 | 45,000.00 | 45,000.00 | 21,900.00 | 21,900.00 | 7,000.00 | 7,000.00 | | 0023 | 804-01-00300 | Precast Concrete Piles (16") | 1,800 | LNFT | 52.00 | 93,600.00 | 66.54 | 119,772.00 | 86.00 | 154,800.00 | 120.00 | 216,000.00 | | 0024 | 804-05-00300 | Precast Concrete Test Piles (16") | 1 | EACH | 60,000.00 | 60,000.00 | 25,000.00 | 25,000.00 | 8,200.00 | 8,200.00 | 16,000.00 | 16,000.00 | | 0025 | 804-09-00100 | Loading Test Piles | 1 | EACH | 14,000.00 | 14,000.00 | 14,093.52 | 14,093.52 | 11,350.00 | 11,350.00 | 2,000.00 | 2,000.00 | | 0026 | 804-10-00100 | Reloading Test Piles | 1 | EACH | 1.00 | 1.00 | 5,000.00 | 5,000.00 | 2,800.00 | 2,800.00 | 2,000.00 | 2,000.00 | | 0027 | 804-11-00100 | Redriving Test Piles | 1 | EACH | 1.00 | 1.00 | 5,000.00 | 5,000.00 | 1,400.00 | 1,400.00 | 2,000.00 | 2,000.00 | | 0028 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1.00 | 1.00 | 100.00 | 100.00 | 11,400.00 | 11,400.00 | 5,000.00 | 5,000.00 | | 0029 | 805-10-00100 | Bridge Superstructure and Substructure (30' CLR RDWY, 90 DEG CROSSING) | 5 | SPAN | 47,500.00 | 237,500.00 | 65,000.00 | 325,000.00 | 76,200.00 | 381,000.00 | 118,000.00 | 590,000.00 | | 0030 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 420 | INLF | 1.00 | 420.00 | 1.24 | 520.80 | 1.20 | 504.00 | 4.00 | 1,680.00 | | 0031 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 630 | INLF | 1.00 | 630.00 | 1.24 | 781.20 | 1.75 | 1,102.50 | 16.00 | 10,080.00 | | 0032 | NS-736-00120 | Construction Photographs And Video | 1 | LUMP | 19,970.00 | 19,970.00 | 4,290.56 | 4,290.56 | 9,800.00 | 9,800.00 | 21,000.00 | 21,000.00 | | 0033 | NS-800-00040 | Concrete Approach Slabs (30' CLR RDWY, 90 DEG CROSSING) (WITH TAPERED CONCRETE BARRIER RAILING) | 2 | EACH | 28,000.00 | 56,000.00 | 24,610.54 | 49,221.08 | 23,600.00 | 47,200.00 | 65,357.00 | 130,714.00 | | 0034 | NS-804-00001 | Vibration Monitoring (INCLUDING TEST PILE & INITIAL SURVEY) | 25 | EACH | 180.00 | 4,500.00 | 613.08 | 15,327.00 | 525.00 | 13,125.00 | 800.00 | 20,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 707,778.97 | | 889,969.59 | | 942,200.00 | | 1,341,420.40 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Thigpen Construction Co., Inc. | | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 50,000.00 | 50,000.00 | | 0002 | 202-02-04000 | Removal of Bridge (STA 6+75; 29.3.' X 99.85' TIMBER BRIDGE WITH ASPHALT) | 1 | EACH | 195,000.00 | 195,000.00 | | 0003 | 202-02-06000 | Removal of Concrete Approach Slabs | 95 | SQYD | 30.00 | 2,850.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 36 | SQYD | 25.00 | 900.00 | | 0005 | 202-02-38500 | Removal of Surfacing and Stabilized Base | 461 | SQYD | 20.00 | 9,220.00 | | 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 25,000.00 | 25,000.00 | | 0007 | 204-06-00100 | Temporary Silt Fencing | 358 | LNFT | 5.00 | 1,790.00 | | 0008 | 302-01-00800 | Class II Base Course (Stone or Recycled Portland Cement Concrete) | 113.9 | CUYD | 80.00 | 9,112.00 | | 0009 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 20 | CUYD | 60.00 | 1,200.00 | | 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 89.6 | TON | 350.00 | 31,360.00 | | 0011 | 702-04-00100 | Adjusting Manholes | 1 | EACH | 500.00 | 500.00 | | 0012 | 705-09-00100 | Rebuilt Fence | 50 | LNFT | 50.00 | 2,500.00 | | 0013 | 706-01-00100 | Concrete Walk (4" Thick) | 7 | SQYD | 150.00 | 1,050.00 | | 0014 | 706-02-00200 | Concrete Drive (6" Thick) | 29 | SQYD | 150.00 | 4,350.00 | | 0015 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 238 | SQYD | 100.00 | 23,800.00 | | 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | | 0017 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 1,000.00 | 100.00 | | 0018 | 717-01-00100 | Seeding | 2 | LB | 100.00 | 200.00 | | 0019 | 718-01-00100 | Fertilizer | 39 | LB | 20.00 | 780.00 | | 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 175,708.00 | 175,708.00 | | 0021 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 200.00 | 800.00 | | 0022 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | | 0023 | 804-01-00300 | Precast Concrete Piles (16") | 1,800 | LNFT | 120.00 | 216,000.00 | | 0024 | 804-05-00300 | Precast Concrete Test Piles (16") | 1 | EACH | 30,000.00 | 30,000.00 | | 0025 | 804-09-00100 | Loading Test Piles | 1 | EACH | 29,000.00 | 29,000.00 | | 0026 | 804-10-00100 | Reloading Test Piles | 1 | EACH | 1,000.00 | 1,000.00 | | 0027 | 804-11-00100 | Redriving Test Piles | 1 | EACH | 1,500.00 | 1,500.00 | | 0028 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1,500.00 | 1,500.00 | | 0029 | 805-10-00100 | Bridge Superstructure and Substructure (30' CLR RDWY, 90 DEG CROSSING) | 5 | SPAN | 95,000.00 | 475,000.00 | | 0030 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 420 | INLF | 3.00 | 1,260.00 | | 0031 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 630 | INLF | 4.00 | 2,520.00 | | 0032 | NS-736-00120 | Construction Photographs And Video | 1 | LUMP | 2,500.00 | 2,500.00 | | 0033 | NS-800-00040 | Concrete Approach Slabs (30' CLR RDWY, 90 DEG CROSSING) (WITH TAPERED CONCRETE BARRIER RAILING) | 2 | EACH | 50,000.00 | 100,000.00 | | 0034 | NS-804-00001 | Vibration Monitoring (INCLUDING TEST PILE & INITIAL SURVEY) | 25 | EACH | 500.00 | 12,500.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,479,000.00 |
|