Proposal:H.010484.6
Parish:Plaquemines
Description:Emergency dredging of Ostrica Locks and Canal
Type Construction:Perform emergency dredging operations and related work.
Estimated Construction Cost:$2,050,375.00
| Rank | License | Bidder | Construction Bid |
| 1 | 36894 | Coastal Dredging Company,Inc | $900,000.00 |
| 2 | 38908 | GRILLOT CONSTRUCTION LLC | $1,030,625.00 |
| 3 | 08768 | PROFESSIONAL CONST. SERVICES, INC. | $1,299,500.00 |
| 4 | 31943 | Hamp's Construction L.L.C. | $1,333,333.00 |
| 5 | 34582 | DREDGE AMERICA INC | $1,652,525.00 |
| 6 | 56385 | Orion Marine Construction, Inc. | $2,341,657.86 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Coastal Dredging Company,Inc | - 2 - GRILLOT CONSTRUCTION LLC | - 3 - PROFESSIONAL CONST. SERVICES, INC. | - 4 - Hamp's Construction L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 204-06-00100 | Temporary Silt Fencing | 5,000 | LNFT | 1.50 | 7,500.00 | 2.00 | 10,000.00 | 6.00 | 30,000.00 | 3.00 | 15,000.00 | | 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 167,500.00 | 167,500.00 | 200,000.00 | 200,000.00 | 187,000.00 | 187,000.00 | 130,120.00 | 130,120.00 | | 0003 | NS-MNT-90000 | Excavation | 175,000 | CUYD | 3.50 | 612,500.00 | 3.75 | 656,250.00 | 5.50 | 962,500.00 | 6.00 | 1,050,000.00 | | 0004 | NS-MNT-90001 | Survey Work | 1 | LUMP | 37,500.00 | 37,500.00 | 50,000.00 | 50,000.00 | 45,000.00 | 45,000.00 | 25,713.00 | 25,713.00 | | 0005 | NS-MNT-11901 | DIKE CONSTRUCTION | 7,500 | LF | 10.00 | 75,000.00 | 15.25 | 114,375.00 | 10.00 | 75,000.00 | 15.00 | 112,500.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 900,000.00 | | 1,030,625.00 | | 1,299,500.00 | | 1,333,333.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - DREDGE AMERICA INC | - 6 - Orion Marine Construction, Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 204-06-00100 | Temporary Silt Fencing | 5,000 | LNFT | 2.00 | 10,000.00 | 2.89 | 14,450.00 | | 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 400,000.00 | 400,000.00 | 233,961.82 | 233,961.82 | | 0003 | NS-MNT-90000 | Excavation | 175,000 | CUYD | 6.50 | 1,137,500.00 | 10.66 | 1,865,500.00 | | 0004 | NS-MNT-90001 | Survey Work | 1 | LUMP | 25,000.00 | 25,000.00 | 86,746.04 | 86,746.04 | | 0005 | NS-MNT-11901 | DIKE CONSTRUCTION | 7,500 | LF | 10.67 | 80,025.00 | 18.80 | 141,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,652,525.00 | | 2,341,657.86 |
|