Proposal:4400021551-R2
Parish:Vernon
Description:LEESVILLE EQUIPMENT STORAGE BUILDING - ROOF/BUILDING REPAIRS
Type Construction:
Estimated Construction Cost:$55,000.00
| Rank | License | Bidder | Construction Bid |
| 1 | 21023 | Pat Williams Construction, LLC | $83,963.00 |
| 2 | 49239 | WL Bass Construction Inc. | $90,707.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Pat Williams Construction, LLC | - 2 - WL Bass Construction Inc. |
| Unit Price | Total Amount | Unit Price | Total Amount |
| 0001 | NS-MNT-07020 | Building Repairs LEESVILLE EQUIPMENT STORAGE BUILDING-
ROOF/BUILDING REPAIRS | 1 | LUMP | 83,963.00 | 83,963.00 | 90,707.00 | 90,707.00 |
| | | | | | | | | |
| | | CONTRACTOR TOTAL | | | | 83,963.00 | | 90,707.00 |