Proposal:H.013907.6
Description:LA 546 CROSS DRAIN FAILURE
Type Construction:CROSS DRAIN REPLACEMENT
Estimated Construction Cost:$562,223.05
| Rank | License | Bidder | Construction Bid |
| 1 | 23112 | BEN ALLEN, INC. | $380,966.10 |
| 2 | 05789 | D & J CONSTRUCTION CO., LLC | $495,522.40 |
| 3 | 15099 | Amethyst Construction, Inc. | $496,782.40 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - BEN ALLEN, INC. | - 2 - D & J CONSTRUCTION CO., LLC | - 3 - Amethyst Construction, Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.23 | LUMP | 2,000.00 | 2,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 25,000.00 | 25,000.00 | | 0003 | 202-02-06020 | Removal of Concrete Box Culverts 5'x5'x35' RCB | 2 | EACH | 5,000.00 | 10,000.00 | 1,000.00 | 2,000.00 | 1,000.00 | 2,000.00 | | 0004 | 202-02-06040 | Removal of Concrete Box Headwall 5'x5' RCB | 2 | EACH | 3,000.00 | 6,000.00 | 1,000.00 | 2,000.00 | 1,000.00 | 2,000.00 | | 0005 | 203-02-00100 | Drainage Excavation | 66.6 | CUYD | 10.00 | 666.00 | 15.00 | 999.00 | 35.00 | 2,331.00 | | 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 444.4 | CUYD | 12.00 | 5,332.80 | 30.00 | 13,332.00 | 40.00 | 17,776.00 | | 0007 | 204-06-00100 | Temporary Silt Fencing | 600 | LNFT | 3.00 | 1,800.00 | 2.50 | 1,500.00 | 3.50 | 2,100.00 | | 0008 | 401-01-00100 | Aggregate Surface Course (Net Section) | 5.4 | CUYD | 100.00 | 540.00 | 250.00 | 1,350.00 | 200.00 | 1,080.00 | | 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 241.1 | SQYD | 130.00 | 31,343.00 | 200.00 | 48,220.00 | 130.00 | 31,343.00 | | 0010 | 701-01-01140 | Cross Drain Pipe (72" RCP) | 224 | LNFT | 316.00 | 70,784.00 | 500.00 | 112,000.00 | 375.00 | 84,000.00 | | 0011 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 56 | LNFT | 10.00 | 560.00 | 2.00 | 112.00 | 1.00 | 56.00 | | 0012 | 710-01-00100 | Flowable Fill | 242.7 | CUYD | 140.00 | 33,978.00 | 150.00 | 36,405.00 | 175.00 | 42,472.50 | | 0013 | 711-03-00500 | Riprap (130 lb) | 988.1 | TON | 80.00 | 79,048.00 | 90.00 | 88,929.00 | 60.00 | 59,286.00 | | 0014 | 711-04-00100 | Geotextile Fabric | 329.9 | SQYD | 3.00 | 989.70 | 2.00 | 659.80 | 2.00 | 659.80 | | 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 3,000.00 | 3,000.00 | 12,000.00 | 12,000.00 | 20,000.00 | 20,000.00 | | 0016 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 600 | LNFT | 2.00 | 1,200.00 | 2.00 | 1,200.00 | 2.50 | 1,500.00 | | 0017 | 714-01-00100 | Slab Sodding (Bermuda Grass) | 520.8 | SQYD | 5.00 | 2,604.00 | 7.00 | 3,645.60 | 9.00 | 4,687.20 | | 0018 | 724-01-00100 | Rumble Strips (Centerline) | 0.048 | MILE | 25,000.00 | 1,200.00 | 1,000.00 | 48.00 | 90,000.00 | 4,320.00 | | 0019 | 726-01-00100 | Bedding Material | 192.2 | CUYD | 98.00 | 18,835.60 | 100.00 | 19,220.00 | 92.00 | 17,682.40 | | 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 18,000.00 | 18,000.00 | 25,000.00 | 25,000.00 | 45,000.00 | 45,000.00 | | 0021 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | 100.00 | 400.00 | 100.00 | 400.00 | | 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 8 | EACH | 50.00 | 400.00 | 55.00 | 440.00 | 50.00 | 400.00 | | 0023 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 900 | LNFT | 2.00 | 1,800.00 | 2.00 | 1,800.00 | 1.50 | 1,350.00 | | 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.057 | MILE | 15,000.00 | 855.00 | 5,000.00 | 285.00 | 5,500.00 | 313.50 | | 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 2,000.00 | 2,000.00 | 1,500.00 | 1,500.00 | | 0026 | 805-01-00900 | Class A1 Concrete RCP Headwall | 62.74 | CUYD | 1,200.00 | 75,288.00 | 1,650.00 | 103,521.00 | 1,850.00 | 116,069.00 | | 0027 | 806-01-00100 | Deformed Reinforcing Steel | 4,228 | LB | 1.50 | 6,342.00 | 2.00 | 8,456.00 | 2.00 | 8,456.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 380,966.10 | | 495,522.40 | | 496,782.40 |
|