Proposal:H.012418.6
Parish:Lincoln
Description:LA 563 CULVERT FAILURE - INDUSTRY D05
Type Construction:REPLACE DAMAGED CULVERT, REPLACE EMBANKMENT AND REPLACE ROADWAY
Estimated Construction Cost:$124,675.74
| Rank | License | Bidder | Construction Bid |
| 1 | 39104 | RMK Construction Co., LLC | $99,575.00 |
| 2 | 15099 | Amethyst Construction, Inc. | $118,105.05 |
| 3 | 23112 | BEN ALLEN, INC. | $122,231.80 |
| 4 | 49239 | WL Bass Construction Inc. | $124,785.20 |
| 5 | 44640 | R.D. Owens Construction, Inc. | $134,416.85 |
| 6 | 54549 | Chad Pody Construction Company, LLC | $151,474.36 |
| 7 | 18546 | C W & W Contractors, Inc. | $177,570.20 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - RMK Construction Co., LLC | - 2 - Amethyst Construction, Inc. | - 3 - BEN ALLEN, INC. | - 4 - WL Bass Construction Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-32100 | Removal of Pipe (Cross Drain) DAMAGED CULVERT | 71 | LNFT | 10.00 | 710.00 | 25.00 | 1,775.00 | 100.00 | 7,100.00 | 100.00 | 7,100.00 | | 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 240 | CUYD | 6.00 | 1,440.00 | 26.00 | 6,240.00 | 12.00 | 2,880.00 | 25.00 | 6,000.00 | | 0003 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 90 | SQYD | 80.00 | 7,200.00 | 140.00 | 12,600.00 | 204.00 | 18,360.00 | 150.00 | 13,500.00 | | 0004 | 701-02-01140 | Cross Drain Pipe Arch (72" Equiv. RCPA) | 144 | LNFT | 350.00 | 50,400.00 | 305.00 | 43,920.00 | 375.00 | 54,000.00 | 355.00 | 51,120.00 | | 0005 | 701-15-00100 | Concrete Collar | 4 | EACH | 700.00 | 2,800.00 | 2,000.00 | 8,000.00 | 1,000.00 | 4,000.00 | 1,000.00 | 4,000.00 | | 0006 | 710-01-00100 | Flowable Fill | 165 | CUYD | 121.00 | 19,965.00 | 150.00 | 24,750.00 | 145.00 | 23,925.00 | 135.00 | 22,275.00 | | 0007 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 1,000.00 | 200.00 | 2,500.00 | 500.00 | 1,500.00 | 300.00 | 5,000.00 | 1,000.00 | | 0008 | 717-01-00100 | Seeding | 5 | LB | 25.00 | 125.00 | 10.00 | 50.00 | 25.00 | 125.00 | 50.00 | 250.00 | | 0009 | 718-01-00100 | Fertilizer | 73.4 | LB | 5.00 | 367.00 | 0.75 | 55.05 | 2.00 | 146.80 | 3.00 | 220.20 | | 0010 | 726-01-00100 | Bedding Material | 55 | CUYD | 95.00 | 5,225.00 | 105.00 | 5,775.00 | 95.00 | 5,225.00 | 130.00 | 7,150.00 | | 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 10,943.00 | 10,943.00 | 14,000.00 | 14,000.00 | 6,000.00 | 6,000.00 | 12,000.00 | 12,000.00 | | 0012 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 100.00 | 200.00 | 220.00 | 440.00 | 85.00 | 170.00 | 85.00 | 170.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 99,575.00 | | 118,105.05 | | 122,231.80 | | 124,785.20 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - R.D. Owens Construction, Inc. | - 6 - Chad Pody Construction Company, LLC | - 7 - C W & W Contractors, Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-32100 | Removal of Pipe (Cross Drain) DAMAGED CULVERT | 71 | LNFT | 140.85 | 10,000.35 | 160.00 | 11,360.00 | 50.00 | 3,550.00 | | 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 240 | CUYD | 16.00 | 3,840.00 | 20.00 | 4,800.00 | 25.00 | 6,000.00 | | 0003 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 90 | SQYD | 154.55 | 13,909.50 | 210.00 | 18,900.00 | 185.00 | 16,650.00 | | 0004 | 701-02-01140 | Cross Drain Pipe Arch (72" Equiv. RCPA) | 144 | LNFT | 400.00 | 57,600.00 | 457.63 | 65,898.72 | 675.00 | 97,200.00 | | 0005 | 701-15-00100 | Concrete Collar | 4 | EACH | 1,200.00 | 4,800.00 | 2,000.00 | 8,000.00 | 3,000.00 | 12,000.00 | | 0006 | 710-01-00100 | Flowable Fill | 165 | CUYD | 150.00 | 24,750.00 | 150.00 | 24,750.00 | 150.00 | 24,750.00 | | 0007 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 1,000.00 | 200.00 | 1,200.00 | 240.00 | 2,500.00 | 500.00 | | 0008 | 717-01-00100 | Seeding | 5 | LB | 10.00 | 50.00 | 35.00 | 175.00 | 50.00 | 250.00 | | 0009 | 718-01-00100 | Fertilizer | 73.4 | LB | 5.00 | 367.00 | 4.50 | 330.30 | 3.00 | 220.20 | | 0010 | 726-01-00100 | Bedding Material | 55 | CUYD | 120.00 | 6,600.00 | 50.00 | 2,750.00 | 150.00 | 8,250.00 | | 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 12,000.00 | 12,000.00 | 13,770.34 | 13,770.34 | 8,000.00 | 8,000.00 | | 0012 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 150.00 | 300.00 | 250.00 | 500.00 | 100.00 | 200.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 134,416.85 | | 151,474.36 | | 177,570.20 |
|