Proposal:H.016621.6
Parish:St. Martin
Routes:LA 92-1
Description:LA 92-1: CROSS DRAIN REPLACEMENT
Type Construction:REMOVE AND REPLACE CROSS DRAIN
Estimated Construction Cost:$849,443.76
| Rank | License | Bidder | Construction Bid |
| 1 | 67770 | Reliant Industrial Solutions L.L.C. | $645,592.36 |
| 2 | 46716 | BRUDD CONSTRUCTION CO., LLC | $721,047.41 |
| 3 | 33663 | Glenn Lege Construction LLC | $803,413.18 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Reliant Industrial Solutions L.L.C. | - 2 - BRUDD CONSTRUCTION CO., LLC | - 3 - Glenn Lege Construction LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.475 | LUMP | 10,000.00 | 10,000.00 | 9,000.00 | 9,000.00 | 32,825.00 | 32,825.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 13,000.00 | 13,000.00 | 7,374.00 | 7,374.00 | 21,664.50 | 21,664.50 | | 0003 | 203-02-00100 | Drainage Excavation | 49 | CUYD | 40.00 | 1,960.00 | 50.57 | 2,477.93 | 111.08 | 5,442.92 | | 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 60,000.00 | 60,000.00 | 40,000.00 | 40,000.00 | 26,916.50 | 26,916.50 | | 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 18 | EACH | 165.00 | 2,970.00 | 177.00 | 3,186.00 | 174.23 | 3,136.14 | | 0006 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 2.20 | 2,200.00 | 2.36 | 2,360.00 | 2.32 | 2,320.00 | | 0007 | 502-01-00100 | Asphalt Concrete | 141.6 | TON | 275.00 | 38,940.00 | 280.00 | 39,648.00 | 312.49 | 44,248.58 | | 0008 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 7 | TON | 385.00 | 2,695.00 | 413.00 | 2,891.00 | 370.27 | 2,591.89 | | 0009 | 509-01-00100 | Milling Asphalt Pavement | 1,331 | SQYD | 11.00 | 14,641.00 | 11.80 | 15,705.80 | 7.55 | 10,049.05 | | 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -74 | CUYD | 0.01 | -0.74 | 0.01 | -0.74 | 0.01 | -0.74 | | 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 900 | SQYD | 154.00 | 138,600.00 | 124.00 | 111,600.00 | 120.35 | 108,315.00 | | 0012 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 188 | LNFT | 100.00 | 18,800.00 | 185.00 | 34,780.00 | 152.56 | 28,681.28 | | 0013 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 96 | LNFT | 134.00 | 12,864.00 | 184.00 | 17,664.00 | 141.24 | 13,559.04 | | 0014 | 701-15-00100 | Concrete Collar | 1 | EACH | 1,200.00 | 1,200.00 | 1,585.00 | 1,585.00 | 1,247.35 | 1,247.35 | | 0015 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 70 | LNFT | 27.50 | 1,925.00 | 33.71 | 2,359.70 | 203.52 | 14,246.40 | | 0016 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 8,000.00 | 8,000.00 | 9,761.00 | 9,761.00 | 3,545.10 | 3,545.10 | | 0017 | 702-08-00100 | Side Drain Safety End (Type 1) | 2 | EACH | 5,700.00 | 11,400.00 | 5,235.00 | 10,470.00 | 3,479.45 | 6,958.90 | | 0018 | 702-08-00200 | Side Drain Safety End (Type 2) | 1 | EACH | 7,600.00 | 7,600.00 | 11,810.00 | 11,810.00 | 9,913.15 | 9,913.15 | | 0019 | 710-01-00100 | Flowable Fill | 165 | CUYD | 210.00 | 34,650.00 | 174.00 | 28,710.00 | 186.45 | 30,764.25 | | 0020 | 711-01-04020 | Riprap (55 lb, 24" Thick) | 70 | SQYD | 234.00 | 16,380.00 | 112.42 | 7,869.40 | 111.61 | 7,812.70 | | 0021 | 711-04-00100 | Geotextile Fabric | 70 | SQYD | 13.00 | 910.00 | 22.28 | 1,559.60 | 11.82 | 827.40 | | 0022 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 23,000.00 | 23,000.00 | 33,567.00 | 33,567.00 | 74,701.82 | 74,701.82 | | 0023 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.182 | MILE | 3,000.00 | 546.00 | 1,180.00 | 214.76 | 1,313.00 | 238.97 | | 0024 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.182 | MILE | 1,100.00 | 200.20 | 1,180.00 | 214.76 | 1,161.50 | 211.39 | | 0025 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.546 | MILE | 1,650.00 | 900.90 | 1,770.00 | 966.42 | 1,742.25 | 951.27 | | 0026 | 724-01-00100 | Rumble Strips (Centerline) | 0.09 | MILE | 550.00 | 49.50 | 1,770.00 | 159.30 | 1,742.25 | 156.80 | | 0027 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.18 | MILE | 550.00 | 99.00 | 1,770.00 | 318.60 | 1,742.25 | 313.61 | | 0028 | 726-01-00100 | Bedding Material | 86.2 | CUYD | 176.50 | 15,214.30 | 170.00 | 14,654.00 | 131.30 | 11,318.06 | | 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 83,000.00 | 83,000.00 | 146,399.50 | 146,399.50 | | 0030 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | 118.00 | 472.00 | 196.95 | 787.80 | | 0031 | 731-02-00100 | Reflectorized Raised Pavement Markers | 12 | EACH | 27.50 | 330.00 | 29.50 | 354.00 | 29.04 | 348.48 | | 0032 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.273 | MILE | 9,350.00 | 2,552.55 | 10,030.00 | 2,738.19 | 9,872.75 | 2,695.26 | | 0033 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.091 | MILE | 7,150.00 | 650.65 | 7,670.00 | 697.97 | 7,549.75 | 687.03 | | 0034 | 739-01-00100 | Hydro-Seeding | 1 | ACRE | 2,915.00 | 2,915.00 | 3,127.00 | 3,127.00 | 3,077.98 | 3,077.98 | | 0035 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 8,554.12 | 8,554.12 | 19,695.00 | 19,695.00 | | 0036 | 805-15-00700 | Reinforced Concrete Box Culverts (Precast) (6' x 5') | 70 | LNFT | 1,300.00 | 91,000.00 | 1,631.98 | 114,238.60 | 1,473.96 | 103,177.20 | | 0037 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall Deformed Reinforcing Steel: 1346.92 LB
Class AI Concrete: 19.43 CUYD | 2 | EACH | 24,500.00 | 49,000.00 | 48,480.00 | 96,960.00 | 31,794.30 | 63,588.60 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 645,592.36 | | 721,047.41 | | 803,413.18 |
|