Proposal:H.016807.6
Parish:Lafourche
Description:LA 304: LA 308 - LA 20
Type Construction:
Estimated Construction Cost:$350,859.00
| Rank | License | Bidder | Construction Bid |
| 1 | 62139 | Huey P. Stockstill, LLC | $381,133.50 |
| 2 | 00046 | Barber Bros. Contracting Co., L.L.C | $426,588.60 |
| 3 | 06276 | Barriere Construction Co., LLC | $523,749.49 |
| 4 | 74077 | TLP Construction Co. LLC | $568,808.77 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Huey P. Stockstill, LLC | - 2 - Barber Bros. Contracting Co., L.L.C | - 3 - Barriere Construction Co., LLC | - 4 - TLP Construction Co. LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06060 | Removal of Concrete Catch Basin | 1 | EACH | 2,000.00 | 2,000.00 | 3,000.00 | 3,000.00 | 4,250.00 | 4,250.00 | 2,000.00 | 2,000.00 | | 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" CMP | 32 | LNFT | 195.00 | 6,240.00 | 40.00 | 1,280.00 | 30.00 | 960.00 | 50.00 | 1,600.00 | | 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) 36" CMP | 40 | LNFT | 195.00 | 7,800.00 | 50.00 | 2,000.00 | 30.00 | 1,200.00 | 70.00 | 2,800.00 | | 0004 | 203-03-00100 | Embankment | 8 | CUYD | 650.00 | 5,200.00 | 120.00 | 960.00 | 750.00 | 6,000.00 | 200.00 | 1,600.00 | | 0005 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 963 | SQYD | 130.00 | 125,190.00 | 190.00 | 182,970.00 | 240.00 | 231,120.00 | 348.00 | 335,124.00 | | 0006 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 32 | LNFT | 625.00 | 20,000.00 | 550.00 | 17,600.00 | 485.00 | 15,520.00 | 300.00 | 9,600.00 | | 0007 | 701-01-01041 | Cross Drain Pipe (36" RCP) | 40 | LNFT | 725.00 | 29,000.00 | 750.00 | 30,000.00 | 520.00 | 20,800.00 | 350.00 | 14,000.00 | | 0008 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 72 | LNFT | 30.00 | 2,160.00 | 22.00 | 1,584.00 | 185.00 | 13,320.00 | 100.00 | 7,200.00 | | 0009 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 10,000.00 | 10,000.00 | 7,500.00 | 7,500.00 | 10,800.00 | 10,800.00 | 8,500.00 | 8,500.00 | | 0010 | 711-02-00300 | Riprap (30 lb) | 10.5 | CUYD | 500.00 | 5,250.00 | 650.00 | 6,825.00 | 610.00 | 6,405.00 | 800.00 | 8,400.00 | | 0011 | 711-04-00100 | Geotextile Fabric | 29.9 | SQYD | 30.00 | 897.00 | 4.00 | 119.60 | 4.00 | 119.60 | 50.00 | 1,495.00 | | 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 52,275.00 | 52,275.00 | 50,000.00 | 50,000.00 | 53,000.00 | 53,000.00 | 37,000.00 | 37,000.00 | | 0013 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.062 | MILE | 1,500.00 | 93.00 | 1,500.00 | 93.00 | 93.00 | 5.77 | 1,950.00 | 120.90 | | 0014 | 717-01-00100 | Seeding | 1 | LB | 55.00 | 55.00 | 500.00 | 500.00 | 255.00 | 255.00 | 120.00 | 120.00 | | 0015 | 718-01-00100 | Fertilizer | 10 | LB | 15.00 | 150.00 | 50.00 | 500.00 | 145.00 | 1,450.00 | 10.00 | 100.00 | | 0016 | 726-01-00100 | Bedding Material | 27.8 | CUYD | 195.00 | 5,421.00 | 145.00 | 4,031.00 | 145.00 | 4,031.00 | 380.00 | 10,564.00 | | 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 38,000.00 | 38,000.00 | 56,000.00 | 56,000.00 | 53,000.00 | 53,000.00 | 55,000.00 | 55,000.00 | | 0018 | 731-02-00100 | Reflectorized Raised Pavement Markers | 25 | EACH | 11.00 | 275.00 | 20.00 | 500.00 | 10.00 | 250.00 | 13.00 | 325.00 | | 0019 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 170 | LNFT | 3.25 | 552.50 | 4.00 | 680.00 | 3.00 | 510.00 | 4.00 | 680.00 | | 0020 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 92 | LNFT | 11.00 | 1,012.00 | 12.00 | 1,104.00 | 0.11 | 10.12 | 13.00 | 1,196.00 | | 0021 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 13.64 | MILE | 4,000.00 | 54,560.00 | 3,800.00 | 51,832.00 | 3,500.00 | 47,740.00 | 4,500.00 | 61,380.00 | | 0022 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.002 | MILE | 1,500.00 | 3.00 | 5,000.00 | 10.00 | 1,500.00 | 3.00 | 1,935.00 | 3.87 | | 0023 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 7,500.00 | 7,500.00 | 53,000.00 | 53,000.00 | 10,000.00 | 10,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 381,133.50 | | 426,588.60 | | 523,749.49 | | 568,808.77 |
|