Proposal:H.016483
Parish:Jefferson
Description:I-10 EB TO NEW ORLEANS BR. RAIL REPAIR
Type Construction:
Estimated Construction Cost:$81,600.00
| Rank | License | Bidder | Construction Bid |
| 1 | 56388 | Franklin Pavement Management, Inc. | $54,000.00 |
| 2 | 28190 | Buck Town Contractors & Co. | $57,700.00 |
| 3 | 48896 | Command Construction Industries LLC | $62,000.00 |
| 4 | 74077 | TLP Construction Co. LLC | $65,000.00 |
| 5 | 26435 | C.E.C., Inc. | $88,000.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Franklin Pavement Management, Inc. | - 2 - Buck Town Contractors & Co. | - 3 - Command Construction Industries LLC | - 4 - TLP Construction Co. LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 35,000.00 | 35,000.00 | 5,000.00 | 5,000.00 | | 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 | 4,700.00 | 4,700.00 | 6,000.00 | 6,000.00 | 5,000.00 | 5,000.00 | | 0003 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 3,000.00 | 3,000.00 | 1,000.00 | 1,000.00 | 2,000.00 | 2,000.00 | | 0004 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation | 20 | LNFT | 1,200.00 | 24,000.00 | 1,500.00 | 30,000.00 | 1,000.00 | 20,000.00 | 2,650.00 | 53,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 54,000.00 | | 57,700.00 | | 62,000.00 | | 65,000.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - C.E.C., Inc. | | Unit Price | Total Amount | | 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | | 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | | 0003 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | | 0004 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation | 20 | LNFT | 2,300.00 | 46,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 88,000.00 |
|