Proposal:H.014437.6
Parish:Orleans
Routes:I-10
Description:I-10 BRIDGE RAIL NEAR FRANKLIN
Type Construction:REMOVE AND REPLACE DAMAGED BRIDGE RAIL SECTION.
Estimated Construction Cost:$69,000.00
| Rank | License | Bidder | Construction Bid |
| 1 | 13782 | KELLY B. ESTES | $41,291.21 |
| 2 | 28190 | Buck Town Contractors & Co. | $49,990.00 |
| 3 | 67770 | Reliant Industrial Solutions L.L.C. | $58,550.00 |
| 4 | 57931 | KCR CONTRACTORS, LLC | $67,114.20 |
| 5 | 61575 | La Pequena Construction LLC | $95,000.00 |
| 6 | 02179 | Boh Bros. Construction Co., LLC. | $119,500.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - KELLY B. ESTES | - 2 - Buck Town Contractors & Co. | - 3 - Reliant Industrial Solutions L.L.C. | - 4 - KCR CONTRACTORS, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 3,000.00 | 3,000.00 | 15,500.00 | 15,500.00 | 18,000.00 | 18,000.00 | 22,435.20 | 22,435.20 | | 0002 | 713-11-00100 | Portable Changeable Message Signs | 1 | EACH | 1,000.00 | 1,000.00 | 400.00 | 400.00 | 1,000.00 | 1,000.00 | 3,360.00 | 3,360.00 | | 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 11,491.21 | 11,491.21 | 6,000.00 | 6,000.00 | 5,800.00 | 5,800.00 | 3,000.00 | 3,000.00 | | 0004 | 740-01-00100 | Construction Layout | 1 | LUMP | 500.00 | 500.00 | 90.00 | 90.00 | 750.00 | 750.00 | 1,200.00 | 1,200.00 | | 0005 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation | 20 | LNFT | 1,265.00 | 25,300.00 | 1,400.00 | 28,000.00 | 1,650.00 | 33,000.00 | 1,855.95 | 37,119.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 41,291.21 | | 49,990.00 | | 58,550.00 | | 67,114.20 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - La Pequena Construction LLC | - 6 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 22,000.00 | 22,000.00 | | 0002 | 713-11-00100 | Portable Changeable Message Signs | 1 | EACH | 10,000.00 | 10,000.00 | 1,500.00 | 1,500.00 | | 0003 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 | 11,500.00 | 11,500.00 | | 0004 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 6,500.00 | 6,500.00 | | 0005 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation | 20 | LNFT | 3,000.00 | 60,000.00 | 3,900.00 | 78,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 95,000.00 | | 119,500.00 |
|