Bid Tabulations
Letting of
10/09/2013
LA DOTD Headquarters
| Lead Project: H.010714.6 | |
| Parish: Ascension | |
| Routes: LA 22 | |
| Description: LA 22 Isaac ER Embankment Repair | |
| Type Const: GRADING, RIPRAP, SACKED CONCRETE REVETMENT AND RELATED WORK. | |
| Estimated Construction Cost: $595,500.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 49356 | Kort's Trucking Inc. | $678,000.00 |
| 2 | 39462 | Jb James Construction Llc | $769,750.00 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $872,000.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Kort's Trucking Inc. |
- 2 - Jb James Construction Llc |
- 3 - Coastal Bridge Co., L.L.C. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-40000 | Removal of Timber Piles | 50 | LNFT | 250.00 | 12,500.00 | 75.00 | 3,750.00 | 400.00 | 20,000.00 |
| 0002 | 203-01-00100 | General Excavation | 100 | CUYD | 100.00 | 10,000.00 | 100.00 | 10,000.00 | 100.00 | 10,000.00 |
| 0003 | 710-01-00100 | Flowable Fill | 30 | CUYD | 350.00 | 10,500.00 | 800.00 | 24,000.00 | 1,800.00 | 54,000.00 |
| 0004 | 711-02-00400 | Riprap (55 lb) | 600 | CUYD | 225.00 | 135,000.00 | 295.00 | 177,000.00 | 450.00 | 270,000.00 |
| 0005 | 711-04-00100 | Geotextile Fabric | 2,000 | SQYD | 3.00 | 6,000.00 | 2.50 | 5,000.00 | 13.00 | 26,000.00 |
| 0006 | 712-02-00100 | Sacked Concrete Revetment | 2,400 | SQYD | 85.00 | 204,000.00 | 160.00 | 384,000.00 | 155.00 | 372,000.00 |
| 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 150,000.00 | 150,000.00 | 90,000.00 | 90,000.00 | 50,000.00 | 50,000.00 |
| 0008 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 76,000.00 | 76,000.00 | 70,000.00 | 70,000.00 |
| CONTRACTOR TOTAL | 678,000.00 | 769,750.00 | 872,000.00 | |||||||