Bid Tabulations
Letting of
05/22/2013
LA DOTD Headquarters
| Lead Project: H.010635.6 | |
| Parish: St. John | |
| Routes: I-10 | |
| Description: I-10 RAISING ROADWAY | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,215,764.91 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $1,343,271.00 |
| 2 | 00481 | Coastal Bridge Co., L.L.C. | $1,470,176.80 |
| 3 | 00046 | Barber Bros. Contracting Co., L.L.C | $1,800,407.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Coastal Bridge Co., L.L.C. |
- 3 - Barber Bros. Contracting Co., L.L.C |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1.00 | 1.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 413 | LNFT | 10.00 | 4,130.00 | 15.00 | 6,195.00 | 10.00 | 4,130.00 |
| 0003 | 202-02-38300 | Removal of Sign and U-Channel Post | 2 | EACH | 10.00 | 20.00 | 10.00 | 20.00 | 20.00 | 40.00 |
| 0004 | 202-03-38000 | Relocation of Sign Relocation of signs which maybe in the way or need height adjustment | 12 | EACH | 800.00 | 9,600.00 | 800.00 | 9,600.00 | 1,000.00 | 12,000.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,300 | CUYD | 25.00 | 32,500.00 | 35.00 | 45,500.00 | 50.00 | 65,000.00 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 16 | EACH | 5.00 | 80.00 | 25.00 | 400.00 | 25.00 | 400.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 4,000 | LNFT | 1.00 | 4,000.00 | 2.00 | 8,000.00 | 2.00 | 8,000.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 9,830.4 | TON | 90.00 | 884,736.00 | 105.00 | 1,032,192.00 | 125.00 | 1,228,800.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 278.2 | TON | 90.00 | 25,038.00 | 125.00 | 34,775.00 | 175.00 | 48,685.00 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 2,145 | SQYD | 5.00 | 10,725.00 | 10.00 | 21,450.00 | 10.00 | 21,450.00 |
| 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -90 | CUYD | 1.00 | -90.00 | 0.01 | -0.90 | 0.00 | 0.00 |
| 0012 | 704-03-00100 | Blocked Out Guard Rail | 287.5 | LNFT | 22.00 | 6,325.00 | 17.00 | 4,887.50 | 30.00 | 8,625.00 |
| 0013 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 65.00 | 3,250.00 | 61.00 | 3,050.00 | 75.00 | 3,750.00 |
| 0014 | 704-11-00100 | Guard Rail End Treatment (Flared) | 2 | EACH | 2,000.00 | 4,000.00 | 2,100.00 | 4,200.00 | 3,000.00 | 6,000.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 132,000.00 | 132,000.00 | 75,000.00 | 75,000.00 | 100,000.00 | 100,000.00 |
| 0016 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 2,600 | LNFT | 0.10 | 260.00 | 0.35 | 910.00 | 0.40 | 1,040.00 |
| 0017 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 360 | LNFT | 0.10 | 36.00 | 1.00 | 360.00 | 0.50 | 180.00 |
| 0018 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.6 | MILE | 200.00 | 520.00 | 1.00 | 2.60 | 750.00 | 1,950.00 |
| 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 5.6 | MILE | 750.00 | 4,200.00 | 1.00 | 5.60 | 1,000.00 | 5,600.00 |
| 0020 | 717-01-00100 | Seeding | 45 | LB | 11.00 | 495.00 | 25.00 | 1,125.00 | 15.00 | 675.00 |
| 0021 | 718-01-00100 | Fertilizer | 1,500 | LB | 0.55 | 825.00 | 1.00 | 1,500.00 | 3.00 | 4,500.00 |
| 0022 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 7,250 | SQYD | 1.25 | 9,062.50 | 1.50 | 10,875.00 | 3.00 | 21,750.00 |
| 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 132,000.00 | 132,000.00 | 125,000.00 | 125,000.00 | 100,000.00 | 100,000.00 |
| 0024 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 82.00 | 164.00 | 75.00 | 150.00 | 120.00 | 240.00 |
| 0025 | 730-15-01000 | Relocate Light Poles Relocation of light poles which may be in the way or need height adjustment | 5 | EACH | 2,500.00 | 12,500.00 | 2,500.00 | 12,500.00 | 6,000.00 | 30,000.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 374 | EACH | 7.75 | 2,898.50 | 7.50 | 2,805.00 | 8.00 | 2,992.00 |
| 0027 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,300 | LNFT | 2.25 | 2,925.00 | 2.50 | 3,250.00 | 2.50 | 3,250.00 |
| 0028 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 180 | LNFT | 6.50 | 1,170.00 | 7.50 | 1,350.00 | 7.00 | 1,260.00 |
| 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.4 | MILE | 4,500.00 | 6,300.00 | 4,500.00 | 6,300.00 | 5,000.00 | 7,000.00 |
| 0030 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.65 | MILE | 1,100.00 | 715.00 | 1,500.00 | 975.00 | 1,200.00 | 780.00 |
| 0031 | 732-05-00100 | Removal of Existing Markings | 0.58 | MILE | 6,500.00 | 3,770.00 | 5,000.00 | 2,900.00 | 7,000.00 | 4,060.00 |
| 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 38,000.00 | 38,000.00 | 25,000.00 | 25,000.00 | 40,000.00 | 40,000.00 |
| 0033 | NS-602-00001 | Milling Concrete Pavement | 335 | SQYD | 5.00 | 1,675.00 | 20.00 | 6,700.00 | 50.00 | 16,750.00 |
| 0034 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 1,500.00 | 9,000.00 | 1,000.00 | 6,000.00 | 6,000.00 | 36,000.00 |
| 0035 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 1.1 | MILE | 400.00 | 440.00 | 2,000.00 | 2,200.00 | 5,000.00 | 5,500.00 |
| CONTRACTOR TOTAL | 1,343,271.00 | 1,470,176.80 | 1,800,407.00 | |||||||